UITF – Upgrade Injector Test Facility

Slides:



Advertisements
Similar presentations
Progress Report 12/13/11. Progress Schedule December 2011 Work Completed December: Installed Concrete topping on roof Rough In M&E East side screen wall.
Advertisements

INJECTOR TEST FACILITY UPGRADE PHASE I: 5-10 MEV INJECTOR Feb. 7, 2014.
Impact of 30 day hold Cedar Conversion to Elementary.
D. Schultz FAC 6/17/08 1 e-Beams Systems Update People Progress the last review LTU and Dump Installation Status Undulator.
Sector 13 Canted Undulator Upgrade Hutch Modification Requirements.
Sector 13 Canted Undulator Upgrade Hutch Modification Requirements ( )
LINACs Michael Bevins May 17, GeV Upgrade - Beam Transport Injection, Linac, Extraction, & Correctors Preliminary Design and Safety Review.
1 Summary of MICE beamline & hall installations This is a very rough summary of the progress since mid-December Richard Apsimon & Andy Nichols MICO meeting.
ILCTA_NML Progress at Fermilab Jerry Leibfritz September 10, 2007.
1 MICE - INFRASTRUCTURE MICO meeting 7 th February 2008 Tim Hayler.
Thomas Jefferson National Accelerator Facility Page 1 UITF Progress meeting Approved Labyrinth Fresh air pulled through “chicken wire” gate.
Thomas Jefferson National Accelerator Facility Page 1 UITF Progress meeting UITF ODH Discussion How to avoid ODH2 conditions? August 5, 2015.
1 UK PM Report Costs & Schedule Alan Grant, STFC.
’ tall Empty space below this metal sheet 66’ 14’ 4’ 10’ Ceiling tiles = 24 Concrete blocks 14’ long There are two “styles” of Ceiling tile,
Upgrade Injector Test Facility: UITF Why Build It? HDIce commissioning Bubble chamber physics with Bremsstrahlung x-rays: photo-disintegration of oxygen.
HINS 6-Cavity Test 3 Month Plan Jan 12, Current Schedule 2-3 day shutdown scheduled to start Jan 18 (Wednesday) to upgrade BPM system and reinstall.
Thomas Jefferson National Accelerator Facility Page 1 UITF Progress meeting UITF Project Status Meeting Matt Poelker July 31, 2015.
1 MICE Hall and Infrastructure - Progress since CM18 Chris Nelson MICE CM19 Oct 2007.
MICE RFCC Module Update Allan DeMello Lawrence Berkeley National Laboratory MICE CM29 at RAL, UK February 17, 2011.
MINU GPP WBS 1. Main Injector Neutrino Upgrades - Infrastructure Project Dixon Bogert APD Department Report – March 7, 2007 Russ Alber - FESS Engineering.
Thomas Jefferson National Accelerator Facility Page 1 UITF Progress meeting UITF Project Status Meeting Matt Poelker October 21, 2015.
ILC Test Facility at New Muon Lab (NML) S. Nagaitsev Fermilab April 16, 2007.
Thomas Jefferson National Accelerator Facility Page 1 UITF Progress meeting Re-scoping UITF Matt Poelker November 14, 2015.
1 Mice Collaboration Meeting CM33 Glasgow University 25 th – 29 th June 2012 STFC Daresbury Laboratory Electrical Infrastructure Report Authors : Ian Mullacrane.
8/31/05DR Lynch1 HBD Preparations in the IR Don Lynch.
CMTF Infrastructure Jerry Leibfritz PIP-II Machine Advisory Committee 9-11 March 2015.
NML - RF Unit Test Facility Jerry Leibfritz Fermilab.
Thomas Jefferson National Accelerator Facility Page 1 UITF Progress meeting UITF Project Status Meeting Matt Poelker April 12, 2016.
Thomas Jefferson National Accelerator Facility Page 1 UITF Progress meeting UITF Project Status Meeting Matt Poelker February 23, 2016.
Thomas Jefferson National Accelerator Facility Page 1 UITF Progress meeting What we started with… UITF as imagined Upgraded Injector Test Facility - UITF.
UITF ODH Assessment UITF Safety Review May 10, 2016.
Thomas Jefferson National Accelerator Facility Page 1 UITF Progress meeting What we started with… UITF as imagined Upgraded Injector Test Facility - UITF.
ILCTA_NML Progress at Fermilab Jerry Leibfritz August 16, 2007.
UITF Laser and Gun High Voltage John Hansknecht UITF Operational Review March 18, 2016.
Schedule and Milestones Roy Preece STFC RAL FAC 17 th April 2015.
Upgrade Injector Test Facility: UITF Why Build It? HDIce commissioning Bubble chamber physics with Bremsstrahlung x-rays: photo-disintegration of oxygen.
AIP and Large Projects Arne Freyberger OPS 2015 StayTreat.
Thomas Jefferson National Accelerator Facility Page 1 UITF Progress meeting UITF Project Status Meeting Matt Poelker July 12, 2016.
ASTA Latest Update E. Harms April Photoelectrons first produced at ASTA on 20 June 2013 –Molybdenum (uncoated) cathode ‘Routine’ Electron operation.
Report Technical Director Storage-Ring-Installation Completed
LCLS-II Technical Requirements
Technical Services: Unavailability Root Causes, Strategy and Limitations Data and presentation in collaboration with Ronan LEDRU and Luigi SERIO.
CBETA Technical Review
LERF as Cryomodule Testing Facility Set-Up and Installation Logistics
Francois and Lau EATM 17 July 2012
LCLS-II Cost Details E. Daly / C. Hovater / M. Wiseman with help from Accel Ops and Engineering 03-AUG-2017.
LERF Operation of a High Current, Low–Energy Research Facility for Nuclear and Accelerator Research Stephen Benson Staytreat, July 17, 2015.
SBN Far Detector integration model overview
Why are we removing our very good gun?
UITF Project Status Meeting
UITF Project Status Meeting
UITF Operational Review
Bubble Chamber Planning Meeting
Upgraded Injector Test Facility
Injector –Linac Status & Schedule E. Bong LCLS FAC October 12, 2006
Upgraded Injector Test Facility - UITF
UITF MPS system requirements
Upgraded Injector Test Facility
A. Freyberg Aug 2016 ECT’16 =>
Electron Beam Systems ETC and Methodology
Uses of UITF 10 MeV spin-polarized electron accelerator, beam current up to 100 uA M. Poelker December 12, 2018.
Carlos Hernandez-Garcia Don Bullard February 2, 2017
Electron Gun UP (EGUP) Plan
X-Ray Endstations Update
Upgraded Injector Test Facility
LCLS Injector System Overview D. H
Installation Status & Operational Readiness Process
Electron Beam Systems ETC and Methodology
UITF Conduct of Operations Review
QCM and C50-12 Status Update
Presentation transcript:

