Electron Beam Systems Wrap-up

Slides:



Advertisements
Similar presentations
Wednesday July 19 GDE Plenary Global Design Effort 1 Instrumentation Technical System Review Marc Ross.
Advertisements

Richard M. Boyce FAC Review – Accelerator Installation October 29-31, Installation – Accelerator Systems Installation Planning.
FAC review, 10/27 D. Schultz 1 e-Beams System Update Injector System Installation has started. Linac System Preparing for ’06 installation. Controls System.
FAC, 10/12/06 D. Schultz 1 e-Beams Systems Update Linac Injector Undulator Production MMF commissioning ARR David Schultz.
Geoff Pile FAC Review - Undulator 12 November 2008 LCLS Undulator System Overview and Fabrication Geoff Pile.
FAC, 4/20/06 D. Schultz 1 e-Beams System Update Linac System Preparing for downtime installation. Injector System Installation has started. Undulator System.
John N. Galayda LCLS FAC 20 April Linac Coherent Light Source Overview and Charge Facility Advisory Committee John.
FAC, 4/16/07 D. Schultz 1 e-Beams Systems Update People ARR Linac Installation Undulator Production MMF Operations David Schultz.
LCLS Linac System Management Linac Coherent Light Source Stanford Synchrotron Radiation Laboratory Stanford Linear Accelerator Center.
D. Schultz FAC 6/17/08 1 e-Beams Systems Update People Progress the last review LTU and Dump Installation Status Undulator.
Stephen Milton Undulator System 20 April, 2006 LCLS Undulator System Update S. Milton, ANL FAC, April 20 th, 2006.
Hamid Shoaee LCLS FAC Controls June 17, LCLS Control System Personnel Linac & BC2 Controls progress LTU, Dump Controls.
Eric Bong LCLS FAC Injector-Linac System October 27, 2005 Injector –Linac System Overview E. Bong LCLS FAC October 27, 2005.
David H. Dowell Injector April 29-30, 2004 LCLS Injector Overview D. H. Dowell, SLAC FAC Review April 29-30, 2004 Injector.
Hamid Shoaee LCLS FAC Review – October Control System Overview Hamid Shoaee Controls System Manager Injector control system commissioning & Support.
FAC, 10/12/06 D. Schultz 1 Readiness for 2007 Startup Linac Injector Controls ARR David Schultz.
1 BROOKHAVEN SCIENCE ASSOCIATES Preparations for Linac Commissioning Ray Fliller, Associate Physicist 8 th ASAC meeting for NSLS-II Project May 10-11,
1 st All Hands Meeting Milton 20 Feb st ANL LCLS All Hands Meeting 20 February, 2006.
David Schultz Accelerator Readiness Dec. 2, ‘08 SLAC National Accelerator Laboratory 1 Undulator Complex Status LCLS Introduction.
LCLS Accelerator SLAC linac tunnel research yard Linac-0 L =6 m Linac-1 L  9 m  rf   25° Linac-2 L  330 m  rf   41° Linac-3 L  550 m  rf  0°
John N. Galayda LCLS Accelerator Readiness December 2, LCLS Overview December 2, 2008 Project Construction Status.
1 Positron Source AD & I Report Jim Clarke ASTeC & Cockcroft Institute Daresbury Laboratory.
Experimental Facilities Planning
Maintain a single control room for all accelerator programs
Injector Performance Requirements Conventional Facilities Update
LCLS Linac Update Brief Overview L1 & BC1 Progress LTU & E-Dump Status Continuing Resolution Impact.
Injector –Linac Status & Schedule E. Bong LCLS FAC October 12, 2006
LCLS Gun Commissioning Status & Plans David H
Injector/BC1 Commissioning (Jan. 2, 2007 through Aug. 31, 2007) P
LTU/Undulator Installation Status
LCLS Injector Commissioning Dates ( )
Linac Ops Budget Review LCLS Overview / Org Structure / Legacies
LINAC OPS Budget Review
John N. Galayda – Director of LCLS Construction March 30, 2009
e-Beams Systems Update
Linac/BC1 Commissioning P
Electron Beam Systems ETC and Methodology
Injector / Linac Installation Current Status
LCLS Linac Overview E. Bong Lehman Review August 10, 2004
LCLS Commissioning P. Emma, et al
Undulator Tuning Status Heinz-Dieter Nuhn, SLAC / LCLS for Zack Wolf, Yurii Levashov, Achim Weidemann, Seva Kaplounenko, Scott Jansson, Ralph Colon, Dave.
Project Management Issues John N. Galayda, SLAC April 24, 2002
LCLS Undulator System Status and Schedule
Integrated Safety and Environmental Management
Undulator Cavity BPM System Status
LCLS Injector/Diagnostics David H. Dowell, SLAC April 24, 2002
LCLS Injector Configuration
Heinz-Dieter Nuhn – LCLS Undulator Group Leader May 14, 2009
E-Beams Systems Manager
LTU/Undulator Installation Status
LCLS Undulator System Status and Schedule
LCLS Injector System Overview D. H
Control System Overview Hamid Shoaee LCLS Control System Manager
LCLS Global Controls Overview August 10, 2004
Linac Coherent Light Source Transition to Operations 11 July 2007
Installation Status & Operational Readiness Process
LCLS Startup, Commissioning & Future Scenarios
Injector/BC1 Commissioning (Jan through Aug. 2007) P. Emma, et al
P. Emma, for the LCLS Commissioning Team LCLS DOE Review May 14, 2009
Electron Beam Systems ETC and Methodology
Injector/Linac Design Status C. E
LCLS e- Beams System Overview
e-Beams Systems Update
LINAC System Engineering / Design Status C.E. Rago
LCLS Control System Personnel Linac & BC2 Controls progress
Physics Update P. Emma FAC Meeting October 27, 2005 LCLS.
DOE Status Meeting of the LCLS Project
LCLS e- Beams Systems Manager
Injector/Linac RF Status
Control System Overview Hamid Shoaee LCLS Control System Manager
Presentation transcript:

Electron Beam Systems Wrap-up David Schultz – LCLS e-Beams Systems Manager May 13, 2009

e-Beams Systems Wrap-up Outline Injector Systems Linac Systems Undulator Complex ARR Undulator Systems Lessons Learned Summary

Injector Systems Emittance Enhancement (Heater) is complete and in successfully tested. Research into its effectiveness is ongoing.

Injector Systems Injector is now in the hands of ASD Operations Accelerator Systems Division Area Physicist: Axel Brachman Area Manager: Patrick Smith Gun cathode was replaced in July ’08, QE has been stable at 4x10-5 near spec. Drive laser availability has been excellent, >99%

Linac Systems LCLS Linac commissioned and operational Accelerator Systems Division Area Physicist: Franz-Josef Decker Area Manager: Tom Graul LCLS Risk Registry items Emittance measurement in sector 24 On the AIP list Linac BPM upgrade Electronics now in fabrication

LTU-Dump installed and being commissioned Linac Systems LTU-Dump installed and being commissioned Some remedial installation planned Photon diagnostics in the dump area Toroids to assure beam delivery to the dump. Designated ASD Area Physicist: Rick Iverson Area Manager: Kathy Burrows Beam Transport Hall

Undulator Complex ARR Accelerator Readiness Review for the Undulator Complex (LTU-UND-EBD) was held 12/2/08-12/4/08 Frank Kornegay chair Pre-start items cleared 12/12/08 SSO approval 12/12/08 Beam to main electron dump 12/13/08 ARR post-start items have now been cleaned up

Undulator Systems Undulator Installation 25 Undulators are installed, 3 more RFI 33 will be installed by the end of June All hardware from ANL received The LTT needs to be relocated at SLAC The remainder of the ANL Beam Loss Monitors need to be fabricated.

Long Term Test at ANL

Undulator Systems Designated Accelerator Systems Division Area Physicist: Heinz-Dieter Nuhn Area Manager: Mike Zurawel Will cycle two Undulators per month through MMF to check for stability.

e-Beams Systems Wrap-up Lessons Learned If hardware and controls are not effectively checked out in the lab prior to installation, then problems are not found until commissioning. Design reviews are the best management tool for collaboration with remote partner laboratories.

e-Beams Systems Wrap-up Summary E-beams Systems Commissioning should be complete next month. 33 Undulators installed Photons into FEE Outstanding items Undulator Installation (TEC) Undulator systems commissioning (OPC) Long Term Test at ANL (OPC)