Project Name – ID # 7/1/2009 Current Project Status Project Issues

Similar presentations


Presentation on theme: "Project Name – ID # 7/1/2009 Current Project Status Project Issues"— Presentation transcript:

1 Project Name – ID # 7/1/2009 Current Project Status Project Issues
3 open; 0 blocking; 29 closed 72% 6/29 Drywall in baths green not grey board; Carlos working with vendor. New board on-site 7/3 6/29 Tile for top floor is not premium as ordered. Joe will have proper tile delivered by 7/4. 6/29 Light fixture delivery delayed 3 days. Project had allowed for this delay in slack. No impact. Delivery scheduled for 7/7. Installation needs 1 day. Target 68% 2 days ahead of schedule Milestones Schedule Complete Designs approved Groundbreaking Foundation Build Framing Roof Walls Interior Landscaping Delivery Complete In Progress (55%) 7/14/08 7/21/08