A U.S. Department of Energy Office of Science Laboratory Operated by The University of Chicago Argonne National Laboratory Office of Science U.S. Department.

Slides:



Advertisements
Similar presentations
Rodd Pope, SLAC Undulator System October 12-13, 2006 FAC Meeting 1 Undulator System Assembly Plans Rodd Pope, SLAC.
Advertisements

Rodd Pope, SLAC Undulator System April 16-17, 2007 FAC Meeting 1 Undulator System Assembly, Installation, and Integration.
Stephen Milton Undulator System 12 October 2004 Undulator System Update Stephen Milton, ANL.
Trip Report on the visit to ICST of HIT, Harbin, China Derun Li Mike Green Steve Virostek Mike Zisman Lawrence Berkeley National Laboratory (from December.
FAC review, 10/27 D. Schultz 1 e-Beams System Update Injector System Installation has started. Linac System Preparing for ’06 installation. Controls System.
FAC, 10/12/06 D. Schultz 1 e-Beams Systems Update Linac Injector Undulator Production MMF commissioning ARR David Schultz.
Geoff Pile FAC Review - Undulator 12 November 2008 LCLS Undulator System Overview and Fabrication Geoff Pile.
A U.S. Department of Energy Office of Science Laboratory Operated by The University of Chicago Argonne National Laboratory Office of Science U.S. Department.
Marion M. White Undulator System 07 April 2005 LCLSLCLSLCLSLCLS Undulator System Tests Marion M. White ANL-ASD-LCLS.
LCLS Undulators October 14, 2004 Heinz-Dieter Nuhn, SLAC / SSRL MMF Review Introduction to the LCLS Undulators Heinz-Dieter Nuhn,
Geoff Pile FAC Review - Undulator 17 June 2008 LCLS Undulator System Status and Schedule Geoff Pile.
FAC, 4/16/07 D. Schultz 1 e-Beams Systems Update People ARR Linac Installation Undulator Production MMF Operations David Schultz.
M. White – June 28, 2004 LCLS Requirements Meeting In a project, we live or die by the schedule. After we’re “baselined” it is our plan for what we will.
A U.S. Department of Energy Office of Science Laboratory Operated by The University of Chicago Argonne National Laboratory Office of Science U.S. Department.
Marion White Magnets & Supports April 16, 2007 Undulator Magnets and Supports Status.
Robert Ruland Installation Alignment -Magnetic Measurements – Fiducialization April 7-8, 2005 FAC Meeting 1 Installation Alignment,
A U.S. Department of Energy Office of Science Laboratory Operated by The University of Chicago Argonne National Laboratory Office of Science U.S. Department.
D. Schultz FAC 6/17/08 1 e-Beams Systems Update People Progress the last review LTU and Dump Installation Status Undulator.
Stephen Milton Undulator System 20 April, 2006 LCLS Undulator System Update S. Milton, ANL FAC, April 20 th, 2006.
Rodd Pope, SLAC Undulator System April 20-21, 2006 FAC Meeting 1 Undulator System Assembly Plans Rodd Pope, SLAC In collaboration.
Linac Coherent Light Source Stanford Synchrotron Radiation Laboratory Stanford Linear Accelerator Center LCLS Undulator Physics.
Stephen Milton Undulator System 14 November, 2004 Undulator System Overview Stephen Milton.
ANL HWR Cryomodule Status Update 27 January 2015 Zachary Conway On behalf of the ANL Linac Development Group Argonne National Laboratory Physics Division.
Undulator System Review Closeout Erik Johnson, Kem Robinson, Dieter Walz 4 March 2004.
Marion M. White Undulator Prototype Status and 12 October 2004 LCLSLCLSLCLSLCLS Undulator Prototype Status and Measurement.
XFD – XF Engineering Group November 15-th, 2004LCLS Undulator Final Design Review1 Undulator for the LCLS project – from the prototype to the full scale.
