Christoph Schwanda (HEPHY Vienna) For the Belle II SVD group

Slides:



Advertisements
Similar presentations
A Low Mass On-chip Readout Scheme for Double-sided Silicon Strip Detectors 13th February 2013 C. Irmler, T. Bergauer, A. Frankenberger, M. Friedl, I. Gfall,
Advertisements

ATLAS SCT Endcap Detector Modules Lutz Feld University of Freiburg for the ATLAS SCT Collaboration Vertex m.
Electrical QA Markus Friedl (HEPHY Vienna) IPMU, 19 March 2012.
Belle-II Meeting Nov Nov Thomas Bergauer (HEPHY Vienna) Status of DSSD Sensors.
The Silicon Vertex Detector of the Belle II Experiment
Milestones and Schedule of SVD Construction Markus Friedl (HEPHY Vienna) on behalf of the Belle II SVD Collaboration BPAC October 2012.
Summary of the SVD session 19 March 2009 T. Tsuboyama (KEK)
The Origami Chip-on-Sensor Concept for Low-Mass Readout of Double-Sided Silicon Detectors M.Friedl, C.Irmler, M.Pernicka HEPHY Vienna.
The LHCb Inner Tracker Marc-Olivier Bettler SPS annual meeting Zürich 21 February 2007.
Striplet option of Super Belle Silicon Vertex Detector Talk at Joint Super B factory workshop, Honolulu 20 April 2005 T.Tsuboyama.
The AMS-02 detector is based on a large acceptance (~0.5 m²sr) and high sensitivity spectrometer composed by a super-conducting magnet (0.8 T), cooled.
The LHCb Inner Tracker LHCb: is a single-arm forward spectrometer dedicated to B-physics acceptance: (250)mrad: The Outer Tracker: covers the large.
Construction and Performance of a Double-Sided Silicon Detector Module using the Origami Concept C. Irmler, M. Friedl, M. Pernicka HEPHY Vienna.
Performance of the DZero Layer 0 Detector Marvin Johnson For the DZero Silicon Group.
19 November 2009 Christian Irmler (HEPHY Vienna) APV25 and Origami Scheme 4 th Open Meeting of the Belle II Collaboration.
SVX4 chip 4 SVX4 chips hybrid 4 chips hybridSilicon sensors Front side Back side Hybrid data with calibration charge injection for some channels IEEE Nuclear.
18 November 2010 Immanuel Gfall (HEPHY Vienna) SVD IR Mechanics 7 th B2GM.
27 January 2010 Immanuel Gfall (HEPHY Vienna) Belle II SVD Mechanics and Cooling DEPFET Meeting Prag.
SVD Mechanics 21th B2GM Florian Buchsteiner (HEPHY Vienna)
18 November 2010 Immanuel Gfall (HEPHY Vienna) SVD Mechanics IDM.
26 April 2013 Immanuel Gfall (HEPHY Vienna) Belle II SVD Overview.
1 Belle II IR 2 Shuji Tanaka KEK Joint Belle II & superB Background meeting 2012//Feb/ 8-9th 1.
Origami Chip-on-Sensor Design: Progress and New Developments 19th September 2012 TWEPP 2012, C. Irmler (HEPHY Vienna) TWEPP 2012, Oxford University.
Installation and operation of the LHCb Silicon Tracker detector Daniel Esperante (Universidade de Santiago de Compostela) on behalf of the Silicon Tracker.
WP9.4 baseline deliverable summary 10 December 2014 Thomas Bergauer (HEPHY Vienna)
Construction and Test of the First Belle II SVD Ladder Implementing the Origami Chip-on-Sensor Design 29 Sept TWEPP 2015, C. Irmler (HEPHY Vienna)
Super-Belle Vertexing Talk at Super B Factory Workshop Jan T. Tsuboyama (KEK) Super B factory Vertex group Please visit
The Belle II Silicon Vertex Detector Florian Buchsteiner (HEPHY Vienna)
Kodali Kameswara Rao TIFR, Mumbai
The Mechanical Structure for the SVD Upgrade
