ESS Pre- Operations Dave McGinnis Accelerator Division/RF Group.

Slides:



Advertisements
Similar presentations
Jan Uythoven, AB/BTLHCCWG, 3 May 2006 Page GeV Commissioning Machine Protection Needs to be commissioned to: Prevent damage with the used, higher.
Advertisements

ESS Timing System Plans and Requirements Timo Korhonen Chief Engineer, Integrated Control System Division May 19, 2014.
The European Spallation Source Dave McGinnis Chief Engineer – ESS\Accelerator Division IVEC 2013.
ESS Accelerator Design Upgrade Project Suzanne Gysin Prject Support Officer ESS Accelerator Division , SLHIPP-1
paul drumm; 3rd December 2004; AFC MM 1 Cost & Schedule Review I Terms of reference: –To review the Cost and schedule of the MICE Muon beam –To review.
Costing Meeting Ajit Kurup 13 th June Page 2 Costing Meeting 13 th June 2011 Ajit Kurup Summary of CERN costing workshop. Proposed Level 3 breakdown.
Maintenance and Engineering Procedures and Tools at Soreq Applied Research Accelerator Facility I. Gertz, Y. Buzaglo, A. Grin, R. Michael, R. Raizman,
How to improve operational efficiency ? [R. Alemany] [CERN AB/OP] [Engineer In Charge of LHC] Beam Commissioning Workshop, Evian Jan 2010.
The ESS vacuum team has overall responsibility for all technical vacuum systems used on the: Accelerator, Target and Neutron Scattering Instruments and.
Prospects of SC Quadrupole Production at IHEP-Protvino The 2nd Institutes Meeting on International Construction of the FAIR Accelerator Complex Protvino,
Linac Front-End R&D --- Systems Integration and Meson Lab Setup
Front End Test Stand Klystron Commissioning Alan Letchford UKNF Plenary Meeting 22 nd April 2009.
Fermilab Implementation of DOE Critical Decision Process FRA Project Management System Presentation by L Edward Temple Jr Head, Office of Project Management.
1 UK PM Report Costs & Schedule Alan Grant, STFC.
Software Tools for Operations and Maintenance Planning Theo Larrieu, Steve Suhring.
POWER Power – Power = P = ___=___ Units = ( ) = ____ = ___ Sample Problem: A crane lifts an 8000 N beam 75 m to the top of a building in 30 s. How much.
Feedback from MEF  Only possible, if COMMON COORDINATION MEETINGS  Main possible conflict: SAFETY –No “work permits” in the injectors. MEF working on.
February NSTX-U Team Meeting. Engineering Operations Feb. 11, 2014 NSTX-U In-Vessel installations and Calibrations to conclude in late March (3/28/2014)
F Project X Overview Dave McGinnis October 12, 2007.
Collider-Accelerator Department EBIS Commissioning Accelerator Readiness Review (ARR) Training, Prior Reviews, Configuration Management Action Item Tracking.
1 Linac4 Overview M. Vretenar, SLHC Meeting, Motivations 2.Layout 3.Main parameters 4.Schedule 5.Status.
G 0 Coordinator Update & “To-Do List” Joe Grames William & Mary, June 5-6, 2006  Hall C Beam Line Tasks  Accelerator Preparation Tasks  Beam Halo 
Roman Pot Engineering Design Review CERN, 14 February 2006 M.Oriunno, CERN PH-TOT Installation, Commissioning and Schedule.
HC Review, May 2005 Hardware Commissioning Review Hardware Commissioning Review Quality Assurance and Documentation of Results Félix Rodríguez Mateos,
Green Field Accelerator Study W. Kaufmann A. Leonardo D. Valuch.
Anders Sunesson RF Group ESS Accelerator Division
1 W-band Module Production and Other Fermilab Contributions Proposed Significant Partnership in QUIET-II to the Fermilab PAC in November 2009 Modest Fermilab.
Alexander Aleksandrov Oak Ridge National Laboratory
HWDB: Operations at the Spallation Neutron Source Workshop on Accelerator Operations August 6-10, 2012 Glen D. Johns Accelerator Operations Manager.
1 Operational availability Optimizing LHC L. Ponce With the (un)intentiona lcontribution of all OP crew.
Nominal Workflow = Outline of my Talk Monitor Installation HWC Procedure Documentation Manufacturing & Test Folder Instantiation – NC Handling Getting.
Lloyd’s Register Energy - Drilling Integrating ModuSpec and WEST Engineering Services to advance excellence in drilling safety, integrity and performance.
1 AGS RSVP Review 4-5 November 2004 Upgrade and Operations Cost & Schedule Summary Philip Pile Collider-Accelerator Department 4 Nov 2004.
O AK R IDGE N ATIONAL L ABORATORY U. S. D EPARTMENT OF E NERGY The Spallation Neutron Source Project: Update T. E. Mason Oak Ridge National Laboratory.
Hardware Commissioning  Preparation Documentation MTF Programme  Status The Review The commissioning activity in Resources  Outlook The new.
LINAC4 COMMISSIONING 1 LESSONS LEARNT DURING MY VISIT AT LINAC4 COMMISSIONING Evangelia Vaena, 02/02/2016.
Proton Source Task Force William Pellico Mu2e Working Group Meeting (WGM) on Wednesday, Jul 21.
DESY. Deutsches Elektronensynchrotron Introduction of DESY and MKK group Jens-Peter Jensen Asset and Maintenance Management Workshop 2013 Genf,
F A Fermilab Roadmap Dave McGinnis May 28, f Fermilab Roadmap - McGinnis Timelines  Divide the road map into three parallel paths  ILC - Energy.
High Intensity Neutrino Source Program Overview for CD Controls Management Meeting Bob Webber October 6, 2006.
Linac2 and Linac3 D. Küchler for the linac team. Planning first preparative meeting for the start-up of Linac2 in June 2013 –this early kick-off useful.
TE-CRG Activities D. Delikaris, TE-CRG.
BooNE Meeting, January 15, Prebys 1 How are we doing? Best running Power loss (W) Protons (p/min) Energy Lost (W-min/p) Best running again ? Mysterious.
NML - RF Unit Test Facility Jerry Leibfritz Fermilab.
Conventional Facilities integration: Approach and Issues Daniel Piso Fernández WP Leader (WP13 Conventional Facilities Integration Support) November 5,
Safety - Lessons learnt from the design, commissioning and operation of the HIE-ISOLDE cryomodules Safety overview ESS 8 June 2016 AP.Bernardes/EN on behalf.
1. Baseline – from LMC  Presentation by F. Bordry at LHC Machine Committee 5.10 on LS1 Organisation: 1. Linac4 is not going to be connected.
LARP Crab Cavities Cryomodule Integration Meeting Final Notes A.Ratti LBNL.
M. Munoz April 2, 2014 Beam Commissioning at ESS.
W. Barth, 8th FAIR Machine Advisory Committee, REPORTS BY NEW PROJECT DIVISION HEADS: “LINAC& Operations” organisation issues tasks and.
Chapter Editor: John Weisend TDR Chapter 6 Cryogenic System, Vacuum System & Test Stands.
22/09/2011 ADO-PO section meeting ADO : Atlas Detector Operation PO : Project Office R. Vuillermet.
WBS 1-7 System Assembly & Installation John Voirin August 10-11, 2011.
ColMat Welcome and Task 1 Ralph W. Aβmann Kick off Meeting of EuCARD/ColMat CERN – June 17 th, Jun 09 1R. Assmann.
Head, Office of Project Management Oversight (OPMO)
TC activities.
Maintenance Scheduling
SNS Status Report Karen S. White 10/15/08.
Accelerator Operations Department Readiness (Part 2)
Proton Source and LEBT Luigi Celona & Lorenzo Neri
UK RFD Pre-Series cryomodule
World Wide Fundamental Power Coupler meeting #3
The Fermi National Accelerator Laboratory is a U. S
Neutron Detector Systems at ESS
Reorganizations, Program Changes and Reduced Funding
LHC upadtes.
ESS Freia Scope Setting ESS - Lund - 17/10/2016.
Installation Binder / IRR – an example
PSS verification and validation
(Beam) Commissioning Plan
Presentation transcript:

