1 MICE phase I - Project Status Richard Apsimon (Project Manager) & Andy Nichols (Technical Coordinator) … with considerable help from Ken Long! MICE Video.

Slides:



Advertisements
Similar presentations
1 Update on project management for MICE Project Status and schedule Richard Apsimon MICE CMPB 5 th Nov 2007.
Advertisements

1 UK Project Alan Grant, STFC. Finance How savings are made Update on stepIV position Milestones Critical Path - stepIV Concerns 2.
Project Managers Update Roy Preece Particle Physics Department, STFC MICE Video Conference, 18 th September 2014.
1 MICE CM31 Key schedule drivers for Step IV Schedule table Milestone summary Comment on Step V Step VI Andy Nichols, STFC, 3/11/11.
MOM Report Ray Gamet MICE Operations Manager University of Liverpool MICO 18 th May 2009.
MICE Superconducting Solenoids: Status and Update RAL: T W Bradshaw M Courthold J Rochford M Hills D Baynham Oxford: J Cobb W Lau S Yang MICE.
1 MICE Video Conference Installations to date Future installation work Plans for May shutdown MICO organisation Use of Technical Board.
Step IV Infrastructure update STFC Tim Hayler Eddie Holtom Norbert Collomb Graham Stokes 14 th December 2011 MICO170 meeting 1Tim Hayler.
MICE Collaboration meeting May 31 st – June 3 rd 2009 RAL Tim Hayler, Andy Lintern DRAFT SEQUENCE OF EVENTS STEPS
MOM Report Paul Soler MICE Operations Manager University of Glasgow MICO April 27, 2009.
MOM Report Paul Soler MICE Operations Manager University of Glasgow MICO April 20, 2009.
MICE: Hall Infrastructure Chris Nelson CEng CM16 8 th Oct 2006.
1 MICE PM Report General Update –Phase I civil engineering –R5.2 in June –Phase II design work –Phase II hardware –A few questions –Schedule, milestones.
Project Report Paul Drumm CM15, FNAL June MICE Schedule Overview First beam September/October 2007 –Shutdown from January 2007 –Eight months for.
MICE FAC Alain Blondel 7 October   MICE The International Muon Ionization Cooling Experiment MICE CM19.
1 Project Manager Report Andy Nichols, STFC – RAL MICE Collaboration Meeting, Harbin, 13-17th January 2009.
MOM Report Ray Gamet MICE Operations Manager University of Liverpool MICO 11 th May 2009.
1 MICE PM Report Installations to date Future installation work Preparations for Phase Two Target status MICE Video Conference, 22nd May, 2008.
MOM Report Paul Soler MICE Operations Manager University of Glasgow MICO May 5, 2009.
1 Status of infrastructure MICE Video Conference, August 17, 2005 Yury Ivanyushenkov Applied Science Division, Engineering and Instrumentation Department.
CMPB Alain Blondel 14 April STATUS OF MICE.
Spectrometer Solenoid Update Michael S. Zisman Center for Beam Physics Accelerator & Fusion Research Division Lawrence Berkeley National Laboratory MICO.
Update Hardware for conductive cooling of the quench resistors has been fabricated at LBNL. Preparation for installation to start this week. Installation.
1 MICE Magnets Contents: Background Refurbishment Testing Installation & survey Current status Upstream beamline Open issues & concerns MICE Beamline Review,
1 Summary of MICE beamline & hall installations This is a very rough summary of the progress since mid-December Richard Apsimon & Andy Nichols MICO meeting.
1 Project Manager Report Andy Nichols, STFC MICE Collaboration Meeting, RAL, June 2009.
MICE - UK Project Progress Roy Preece 30 th April 2013.
1 MICE PM Report Phase One installations to date Phase One remaining items Progress with Phase Two Phase Two planning sequence Worries Don’t have time.
1 MICE Video Coference Project Manager Report Contents: Technical organisation of project Target and upstream beamline Muon beamline Infrastructure and.
ILCTA_NML Progress at Fermilab Jerry Leibfritz September 10, 2007.
Project report. Status: MICE Muon Beam Target: –Target presently installed ‘in-operative’: Optical connections removed (why?) –Implies realignment/set-up.
1 Hall & Beamline Installation Richard Apsimon, Andy Nichols, Willie Spensley MICE Collaboration Meeting, th Feb 2008.