Geoff Pile LCLS Und. System Fabrication FAC 29 th, 30 th & 31 st October 2007 LCLS Undulator System Fabrication Schedule FAC.
A U.S. Department of Energy Office of Science Laboratory Operated by The University of Chicago Argonne National Laboratory Office of Science U.S. Department.
A U.S. Department of Energy Office of Science Laboratory Operated by The University of Chicago Argonne National Laboratory Office of Science U.S. Department.
A U.S. Department of Energy Office of Science Laboratory Operated by The University of Chicago Argonne National Laboratory Office of Science U.S. Department.
A U.S. Department of Energy Office of Science Laboratory Operated by The University of Chicago Argonne National Laboratory Office of Science U.S. Department.
LSU 01/18/2005Project Life Cycle1 The Project Life Cycle Project Management Unit, Lecture 2.
From Research Prototype to Production
Marion M. White Undulator System 27 October FAC LCLSLCLSLCLSLCLS Progress on the Undulator Module System Test Marion M.
Cost Estimate Marion White (Argonne) SCU 3-Lab Review Meeting December 16, 2014.
Project Management Mark Palmer Cornell Laboratory for Accelerator-Based Sciences and Education.
THE PROJECT LIFE CYCLE PROJECT MANAGEMENT LIFE CYCLE LSU 01/18/2005 PROJECT LIFE CYCLE 1.
TOF Preliminary Design and Safety Review Project Management Controls R. L. Brown.
A U.S. Department of Energy Office of Science Laboratory Operated by The University of Chicago Argonne National Laboratory Office of Science U.S. Department.
A U.S. Department of Energy Office of Science Laboratory Operated by The University of Chicago Argonne National Laboratory Office of Science U.S. Department.
Procurement and Manufacture of LCLS Undulators FY 04 Activity: Complete design of Second Prototype Undulator This will include field control comb Procure.
Finance Roy Preece STFC RAL Oversight Committee Meeting 27 th November 2015.
Proposed LCLS-II SCU Schedule Soren Prestemon (LBNL) SCU 3-Lab Review Meeting December 16, 2014.
O. Kester, NuSTAR annual meeting, 27/02/2013
Rob Connatser NSS Instrument Work Packages and XLPM.
Jan , 2008 LCLS Undulator Week Dean R. Walters 1 Vacuum Components Undulator System SH Lee, J Morgan, and D Walters.
Cost and Schedule Paul Weinman Pacific Northwest National Laboratory.
Jim Fast Pacific Northwest National Laboratory
Reconstruction site Investigation, Planning, Scheduling, Estimating and Design Eng. Fahmi Tarazi.
EDR HLRF Work Packages Draft Summary
DOE: Transition from MIE to Early Operations Kevin Reil LSST Camera Commissioning Lead LSST Commissioning Plan Review January 24-26, 2017.
Linac Coherent Light Source Procurement
Undulator Scope, Management, and Organization
Electron Beam Systems ETC and Methodology
Undulator Cost & Schedule Patric Den Hartog, ANL April 24, 2002
Undulator Tuning Status Heinz-Dieter Nuhn, SLAC / LCLS for Zack Wolf, Yurii Levashov, Achim Weidemann, Seva Kaplounenko, Scott Jansson, Ralph Colon, Dave.
LCLS Undulator System Status and Schedule
LCLS Undulator System Production Management
Undulator Scope, Management, Organization
Heinz-Dieter Nuhn – LCLS Undulator Group Leader May 14, 2009
E-Beams Systems Manager
LCLS Vacuum System Plans (July 07)
LCLS Undulator System Status and Schedule
Undulator Long-Lead Procurement Preparation
Undulator System Overview
Undulator Integration Test Status
Electron Beam Systems ETC and Methodology
Undulator Assembly and Installation Planning
Undulator and Magnet Production Status 25 October 2006
SNS-PPU upgrades the existing accelerator structure
Presentation transcript:

A U.S. Department of Energy Office of Science Laboratory Operated by The University of Chicago Argonne National Laboratory Office of Science U.S. Department of Energy Undulator Magnet Systems Scope/Plan/Schedule/Cost Marion M. White APS-ASD

Pioneering Science and Technology Office of Science U.S. Department of Energy 2 Scope – Undulator Systems 33 Precision magnetic arrays with canted poles 33 Support/alignment systems including: -Cradle that supports the undulator, BPM, and quadrupole magnet. -Precision CAM movers and motors enabling positioning, alignment, and adjustment of the cradle. -Rail system to move the undulator, facilitating manual retraction of an undulator out of the beamline and precision reproducible re-insertion. 7 Spare Undulator Systems 1 Undulator Transport Device for Installation

Pioneering Science and Technology Office of Science U.S. Department of Energy 3 Scope - Undulator Module Magnet Assembly BPM Quadrupole Rails CAM Movers Cradle

Pioneering Science and Technology Office of Science U.S. Department of Energy 4 Scope – Undulator Spares 7 spare undulator units -4 complete modules -- assembled, together with BPM and quadrupole, aligned, fiducialized, and stored in a temperature-controlled environment. - 3 modules are ready for installation at any time. - 1 is a reference module, maintained in a thermally stable environment and used for long-term stability monitoring. -3 include just the undulator and support systems, no quadrupole or BPM; not final assembled.

Pioneering Science and Technology Office of Science U.S. Department of Energy 5 Plan – Undulators (1) To meet schedule and funding profiles, and to ensure that the Undulator Systems are complete by July 2007, we plan to procure the following long-lead items as early as possible in FY05: - Precision-machined titanium strongbacks - Magnet blocks - Magnet poles The same APS undulator experts, who were relied upon for design, construction, and assessment of the prototype, will finalize procurement packages for the LL items, in accordance with our Advance Procurement Plans [APP].

Pioneering Science and Technology Office of Science U.S. Department of Energy 6 Plan – Undulators (2) Undulator magnet and support fabrication and assembly contracts will be awarded as early as possible in 2006, to at most two pre-qualified vendors who are competent in precision mechanical fabrication and assembly. -Awarding a 1 st article undulator [per vendor] in late 2005 reduces the undulator schedule risk significantly, but advances the funding needs. -FY05 1 st article undulators are not in the current baseline and funding plan.

Pioneering Science and Technology Office of Science U.S. Department of Energy 7 Plan – Undulators (3) Responsibility for vendor management and vendor performance oversight rests with ANL-APS. Periodic travel is required during the procurement and production phases for vendor pre-qualification, QA, process monitoring, and acceptance testing. Undulator assembly vendors will be furnished with all “travelers” from the long lead-item production, and they will provide complete undulator documentation, information, and production travelers. Relevant data will be reviewed prior to “permission to ship.”

Pioneering Science and Technology Office of Science U.S. Department of Energy 8 Plan – Undulators (4) The first two assembled undulators are: -Factory accepted at the vendor(s) and shipped to ANL -Tuned and measured (magnetic & mechanical) at ANL -Accepted officially by ANL -Shipped to SLAC -Re-measured at the MMF -Fiducialized -Assembled together with - Measured and fiducialized quadrupole, - Calibrated, cleaned, baked, and fiducialized BPM, - Cleaned, baked, and aligned vacuum chamber

Pioneering Science and Technology Office of Science U.S. Department of Energy 9 Plan – Undulators (5) The first two assembled undulators (cont’d.): -The complete undulator module undergoes final alignment and is - -Declared Ready for Installation -It’s then either installed, or, if the building is not deemed an undulatorially-safe environment at the time, it is carefully transported to a long-term, temperature- and humidity-controlled storage area.

Pioneering Science and Technology Office of Science U.S. Department of Energy 10 Plan – Undulators (6) All subsequent undulators are shipped directly to SLAC for tuning, measurement, fiducialization, final assembly, etc. Some ANL-APS effort is associated with the SLAC activities, in a “Lead, Mentor, Consult” role. - Lead – ANL leads the effort; SLAC personnel observe/participate. - Mentor – SLAC leads the effort – ANL observes. - Consult –ANL personnel are available for questions, troubleshooting, brainstorming.

Pioneering Science and Technology Office of Science U.S. Department of Energy 11 Plan – Undulators (7) Details of the interfaces between undulator modules and other systems will be documented with ICDs [Interface Control Documents] agreed upon by all relevant parties. Acceptance criteria will be clearly documented. APPs are in preparation at this time.

