Presentation is loading. Please wait.

Presentation is loading. Please wait.

Hardware Commissioning  Preparation Documentation MTF Programme  Status The Review The commissioning activity in 2005-2006 Resources  Outlook The new.

Similar presentations


Presentation on theme: "Hardware Commissioning  Preparation Documentation MTF Programme  Status The Review The commissioning activity in 2005-2006 Resources  Outlook The new."— Presentation transcript:

1 Hardware Commissioning  Preparation Documentation MTF Programme  Status The Review The commissioning activity in 2005-2006 Resources  Outlook The new schedule Roberto Saban on behalf of the Hardware Commissioning Team MAC19 060616

2 Roberto Saban TS MAC 19 060616 The method individual system tests hardware commissioning  qualification for operation of the individual systems After the qualification for operation of the individual systems of a sector (vacuum, cryogenics, quench protection, interlocks, powering, etc.),  each sector will be commissioned as a whole each sector will be commissioned as a whole up to the powering to nominal current of all the circuits. Validation and specific studies Validation and specific studies will be carried-out on the first commissioned sector. What tests the procedures and the sequencethe procedures and the sequenceHow what conditions are required to startwhat conditions are required to start what conditions determine it is finishedwhat conditions determine it is finished what conditions are required during the testswhat conditions are required during the tests Sytem owners define and carry-out Hardware Commissioning Coordination ensures that the conditions required exist What tests the procedures and the sequencethe procedures and the sequenceHow what conditions are required to startwhat conditions are required to start what conditions determine it is finishedwhat conditions determine it is finished what conditions are required during the testswhat conditions are required during the tests Hardware Commissioning Coordination with System Owners define and carry-out and ensures that the conditions required exist Preparation

3 Roberto Saban TS MAC 19 060616 The logic Preparation subsystems ready all systems ready for machine check out individual system tests hardware commissioning two types of documents : as designed as tested  impact on equipment safety  impact on equipment/system performance  impact on machine performance

4 Roberto Saban TS MAC 19 060616 Commissioning Procedures & Failure Scenarios  Progress has been made in convincing our colleagues from the equipment groups of the usefulness of the documentation  Documentation describing the Individual System Test and Hardware Commissioning Procedures now exist for most of the systems  Only a few documents describing Failure Scenarios have been prepared  A standard chapter on Safety was introduced in all of them following the guidelines of the Safety Coordinators  These documents are used as a hard reference by those who carry out the tests in the field; these documents are alive : in fact, the have undergone updates following experience when carrying them out Preparation

5 Roberto Saban TS MAC 19 060616 SECTOR 7-8  Sector  RegionComponentsEquipment group  Superconducting Circuits RQS.A78B2.RR77 Equipment  Arc 78 Power Converter IST The Manufacturing & Test Folder Preparation

6 Roberto Saban TS MAC 19 060616 The Manufacturing & Test Folder Preparation EDMS – MTF for Circuit Related Components: AC Distribution Powering Interlock for warm and cold circuits Quench Protection System Energy Extraction Control Cooling & Ventilation Cooling Power Cables Electrical Quality Assurance Power Converter Short Circuit Tests DFBs Cryogenics Vacuum Access & Safety EDMS – MTF for Beam Related Components: Beam Instrumentation Controls + Beam Energy Meter Collimators Kicker System Diluters Beam Interlock System Beam Dumping System Beam Injection System RF

7 Roberto Saban TS MAC 19 060616 The Manufacturing & Test Folder Preparation Data already uploaded for Sectors 78, 45 and 81 ! (~1000 slots filled in)

8 Roberto Saban TS MAC 19 060616 The commissioning programme Preparation Front 1Front 2Front 1Front 2 LeftRight 6.6 km Front 1 arc and the matching section on the even side Front 2 arc, the matching section on the odd side and the inner triplets on both sides two shifts = 15 hour days

9 Roberto Saban TS MAC 19 060616 The day to day coordination : the human resources Preparation operation support to operation data recording reporting Field Control Room or CCC Sector A 1 Engineer 1 Technician 1 AB Operator Sector B 1 Engineer 1 Technician Progress Tracking Planning Re-scheduling Meetings Crisis Management MTF Database Analysis Information processing Publications Project Management 1 Project Leader 1 Mr.Circuit & DPL 1 Database/Web Expert 1 Administrative Assistant hardware oriented small repair missing details access/balisage Field Preparation LHC Safety Coordination advise on safety matters enforce safety in the field

10 Roberto Saban TS MAC 19 060616 The review & its recommendations Status  Some organisational matters were judged worth further attention.  It was noted that Hardware Commissioning will be the first occasion where the safety measures (responsibility, training, access conditions, signalling, etc.) put in place for LHC will be evaluated for the first time. Furthermore, Hardware Commissioning will be a test of the new organisation of Safety at CERN; its impact must be monitored.  A number of issues related to controls & informatics were noted.  Important technical issues related to either the conditions under which the tests are carried-out (e.g. the ventilation of the tunnel during the tests) or the tests themselves were considered; some of them must be reconsidered in the light of the present installation and commissioning scenario.

11 Roberto Saban TS MAC 19 060616 The commissioning activity in 2005-2006 Three underground powering areas around even points were tested with the power converters connected to the cables (water and air cooled) Status DFBs field control room Power Converters Energy Extraction Systems One smaller underground powering area close to Point 7 is being tested now.

12 Roberto Saban TS MAC 19 060616 The commissioning activity in 2005-2006 Status

13 Roberto Saban TS MAC 19 060616 The supply air temperature of the HVAC units is regulated at 17.5 ± 1.5 ˚C except ESCL 7,9,10,11 and 12. ESCL1 PID is optimized for hi-speed fan. ESCL7 showed a regulation problem since a manual valve had remained closed. ESCL9 to 12 inefficiency problem. Data provided by ST-CV The commissioning activity in 2005-2006 Status

14 Roberto Saban TS MAC 19 060616 The temperature at the ducts showed maximum values of 74 ˚C 10h after start up PC. At 03:15 cables 1808470 showed 154 ˚C at their end. Tightening problem solved at 04:30. The commissioning activity in 2005-2006 Status

15 Roberto Saban TS MAC 19 060616 Resources Status

16 Roberto Saban TS MAC 19 060616 The new schedule Outlook A piece of cake The nightmare

17 Roberto Saban TS MAC 19 060616 The new schedule  It looks it can be done with a few reserves like the activation of the tunnel during this first run, the commissioning of the access safety and access control system, the approval of the as-built access safety and access control system by the INB authorities, the fact that we would start with a machine which is not so well aligned ( no smoothing )  Careful tuning of co-activities is needed  Some additional resources will be needed in 2007 (man power and hardware)  Resources not originally planned for will be needed in 2008  The program for 2008 must be closely watched to ensure that the remaining commissioning can really be done in the three months allocated Outlook

18 Roberto Saban TS MAC 19 060616 Conclusions  Preparation “finished”  Awareness of safety and equipment integrity must be continuously stimulated  First experience in the field positive but the real heat is not yet on  The resources were found but must be monitored in the light of the changing scenario  Delicate scheduling of the activities to match the available resources and the requirements of the schedule Hardware Commissioning


Download ppt "Hardware Commissioning  Preparation Documentation MTF Programme  Status The Review The commissioning activity in 2005-2006 Resources  Outlook The new."

Similar presentations


Ads by Google