Minuteman Vocational Technical Regional High School Progress

Similar presentations


Presentation on theme: "Minuteman Vocational Technical Regional High School Progress"— Presentation transcript:

1 Minuteman Vocational Technical Regional High School Progress
September 17th, 2018 – October 15th, 2018

2 September 29th View of Area A & B – East Elevation
Installation of Curtain Wall & Glazing in Progress October 15th View of Area A & B – East Elevation FAPA Complete Window Frames & Glazing Complete Metal Panel Framing & Insulation in Progress

3 October 15th View of Area A & B – North Elevation
Install of Metal Panel in Progress October 15th View of Area A & B – Upper Level Installation of in-wall blocking to support drywall activities.

4 October 15th View of Area G – North Elevation
Upper Level Window Frames & Glazing Complete Lower Level Masonry Veneer in Progress

5 October 15th View of Area E – Courtyard
Installation of Curtain Wall Frames in Progress October 15th View of Area E – Courtyard Exterior Framing & Sheathing

6 October 12th View of Area E – North Roof Level
Installation of bituminous roofing assembly in progress.

7 October 15th View of Area D – Lower Level
Rough-in of overhead MEP’s in Mechanical Room Interior CMU wall construction in progress

8 October 15th View of Area D – West Elevation
Masonry Veneer Activities in Progress Site Utilities in Progress

9 October 15th View of Area E+F – Lower Level
Slab on Grade placement for the Cafeteria & Kitchen

10 October 15th View of Area F – Lower Level
Underground utilities and backfill activities in Culinary Kitchen

11 October 15th October 15th View of Area C – West Elevation
Construction of exterior CMU walls in progress. October 15th View of Area C – East Elevation Construction of exterior CMU walls in progress.

12 October Construction Schedule Look Ahead:
Area A+B Complete with installation of waterproofing materials on exterior walls. Complete Masonry Veneer activities. Continue Window & Metal Panel Activities Commence Sheetrocking activities on Upper Level B Area G Complete installation of waterproofing materials on exterior walls. Continue with interior CMU wall construction on Lower Level. Continue Window system installation Commence Sheetrocking activities on Upper Level Area E Complete roofing installation activities. Complete waterproofing activities. Continue Curtain Wall & Window System installation Continue Rough-In of OH MEP’s on Upper & Bridge Levels Continue Wall Framing activities to support MEP’s Area D Complete exterior sheathing activities. Continue Rough-In of OH MEP’s in Mechanical Room & Lower Level. Continue Masonry Veneer activities. Area F Complete excavation and installation of underground utilities. Place concrete slab on grade Commence Masonry Veneer activities. Area C Continue with interior and exterior CMU Masonry walls. Sitework Complete installation of water line loop around perimeter of building. Complete Drainage System installation and connections to the building.

13