Pioneering Science and Technology Office of Science U.S. Department of Energy 12 Schedule – Undulators Risks are decreased by having already constructed a prototype -and by early procurement of long-lead items. Advancing 1 st article undulators to later in FY05 would further decrease schedule risks. All undulators are to be delivered to SLAC by end of March 2007, consistent with completion in July end of the talk – continues to be refined.

Pioneering Science and Technology Office of Science U.S. Department of Energy 13 Cost – Undulators Costs for the long lead items are based on vendor quotes. Details were presented by Den Hartog in the May 2003 DOE review. Fabrication and Assembly costs are based on the cost to create the prototype, with additional money added for profit. The resulting number was cross- checked against actual costs for APS undulators, decreased to account for non-moving jaws, and increased to account for greater length. Cost estimate refinement continues.

Pioneering Science and Technology Office of Science U.S. Department of Energy 14 Scope – Quadrupole Magnet Systems 34 Quadrupole Magnet Systems - installed -Permanent Magnet Quadrupole -Support with Precision Translator [manually settable to 5 um; readout to 1um] 4 Spare Magnet Systems Separate steering is not included

Pioneering Science and Technology Office of Science U.S. Department of Energy 15 Plan – Quadrupole Magnet Systems (1) The permanent-magnet quadrupoles, including supports and translators, will be procured from and designed by a vendor per our physics, engineering, and magnet quality specifications. Procurement packages will be prepared by experienced ANL-APS personnel according to an APP.

Pioneering Science and Technology Office of Science U.S. Department of Energy 16 Plan - Quadrupole Magnet Systems (2) Responsibility for vendor management and vendor performance oversight rests with ANL-APS. Periodic travel is required during the procurement and production phases for vendor pre-qualification, QA, process monitoring, and acceptance testing. The vendor will provide LCLS with complete documentation, information, and travelers from the production. Relevant data will be reviewed prior to “permission to ship.”

Pioneering Science and Technology Office of Science U.S. Department of Energy 17 Schedule – Quadrupole Magnet Systems Quadrupole magnet production will be awarded in FY06. The 1st article will be measured at ANL. Subsequent magnets are delivered to the SLAC MMF, measured, and fiducialized in time for undulator assembly and alignment. - Awarding a 1 st article quadrupole assembly late in FY05 would reduce schedule risk, in that a 1 st article could be more fully investigated prior to beginning the production run.

Pioneering Science and Technology Office of Science U.S. Department of Energy 18 Schedule Level 4 Roll-up schedule (1)

Pioneering Science and Technology Office of Science U.S. Department of Energy 19 Level 4 Roll-up schedule (2)

Pioneering Science and Technology Office of Science U.S. Department of Energy 20 Milestone (1) 6/22/06 Oops

Pioneering Science and Technology Office of Science U.S. Department of Energy 21 Milestone (2)

Pioneering Science and Technology Office of Science U.S. Department of Energy 22 Milestone (3)

Pioneering Science and Technology Office of Science U.S. Department of Energy 23 Milestone (4)

Pioneering Science and Technology Office of Science U.S. Department of Energy 24 Milestone (5)

Pioneering Science and Technology Office of Science U.S. Department of Energy 25 Milestone (6)

Pioneering Science and Technology Office of Science U.S. Department of Energy 26 Milestone (8) The Magnet Measurement, Fiducialization, and Alignment detailed schedule is shown in Robert Ruland’s talk.

Pioneering Science and Technology Office of Science U.S. Department of Energy 27 Milestone (9)

Pioneering Science and Technology Office of Science U.S. Department of Energy 28 Summary Significant effort has been devoted to planning, resulting in a detailed undulator construction schedule that is integrated with the BPM, quadrupole and vacuum chamber construction and testing. The undulator schedule and the magnet measurement schedule are mostly integrated, and are consistent with completion of undulator systems in July A skeleton installation schedule exists; details are being added and integration with the rest of the schedule is ongoing. Schedule refinement is ongoing. Costs were estimated by in-house experts with relevant experience and were based on vendor quotes and previous experience. Cost scrubbing will continue. The greatest schedule risks come from: -Design changes -Delayed funding