1 Technical Co-ordination, Phase One The shared post of PM/TC has worked quite well Six months ago there was much for us to learn:  Revised the WBS 
1 MICE - INFRASTRUCTURE MICO meeting 7 th February 2008 Tim Hayler.
MICE: overview K. Long, 18 March, Contents ► Introduction ► Beam line ► Infrastructure ► MICE steps ► Phase II (comment) ► Conclusions.
Infrastructure Update As at 11 th March 2009 Remaining four plates now fitted to North shield wall North & South walls and all galleries are considered.
MICE status. Mice layout Beam line elements (including channel magnets) Detector components Civil Engineering Software target Decay Solenoid Beam Stop.
1 UK PM Report Costs & Schedule Alan Grant, STFC.
1 MICE PM Report Completion of Infrastructure Target, solenoids Phase Two planning & schedule Non-MICE costs Staffing & visitors Don’t have time for a.
K. Long, 10 October 2015 Project Manager’s report Status/progress since CM18 Looking forward Organisation Conclusions.
Preparations in the MICE hall Video Conference 25 th June 09 Tim Hayler Andy Lintern Peter Lau Geoff Barber.
The status of the construction of MICE Step IV K. Long, on behalf of the MICE collaboration.
Schedule and Work We are moving into a very intensive 4 months with a lot of work to be carried out Electrical services to the devices – after the South.
1 Project Manager Report Andy Nichols, STFC – RAL MICE Collaboration Meeting, DL, 4 th -7 th June 2008.
1M. Ellis - MICE VC - 1st November 2007 Cosmic Ray Test Preparations  The cosmic ray test was initially planned to be held in R12, but this proved to.
Status of the MICE Project & Dashboard MICE Project Board 14 th November 2013 Roy Preece.
1 MICE Hall construction status Richard Apsimon MICE VC meeting 29th Nov 2007.
Target Status CM19 RAL October 2007 P J Smith – University of Sheffield.
MICE FAC Alain Blondel 21 september   MICE The International Muon Ionization Cooling Experiment BRIEF STATUS OF MICE.
1 MICE Hall and Infrastructure - Progress since CM18 Chris Nelson MICE CM19 Oct 2007.
MICE Status & Plans MICE-UK paul drumm 15 th September 2004.
1 MICE PM Report Summary since CM21 Decay solenoid Infrastructure progress Step One Installation Worries MICE Video Conference, 19 th June, 2008.
Spectrometer Solenoid Schedule MICE Schedule Review May 23 rd 2011 Roy Preece (STFC RAL, LBNL)
1 MICE Beamline Installation, status & plans Contents: Upstream & Target, BPM Decay solenoid DSA, D2, Q4,5,6 cKOV support Q7,8,9 Open issues & concerns.
MICE Oversight Committee Meeting RAL, 24 April 2014 Paul Soler on behalf of the MICE Collaboration Status of MICE and Spectrometer Solenoids.
MICE Project Report Alan Bross (for Paul Drumm). Project Issues ● Key dates: – ISIS Synchrotron start-up scheduled for 1st August ● Shielded area around.
CM27 – 8 th July 2010 LH2 System Progress and Future Plans M Hills T Bradshaw M Courthold I Mullacrane P Warburton.
OsC mtg 24/4/2014 OsC mtg Alan Grant. 2 OsC mtg 24/4/ MICE Finances - Forward Look.
1 MICE PM Report General Update –Phase I nearing completion –MICE Power –Actions for Decay solenoid & target –Follow-ups from last VC –Conclusions MICE.
1 Project Infrastructure for steps I-III Tim Hayler, STFC – RAL MICE Collaboration Meeting, RAL, nd October 2008.
Malcolm Ellis – Brunel University – 8th April The International Muon Ionization Cooling Experiment.
OsC mtg 15/10/2014 MICE Step IV Alan Grant. Content Step IV – Construction Status – Finances – Schedule – Risks – Summary 2.
Tuesday 9 th January Project Status Report Project Achievements Project Schedule Issues Finance Summary Risk Register Photos.
1 MICE PM Report Phase One installations to date Phase One remaining items Progress with Phase Two Worries Don’t have time for a detailed status report,
What do we want to achieve in this running period? Michael S. Zisman Deputy Spokesmouse Center for Beam Physics Lawrence Berkeley National Laboratory MICO.
ILCTA_NML Progress at Fermilab Jerry Leibfritz August 16, 2007.
US Construction Project: SSs, PRY, Cavities and test program 1.
MICE CM31 Schedule summary
MICE PM Report Progress with the Infrastructure A few problems
Presentation transcript:

1 MICE phase I - Project Status Richard Apsimon (Project Manager) & Andy Nichols (Technical Coordinator) … with considerable help from Ken Long! MICE Video Conference 1 st Nov 2007

2 Contents 1.MICE WBS 2.MICE target news 3.Upstream beamline 4.DSA & the Decay Solenoid 5.Linde refrigeration installation & commissioning 6.Q35 Refurbishment, testing & installation 7.MICE LCR 8.Other issues

3 MICE WBS

4 Weekly MICE Hall planning meetings. Essentially a 2 week look-ahead Weekly MICE Schedule planning meetings, concentrating On the longer term plus planning for the forthcoming weekend

5 MICE Target Past problems with bearing wear. Now using DLC (Diamond Like Carbon or Diamolith). It is a “Plasma Enhanced Chemical Vapour Deposition” (PECVD) process that deposits a material layer that is about 3-5um thick. At present only got one, top bearing, DLC coated and the target shaft. >2M operations without wear

6 MICE Target Problems that we needed to solve for target installation into ISIS: –Removal of the old target. Need to demonstrate procedure Can we use short Nov. shutdown? –Approval to put the new target into ISIS. YES! MICE procedure accepted by ISIS –Some conditions –Infrastructure ready for target in ISIS. Two targets needed, test vessel, remote handling, fibre optics, control cables. Bottom bearings need coating

7 Target: schedule:

8 Target: schedule continued: Now planned with DL controls group: needs to be updated.

9 Upstream beamline Require to complete/install: –Alignment PROBLEM – need to lower magnet stands –Vacuum vessels PROBLEM with Dipole 1 –Need to move vacuum box –Services: Vacuum Water Electrical –Agreement with M.Krendler (ISIS): –Milestone (deadline) for completion of above 20Jan08: the end of the Christmas shutdown Working with individuals to complete as much as possible before ‘minor maintenance’ period –Next three/four weeks Next opportunity November ‘minor maintenance’ –But most people at the limit of their annual dose. We should get the supplies connected.

10 Upstream beam line: power supplies: Rack being installed now: –Required removal of ‘treads’ of north-east stair case Power-supply units and cabling to follow

11 Upstream beam line: Xmas work

12 DSA (Decay Solenoid Area) June: Hole to synchrotron vault, North wall in place October: Shielding to synchrotron, W & S walls of iron & concrete built. PPS doors installed. Plinth built, additional shielding on plinth, wall painted. Dipole 2 installed, downstream Q35 baseplate in position.

13 View over DSA into MICE Hall June: Most of Hall cleared, some shielding October: Decay Solenoid Area civil engineering almost complete. Roof still to be designed & fitted. Can we remove North Wall? On-going discussions. Looks possible if we can replace sandbags with steel shot. More news from Willie & Andy?

14 Delay Solenoid So far, major leak has been found and repaired BUT at the cost of considerable damage to MLI. Need 2? weeks of skilled effort. Matt is developing a plan to complete this task. Cold mass still to be aligned and tie rods re-tensioned

15 Linde cryogenics After DSA completed, support installed for buffer tank, below which is control plant. Transfer line carries cold helium gas to and from either ‘Test Cap’ or decay solenoid

16 Linde cryogenics Helium transfer line installed and connected to ‘Test Cap’. Most of the scaffolding now removed. After cool-down and other tests, transfer line will be connected to PSI Decay Solenoid Installation completed ahead of schedule Commissioning started and hope to finish 25 th or even 18 th Nov.