ESS Pre- Operations Dave McGinnis Accelerator Division/RF Group

Pre-Operations (my definition) Starts when we try to accelerate one proton down the beam tube Until we achieve 5 million Watts (5 MegaWatts) – 900 trillion protons per pulse – 14 times a second – Beam voltage of 2.5 billion volts

What is 5 MegaWatts? At 5 MegaWatts, – one beam pulse has the same energy as a 16 lb (7.2kg) shot traveling at – 1100 km/hour – Mach 0.93 Has the same energy as a 1000kg car traveling at 96 km/hour Happens 14 x per second – You boil 1000 kg of ice in 83 seconds A ton of tea!!!

Pre-Pre-Operations Will start during construction. As soon as a small section of the accelerator is ready (Ion Source->RFQ- >Drift Tube) – We will run beam to check out major systems (controls, RF, instrumentation, operations staff…) Beam is the Ultimate System Integrator! Commissioning will happen from 8pm – 8am – Construction and repair will happened during the day

Accelerator Readiness Because of the immense damage the beam can cause we will have to prepare procedures to makes sure all systems are ready – A BIG DEAL For example, formal sign-offs of all the systems: – Safety (shielding, interlocks, electrical,…) – Electrical – Vacuum – Instrumentation – RF – Cryogenics

Pre-Operations Once the machine is cold, and the accelerator is ready, we will begin round- the-clock operations – It is too expensive to not run round-the- clock – We have to maintain configuration control We will need to make a detailed commissioning plan – Detailed shift plan for 3 shifts per day for 3 months. People, tasks, tools – Plan will be invalid after the first shift “Plans are worthless, but planning is everything. ” Dwight Eisenhower

Staff We will need two types of crews – Operations crew (permanent) 3 operators/crew 5 crews – Scientist/ Engineer crew (temporary) 2 staff members/crew 6-7 crews We will need coordination – Machine coordinator (scientist) – Machine scheduler (operations) Meetings – Shift change meetings – Daily operations meetings

Super Rough Schedule ~1 month to thread the beam 1-6 months for 100kW beam 6-24 months for > 2 MW beam What are we doing between ???

“If it works the first time, then its over-designed” Archimedes to his junior engineer, Wally, ~220 B.C

Upgrades A “gold-plated” accelerator is un- affordable. We have to plan to upgrade (fix) systems that did not perform as expected – Every large accelerator system built has taught us this LHC Tevatron SNS … Funding will be needed during the pre-operations phase for upgrades.