Carleton College Summer 2018 Science and Campus Construction Plan

Similar presentations


Presentation on theme: "Carleton College Summer 2018 Science and Campus Construction Plan"— Presentation transcript:

1 Carleton College Summer 2018 Science and Campus Construction Plan
Carleton College Summer 2018 Science and Campus Construction Plan* January 11, 2018 *Subject to change

2 New Building Completion Summer 2019
Auditorium New Building Completion Summer 2019 New Building We chose to locate the new construction so that it would fully integrate with Olin and Hulings—this is key for fostering interdisciplinary work.

3 Construction Milestones
New Building Completed Summer 2019 Olin Renovation Summer 2019 – Summer 2020 Hulings Renovation – Vivarium Summer 2018 Remaining Hulings Renovation Summer 2019 – December 2020

4 New Building Construction Schedule
January 2018 – March Footings and Foundations February 2018 – July Structural Steel and Slab on Metal Decks May 2018 – October Exterior Skin May 2018 – January Mechanical, Electrical, Plumbing and Fire- Protection Rough-in July 2018 – January Interior Framing September 2018 – May Interior Finishes

5 Summer 2018 Impact on Olin and Hulings
Connection to Hulings Auditorium Summer Impact on Olin and Hulings New Building East Earmuff 3rd floor classroom bump-out We chose to locate the new construction so that it would fully integrate with Olin and Hulings—this is key for fostering interdisciplinary work. Lower level Vivarium

6 East Earmuff Location

7 Ground Floor Olin; Construction Highlighted Blue
Ground Floor Olin; Construction Area Highlighted Blue Cognitive Science/Psychology Chemistry Laboratories

8 Ground Olin—Temporary Walls
Enlarged Olin Ground and First Level Corridor areas to be shut down Summer of 2018 from June 5th to September 4th. Men’s restrooms on level one will also be inaccessible during this duration. Restrooms on 2nd and 3rd Levels will have to be used during this duration. Summer of 2018 only—June 5th to September 4th

9 First Floor Olin; Construction Area Highlighted Blue
Classrooms Psychology Offices Psychology/Cognitive Science Offices and Labs

10 First Olin—Temporary Walls
Summer of 2018 only—approx. June 5th to September 4th Men’s restrooms on level one will be inaccessible. Restrooms on 2nd and 3rd Levels will be accessible

11 Olin First Floor Temporary Egress
Olin First Floor Temporary Egress Path. Exiting will take place out the north sets of double doors.

12 Olin Ground Floor Temporary Egress
Olin First Floor Temporary Egress Path. Exiting will take place out the north sets of double doors.

13 Olin 3rd Floor Classroom Bump Out

14 Olin Future 3rd Floor Classroom Location
3rd Floor Classroom Location of Construction

15 Olin 3rd Floor Plan with Future Classroom Area Highlighted

16 Temporary Walls Constructed June 5, 2018 Remain through July 2020

17 Hulings Connection to the New Building Location

18 Olin 3rd Floor Plan with Future Classroom Area Highlighted
First and Second Floors—Temporary Walls around Ornamental Staircase Constructed June 5, 2018 Remain through July 2019

19 Olin 3rd Floor Plan with Future Classroom Area Highlighted
Third Floor—Temporary Wall Partitioning Hulings 300 300 Constructed June 5, 2018 Remain through Summer 2019

20 Vivarium Construction Location

21 Scope of Vivarium Work Timeframe Replace Air Handler
Upgrade HVAC Controls Replace Cage Washer Upgrade Lighting Upgrade Fire Alarming Isolate Mechanical & Electrical Systems UPS Backup Timeframe Spring Break (less invasive) Spring Term (less invasive) June (major construction)

22 Next Steps in Planning Finalize Furniture for Department Spaces January Complete Lab Casework Review for New Building February Review Furniture for Offices February-March Begin Science Migration Summer 2019 Planning February Wood Millwork Review Spring Term

23 2018 Summer Project Work Offline summer and fall BALD SPOT
Preliminary plan as of 1/8/18. Project durations and locations still subject to change.

24 2018 Summer Project Work Offline all summer (June 18 to August 31)
Offline summer and fall Offline all summer (June 18 to August 31) Preliminary plan as of 1/8/18. Project durations and locations still subject to change.

25 2018 Summer Project Work Utility excavation Offline summer and fall
Offline all summer (June 18 to August 31) Utility excavation Preliminary plan as of 1/8/18. Project durations and locations still subject to change.

26 2018 Summer Project Work Offline all summer (June 18 to August 31)
Offline summer and fall Offline all summer (June 18 to August 31) Utility excavation Building exterior work: roofs, walls, tuck-pointing, roofs, windows Preliminary plan as of 1/8/18. Project durations and locations still subject to change.

27 2018 Summer Project Work Offline all summer (June 18 to August 31)
Offline summer and fall Offline all summer (June 18 to August 31) Utility excavation Building exterior work: roofs, walls, tuck-pointing, roofs, windows Offline for 2-4 weeks 2-4 wk. shut-down 3-4 wks. Preliminary plan as of 1/8/18. Project durations and locations still subject to change.

28 2018 Summer Project Work Offline summer and fall
Offline all summer (June 18 to August 31) Utility excavation Building exterior work: roofs, walls, tuck-pointing, roofs, windows Offline for 2-4 weeks 2-4 wk. shut-down BALD SPOT 3-4 wks. STEAM PLANT SHUT-DOWN: June 18-24 Preliminary plan as of 1/8/18. Project durations and locations still subject to change.