17 Linde Schedule as of 9 th Oct

18 Q35 Refurbishment & Installation First 3 magnets finished this week. Test in R6. One technician has left. Replacement being sought. Need to increase # people with crane licences –Trial assembly of magnet support on baseplate complete –Upstream baseplate (Q4-Q6) in DSA has been aligned & levelled (grouted today?) –Downstream plate ready with all components

19 Down-stream beam-line: Quadrupole triplets: –First quad triplet refurbished: Magnetic testing to start next week –Trial build of quad stand complete Quadrupole triplets cont.: –Refurbishment of remaining quads: Goal: complete by 20Jan08 –Services being installed now

20 Q35 refurbishment: schedule: Focus on Q35 work has paid off, but: –Magnetic testing will start 01Nov07: Developing schedule with Paul Flower now he has returned from CERN –Have had one more coil failure: potential issue: Have expedited testing of remaining coils Continuing refurbishment –Need to consider options when it is known if any more coils have failed

21 MICE Local Control Room (MLCR) Rack bases delivered DPM & floor screed completed Network rack delivered this week? PPS rack, populated and tested DL) also delivered this week? Remaining racks the following week. Air conditioning and power to start soon. –Estimated to take three weeks so complete by 9th November. Roof has been fitted & plastered this week Network connection cabling installed. –Connection to RAL site to start as soon as the racks have been delivered from DL. –A wireless access point to be set up as soon as possible. Further wiring into the hall to follow. –Too much civil still going on to start too early.

22 MLCR timescale

23 Reviews: beam line

24 Spectrometer and instrumentation: Spectrometer solenoid: –First spectrometer solenoid: Coils almost complete Expect delivery to FNAL for magnetic field mapping in December –Second spectrometer solenoid: Fabrication advanced Expect delivery ~2 months after first CKov: –Two modules: Most of the first (CKova) at RAL Second module under construction in Mississippi TOF: –TOF0 and TOF1 under construction in Milan: Expected at RAL 15 th November for cosmic ray tests Calorimeter: –Pre-sampler (KL): under construction in Rome Expected at RAL 15 th November for cosmic ray tests –Sandwich calorimeter: Design complete, prototype under construction

25 First full tracker being manufactured: –Final step in QA chain (station acceptance rig) now in full production mode –Space frame being built –Support frame in manufacture Electronics: –Being prepared for shipping in FNAL –Will be shipped this week or next week Spectrometer and instrumentation: continued

26 Cosmic-ray integration test: Will start 12Nov07: –Will include: CKov, Tracker, ToF, and KL (pre- sampler)

27 Other Issues Xmas shutdown –Well planned, WBS manager (Tim Hayler) –Already VERY tight. Every other task that is delayed now moves into this schedule. False floor and plinth in main hall –False floor should be completed in time for decay solenoid to move for cool-down tests Other news –Water chiller order placed. –Rolling platform FDR completed, PRR due. –Magnetic shield. South wall drgs. complete. North wall, design almost complete. Aim to have contracts placed well before end of this FY. –Quotes for “Cyclotron steel” being sought

28 Phase I instrumentation: Cosmic integration test: will start 12Nov07 –Craig MacWaters coordinating test Will use R8: –3-phase, water, etc. being planned »Unforeseen expense (likely small, but being estimated) –Components: Tracker: –Station acceptance QA rig now running at Imperial »Station ‘5’ (first final station) has been QAed: results OK; »Decide today 15:30(?): proceed with QA or more studies required on station 5 –Space frame in manufacture –Cosmic stand signed off for manufacture (?) TOF: –Expected to arrive 15Nov07 KL: –Expected to arrive 15Nov07 CKova –Already at RAL, needs to be assembled DAQ –Already at RAL, needs to be moved to R8

29 Cooling channel components: RFCC module: –CC design and fabrication done in collaboration by LBNL and ICST in Harbin, China conductor ready to order –RF cavities will be similar to existing MuCool prototype fabrication to get under way shortly –MuCool 201 MHz cavity R&D: Without field now have 19 MV/M

30 Cooling channel components: AFC module: Focus coil module presently out for tender –anticipate contract award in September 2007 –two coils that can run with same or opposite polarity »20-L LH 2 absorber (plus safety windows) fits inside Oxford, RAL, KEK

31 Current concerns Preparation of –The PSI solenoid –MICE target –Upstream beamline Is the misalignment critical? Can it be solved in time? –Connection of upstream & downstream beamline components Radiation surveys –Many areas where these matter; Target removal Connection of magnets in synchrotron vault Work inside DSA – removal of North wall Excavation of earth for H2 vents and pumps