PALM-3000 Management Update A. Bouchez Team Meeting #9 10/22/2008.

Slides:



Advertisements
Similar presentations
LBT Q Eng/SW Review SFWG – Software Group General Norm Cushing.
Advertisements

The Project Office Perspective Antonin Bouchez 1GMT AO Workshop, Canberra Nov
PALM-3000 Management Update A. Bouchez, J. Roberts Team Meeting #15 10/29/09.
PALM-3000 PALM-3000 Management Update Antonin Bouchez, Jenny Roberts Team Meeting #7 27 February, 2008.
Build to Cost Meeting: Goals, Agenda & New Directions Peter Wizinowich NGAO Team Meeting September 11-12, 2008.
OHT 6.1 Galin, SQA from theory to implementation © Pearson Education Limited 2004 Development plan and quality plan objectives The elements of the development.
PALM PALM-3000 project status 31 Jan COO All-Hands Mtg. Recent Milestones Requirements review on 12 Nov AO system offline for maintenance.
PALM-3000 P3K Team Meeting #16 Stephen Guiwits Dean Palmer, Ernest Croner, Antonin Bouchez Team Meeting # Cahill March 05, 2010.
PALM-3000 P3K Integration and Test Review Stephen Guiwits P3K System Computers and Electronics 273 Cahill September 22, 2010.
PALM-3000 Integration and Testing Status A. Bouchez Team Meeting #15 10/29/2009.
CS 501: Software Engineering Fall 2000 Lecture 4 Management I: Project Management.
PALM-3000 PALM-3000 Instrument Architecture Antonin Bouchez PALM-3000 Requirements Review November 12, 2007.
PALM-3000 PALM-3000 Status A.H. Bouchez, J.E. Roberts Project 1640 Las Vegas Summit 1/28/2010.
GLAST LAT ProjectEGSE Peer Design Review, August 17, S. WilliamsEGSE Schedule and Cost Electrical Ground Support Equipment Schedule and Cost Scott.
WBS & AO Controls Jason Chin, Don Gavel, Erik Johansson, Mark Reinig Design Meeting (Team meeting #10) Sept 17 th, 2007.
NGAO Management Update Peter Wizinowich NGAO Meeting #11 November 5, 2007.
John Arthur Photon October 29, Photon Systems Update FAC recommendations Current status New plan for Photon Systems.
PALM-3000 Optical Bench Update Jenny Roberts Optical Bench Team: C. Baranec, A. Bouchez, K. Bui, R. Burruss Team Meeting #15 10/29/2009.
GLAST LAT ProjectSubsystem Managers Face to Face, November 17, GLAST Large Area Telescope: Darren Marsh Stanford Linear Accelerator Center Performance.
PALM-3000 PALM-3000 Software Requirements Review Thang Trinh PALM-3000 Requirements Review, Caltech Campus November 12, 2007.
NGAO Team Meeting Management Peter Wizinowich May 26, 2009.
PALM-3000 Instrument commissioning schedule Antonin Bouchez Team Meeting #7 27 February, 2008.
OHT 6.1 Galin, SQA from theory to implementation © Pearson Education Limited 2004 Development plan and quality plan objectives The elements of the development.
John Arthur Photon October 12, Photon Systems Update John Arthur SLAC 1.
PALM-3000 Budget and Schedule Update A. Bouchez, J. Roberts Team Meeting #10 1/8/2009.
NGAO Instrumentation Preliminary Design Phase Planning September 2008 Sean Adkins.
5 th February 2010 FP7 Prep WP9000 Progress Meeting 1 Update Tim Morris Durham University FP7 Prep WP 9340.
Project planning. Software project management Informal definition of management – The art of getting work done through other people Software project management.
LSU 01/18/2005Project Life Cycle1 The Project Life Cycle Project Management Unit, Lecture 2.
U.S. ATLAS Physics and Computing Budget and Schedule Review John Huth Harvard University DOE/NSF Review of U.S. ATLAS and CMS Computing Projects Brookhaven.
Annie Griffith Infrastructure Programme Manager July 2007 UK Link Technology Refresh.
ASPERA-3 Sep. 25, 00 Monthly Status Report ASPERA Monthly Status ReportMonthly 9_25/ Page 1 Monthly Status Report Report due 9/25/00 Schedule statused.
LBT Q Engineering Review DYB. 26-Oct-2007LBT Q Engineering Review Highlights (Q3/2007) Currently in Commissioning Phase Currently in Commissioning.
BROOKHAVEN SCIENCE ASSOCIATES National Synchrotron Light Source II Project Management Jim Yeck Deputy Director (Project Management)
David M. Lee Forward Vertex Detector Cost, Schedule, and Management Plan Participating Institutions Organizational plan Cost Basis R&D Costs.
COROTWEEK n°8 Toulouse May the 24th, 2005 Program Status (Th. Lam-Trong) 1 COROT.
Rev. 0 CONFIDENTIAL Mod.19 02/00 Rev.2 Mobile Terminals S.p.A. Trieste Author: M.Fragiacomo, D.Protti, M.Torelli 31 Project Idea Feasibility.
BROOKHAVEN SCIENCE ASSOCIATES National Synchrotron Light Source II Project Management Jim Yeck NLSL II Deputy Director (Project Management)
1 BROOKHAVEN SCIENCE ASSOCIATES NSLS-II Project Baseline Jim Yeck NSLS-II Deputy Project Director NSLS-II PAC Meeting November 20, 2007.
Magellan F/5 System Status A.Szentgyorgyi / Ann Arbor 25 Sept 2005.
October 4-5, Status of ARRA funded AIPs Electron Lens Scope, Cost, and Schedule Wolfram Fischer October 4, 2010 Electron Lens.
January LEReC Review 12 – 13 January 2015 Low Energy RHIC electron Cooling Kerry Mirabella Cost, Schedule, Personnel.
CS 501: Software Engineering Fall 1999 Lecture 6 Management I: Project Management.
1 These courseware materials are to be used in conjunction with Software Engineering: A Practitioner’s Approach, 5/e and are provided with permission by.
THE PROJECT LIFE CYCLE PROJECT MANAGEMENT LIFE CYCLE LSU 01/18/2005 PROJECT LIFE CYCLE 1.
January LEReC Review 12 – 13 January 2015 Low Energy RHIC electron Cooling Kerry Mirabella Cost, Schedule, Personnel.
DEX Publication Project OASIS PLCS Telecon 27 November 2007 Trine Hansen.
1 ME1/1 ODMB Production Readiness Review: Schedule and Budget Darien Wood Northeastern University For the ME1/1 Electronics Project.
Deliverables, Cost, Manpower, Schedule & Maintenance Su Dong CSC Readout Replacement CDR Oct/8/
Mark McKinnon NSF Mid-Project Review May 11-12, Baseline Project Definition Mark McKinnon Project Manager.
David M. Lee Forward Vertex Detector Cost, Schedule, and Management Plan Participating Institutions Organizational plan Cost Basis R&D Costs.
Planning of the EUSO-BALLOON project Sylvie Dagoret-Campagne on behalf of the JEM-EUSO collaboration, EUSO-BALLOON project manager LAL/France EUSO BALLOON.
Time to resolve Design Issues 1. Disclamer Due to the engineering meeting last week I have not had time to coordinate this material with Tim or the L3.
Schedule and Milestones Roy Preece STFC RAL FAC 17 th April 2015.
Camera PDR/CD1 Planning 19 September 2008
Jim Fast Pacific Northwest National Laboratory
Project Management W. J. Foyt
Software Project Management
TripleSpec 4 Status and Coming Steps
Software Project Management
Key Issues CPOC Update February 2011 Second Avenue Subway TBM Drive #1
Management Breakout: MREFC Budget Summary Victor L
X-ray Pump-Probe Instrument
Virgo Update – LSC meeting
Linac Coherent Light Source Procurement
LGS Project Meeting December 21, 2006 Agenda SWIFT update - A. Bouchez
Project Management Issues John N. Galayda, SLAC April 24, 2002
Greater Kaweah GSA Board Meeting
DOE Status Meeting of the LCLS Project
XRN 4927 – MiR Drop 4 - Status Update
Presentation transcript:

PALM-3000 Management Update A. Bouchez Team Meeting #9 10/22/2008

PALM Where we are We are midway through the preliminary design phase. Some subsystems are further advanced –Real-time reconstructor computer. –High-order wavefront sensor. We’ve fallen 6 months behind our original schedule. We have commissioned 2 new state-of-the-art instruments on the PALMAO system. The PALM-3000 design has been refined, and we now have far better estimates of the effort and cost required to completion. With some reduction in scope, we have the funding and people to deploy PALM-3000 in late summer 2010.

PALM What’s new? Scope Changes To reduce cost and keep to summer 2010 delivery date, we have decided to postpone LGS capabilities to FY2011 at the earliest. –Include LGS components in design, but not implementation. Personnel Changes John Cromer is moving off of P3K (to MOSFIRE and NIRES). Justin Crepp started on 1 Oct. –HODM testing, systems engineering, P1640 Cal system interface. David Hale will be joining Software team on ~1 Dec. We are recruiting an additional software engineer (0.5 FTE).

PALM FY09 Budget $125k MRI carry-over from FY08 due to slower than expected progress on software, systems engineering. While we have identified resources to get us to first light in Aug. 2010, budget is tight.

PALM FY09 Schedule Issues Critical Path(s) Software development –Automations server - AOCP - motor control –High Order Wavefront Processor High-order deformable mirror procurement and testing –Already delayed by at least 7 months… Electronics assembly and testing –Especially DM & motor cabling. Strategies Build up software team. Monitor progress at Xinetics through meetings and visits. Be prepared to seek additional electronics technician help as necessary.

PALM-3000 Critical path schedule

PALM Milestones Electronics PDR: 12 November. Software PDR in mid-January Optical Bench PDR: 9 February … Pre-ship review: end January First commissioning run: August 2010.