UITF – Upgrade Injector Test Facility Deliverables/Milestones Beam on HDIce by August 2016 (nA current level at ~ 10 MeV) Staffing Critical Skills needed NOW: Facilities, Cryo including ODH assessment, Mechanical Design, Safety System Group for ODH, Ops Software Update since last meeting Monthly meetings with Mont, on-going Cave1 north concrete wall demolition complete Accelerator design sufficiently complete to start building the keV beamline Shaun Gregory has started the MeV beamline design Cave1 cleared out, ready for Survey and Alignment Consensus achieved on entry/exit labyrinth from shielding point of view We realized we might have unwanted ODH2 conditions. Mat Wright now performing formal ODH assessment, which will include recommendations (?). Suspect we must revisit Cave2 ceiling design, to provide a passive escape path for helium gas Stairway to top of Cave1 – PR has been awarded Carlos and Don Bullard are back – they can focus on 350kV gun Continued progress on “stretch goals”: RF control modules, trim cards, quad magnets, BPMs (and staying within FY15 budget) Division Resource Planning and Coordinating

Concrete demolition complete

Division Resource Planning and Coordinating Cave 1 cleared out in the queue for Survey and Alignment Division Resource Planning and Coordinating

Ready to build the keV beamline 80/20 girder has been ordered, new gun table to straddle trench, 400kV gun HV power supply in house, waiting for SF6 tank which was evaluated by Tommy Hiatt, method identified to pressure-vessel certify the HV receptacle Survey and Alignment to add monuments, they will tell us where to put the gun, the 80/20 stand, and the ¼ CM

Shaun Gregory has started the MeV beamline design (we think the MeV portion of accelerator will be easier to design than keV portion) Division Resource Planning and Coordinating

Interior Page Design 2

“Shed” triple-point protection Doped insulator SF6 R350 epoxy receptacle Revisit one of our successful test configurations – polish the shed and test with actual gun electrode Use a large doped insulator purchased by FEL: Danny Machie working on design

UITF – Upgrade Injector Test Facility To-do list for next 30 days Setup the electronics racks above Cave1 Agree on layout, RadCon to approve it Installation Group (Neal Wilson and company) to build it Need a temporary stairway to access the top of Cave Provide electrical requirements to Facilities/Jason Willoughby Obtain the formal ODH assessment, use it to provide Tom Renzo information relevant to Cave2 ceiling design. Modifications to Cave1 ceiling required? Facilities should remove utilities on Control Room exterior wall (window air conditioner, fire, electric), so that Walter Kehlner can move more concrete block into position to erect the perimeter of Cave2 Installation Group to install unistrut along east wall, for attaching utilities. Installation Group and Facilities to begin attaching utilities to this wall: LCW, GN2, compressed air, electric, lighting, fire suppression Move the ¼ CM into Cave1 or Cave2 Apply high voltage to gun with shed electrode at FEL Gun Test Stand Need to make some headway on Bob May’s EHS&Q task list Division Resource Planning and Coordinating

There’s enough LHe in UITF to completely displace all the air in the room. We don’t want the hassle of ODH2 conditions. Can’t rely on active ventilation, need adequate passive ventilation….

Electronics Racks above Cave1 Fix the design Finalize electrical requirements Build it, populate the racks

UITF – Upgrade Injector Test Facility Issues/Concerns that could affect on-time delivery Can Cryo provide plumbing soon? Begin work on He recovery system for HDIce? Want to leave space for them to do their work but also want to start “filling up the cave” now Designers in short supply Can SSG provide the ODH and PSS systems on schedule? Facilities end-date February 2016 could delay ¼ CM commissioning, gun HV conditioning, and intentional beam generation Impact on CTF, a new LHe User Recommended Mitigation Purchase contract designer We can use portable ODH monitoring system for ¼ CM commissioning Temporary shield wall and OSP could provide a means to commission ¼ CM, condition gun and perhaps make 350kV beam without a completed UITF concrete enclosure and PSS? Preble, K. Davis, Cryo Group have started conversation related to oversubscribed CTF. However, near term solution is likely a scheduling solution. Timing is good for Ops Software, provided we (mostly) duplicate existing CEBAF software controls Division Resource Planning and Coordinating