Progress Report 12/13/11
Progress Schedule December 2011 Work Completed December: Installed Concrete topping on roof Rough In M&E East side screen wall foundations poured Building Insulation Tower Foundation Completed Rough in of Fire Protection System Interior Plumbing, Roof Drains Work Scheduled January: Complete Roofing Frame Interior Walls Rough in M & E Erect Tower Run Electrical Service Run Natural Gas Service Start Masonry Screen Walls Complete Exterior Brick Window Installation
Progress 12/13/11 West Mechanical Screen WallRoof Blocking
Progress 12/13/11 Tower FoundationCall Center
Office Corridor Rough In Progress 12/13/11
Staff Support Rough InCall Center