SVD Mechanics Markus Friedl (HEPHY Vienna) BPAC, 26 October 2015.
11 June 2015 Thomas Bergauer (HEPHY Vienna) Belle II SVD beam Test SPS 2015 SPS users meeting.
- Performance Studies & Production of the LHCb Silicon Tracker Stefan Koestner (University Zurich) on behalf of the Silicon Tracker Collaboration IT -
1 FPCCD VTX Work Plan Y. Sugimoto 2010/1/22. 2 FPCCD: Features and R&D issues (1/2) Small pixel size (~5  m) –Sensor development Small size chip; ~6mm.
The Belle II Silicon Vertex Detector assembly and mechanics
10 September 2010 Immanuel Gfall (HEPHY Vienna) Belle II SVD Upgrade, Mechanics and Cooling OEPG/FAKT Meeting 2010.
Origami and PA design 6 February 2012 Christian Irmler (HEPHY Vienna) 1 Common SVD-PXD Meeting.
Comments on ladder structure 5 Feb Toru Tsuboyama.
2 Oct C. Irmler (HEPHY Vienna) BPAC Preparation and SVD Schedule 6 th Belle II VXD workshop.
Technical Design for the Mu3e Detector Dirk Wiedner on behalf of Mu3e February Dirk Wiedner PSI 2/15.
Overview SVD 21 Jan C. Irmler (HEPHY Vienna) 7 th Belle II VXD Workshop, Prague.
Origami and Cooling 24th September 2012 C. Irmler (HEPHY Vienna) Joint PXD and SVD Meeting Göttingen.
Location of SVD Temperature and Humidity Monitors L.Vitale & L.Lanceri INFN & Univ. Trieste 6 th VXD Workshop, 02/10/2014 SVD parallel for discussion Sep.
25th April 2013 C. Irmler (HEPHY), Y. Onuki (IPMU) Ladder Assembly Procedure Belle II – New Collaborators Meeting.
L5 Assembly 10 Sept C. Irmler (HEPHY Vienna) 8 th Belle II VXD Workshop OS5.905.
SVD Status Markus Friedl (HEPHY Vienna) SVD-PXD Göttingen, 25 September 2012.
Status & schedule of ladder parts production Oct. 2, 2014 Koji Hara (KEK)
24 September 2012 Immanuel Gfall (HEPHY Vienna) SVD Status of Mechanics PXD-SVD Meeting Göttingen.
24 September 2012 Immanuel Gfall (HEPHY Vienna) Annekathrin Frankenberger (HEPHY Vienna) SVD Status of Mechanics PXD-SVD Meeting Göttingen.
Schedule 24 September 2012 Christian Irmler (HEPHY Vienna) Joint PXD and SVD Meeting Göttingen.
SVD Slow Control Markus Friedl (HEPHY Vienna) DAQ/SC Kickoff Meeting, 8 November 2012.
Silicon Vertex Detector Schedule 23 July 2012 Christian Irmler (HEPHY Vienna) 12 th Open Meeting of the Belle II Collaboration.
Florian Buchsteiner (HEPHY Vienna)
SVD Electronics Constraints
SVD Introduction Wetzlar SVD-PXD Meeting, 4 February 2013
SVD Overview Christoph Schwanda Institute of High Energy Physics Austrian Academy of Sciences 8th Belle II VXD Workshop September 9-11, 2015 Trieste, ITALY.
Progress with System Integration of the CBM Silicon Tracking Detector
 Silicon Vertex Detector Upgrade for the Belle II Experiment
Update on the SVD construction
7th Belle II VXD Workshop, Prague
IBL Overview Darren Leung ~ 8/15/2013 ~ UW B305.
Report on WP2 Activities
Application of VATAGP7 ASICs in the Silicon detectors for the central tracker (forward part) S. Khabarov, A. Makankin, N. Zamiatin, ,
Katsuro Nakamura Sep. 10, 2015 VXD meeting
PXD Summary Tests PXD9 Pilot Production ASICs Components Plans:
The Silicon Vertex Detector of the Belle-II Experiment
BPAC, 17 October 2017 VXD GND/EMC Markus Friedl (HEPHY Vienna)
Class B Ladder assembly
SVD group organization, schedule, milestones
C. Irmler, M. Friedl, M. Pernicka HEPHY Vienna
Presentation transcript:

Christoph Schwanda (HEPHY Vienna) For the Belle II SVD group WP2 activities – SVD Christoph Schwanda (HEPHY Vienna) For the Belle II SVD group JENNIFER Consortium General Meeting September 22, 2016, QMUL, London UK

Components of the Belle II SVD VXD requirements Fast – to operate in high background environment Better resolution at IP – to compensate reduction of boost wrt. Belle I Radiation hard (up to 100 kGy) Self-tracking capable – to track particles down to 50 MeV in pT Carbon fiber (CF) cone Outer CF shell End flange End rings Ladders Beam pipe PXD (independent sub-detector inside SVD)

SVD ladders L6 Ladder (Kavli IPMU) FWD L5 Ladder 47 FW/BW + spares (4) Layer Ladders (spares) DSSDs / ladder 6 16 (4) 5 12 (3) 4 10 (2) 3 7 (2) 2 SVD ladders L6 Ladder (Kavli IPMU) FWD module FWD Origami +z L5 Ladder (HEPHY) Origami ce 47 FW/BW + spares (4) BWD Origami -z L4 Ladder (TIFR) BWD module L3 Ladder (Melbourne) Cooling pipe FWD module (Pisa) Cooling pipe BWD module (Pisa) Cooling pipe

SVD silicon sensors DSSD (Double-sided Si strip detector) Rectangular sensor (HPK) DSSD (Double-sided Si strip detector) thickness: 320mm p-side strip n-side strip (other side) Sensor thickness = 300-320μm 125mm (large) 60mm (small) 40mm Strip numbers and pitches Trapezoidal sensor (Micron) 3 types of DSSD sensors 41mm Sensors Rectangular (Large) (Small) Trapezoidal # of p-strips 768 p-strip pitch 75μm 50μm 50…75μm # of n-strips 512 n-strip pitch 240μm 160μm p-side strip (other side) 126mm n-side strip thickness: 300mm 61mm

APV25 – front end readout ASIC APV25 chip Specifications # of input channels: 128 ch. shaping time: 50nsec radiation hardness: > 1MGy max heat dissipation: 0.4W necessity of cooling Within acceptance thinned to 100mm for reduction of the material budget APV25 chips in ladder APV25 APV25

“chip on sensor” concept ORIGAMI flex (Si sensor is under the flex) Sensor under ORIGAMI (n-strips) n-strip signals APV25 APV25 APV25 Sensor from other side (p-strips) flip n-strip signals p-strip signals p-strip signals p-strip signals Flex circuit (ORIGAMI flex) is glued onto sensor n-side on an isolation foam APVs are placed directly onto the ORIGAMI flex to minimize the analog path length (capacitive noise) Sensor strips and ORIGAMI flex are connected with Al wire-bonding (φ25mm). Wire bonding with Al wires.

CO2 ladder cooling 2-phase (liquid and gas mixture) CO2 cooling system CO2 cooling pipe in final setup (CAD) Cooling pipes attached on ladders cooling pipe Softtherm APV25 chips 2-phase (liquid and gas mixture) CO2 cooling system Efficient and low mass cooling Simple control of coolant temperature (only with pressure) Small pressure loss in the pipe Thin stainless tube (OD:1.6mm, thickness:0.1mm) used to minimize material Softtherm 86/125 thermal-conductive dielectric pad.

Distributed SVD assembly @HEPHY (Austria): Layer-5 assembly @Kavli IPMU (Japan): Layer-6 assembly Layer-4 assembly by TIFR Assembled Layer-5 ladders to KEK FW/BW DSSDs to HEPHY @KEK (Japan): SVD assembly SVD installation FW/BW DSSDs to IPMU @Univ. of Pisa (Italy): FW and BW DSSD assembly TIFR (India) Assembled Layer-3 ladders to KEK Assembly sites are reviewed by the SVD QC group to guarantee compliance of the local production All parts (quality grade, location) are tracked in a construction data base @Univ. of Melbourne (Australia): Layer-3 assembly

Ladder quality assurance 1. Mechanical precision measurement with CMM Control reference point possitions on DSSD sensors in 3-dimensions 2. I-V curve measurement Confirm the sensor functionality for biasing. 3. b-source (Sr90)/laser measurement I-V curve Hit map Noise map Cluster size distribution S/N ratio distribution

Ladder production status BW FW Now all the ladder assembly sites are in mass-production stage FW/BW DSSD BW: 100% completed FW: 93% completed Layer-3 Ladder 5 out of 7+2 ladders (56%) completed Layer-4 Ladder 3 out of 10+2 ladders (25%) completed Layer-5 Ladder 4 out of 12+3 ladders (27%) completed Layer-6 Ladder 3 out of 16+4 ladders (15%) completed Completion of the ladder production by Nov. 2017 is expected Layer-3 Layer-4 Layer-5 Layer-6

SVD assembly at KEK SVD assembly at KEK is the final step to complete construction of SVD Prototypes of all mount tools are available We will finalize the tools by February 2017 Ladder mount tool CO2 pipe attachment tool Softtherm attachment tool

Beam test at DESY in April 2016 SVD ladders Solenoid magnet SVD+PXD in the box PXD e- beam insert SVD+PXD into magnet SVD + PXD detector setup Apr 2016 2-5 GeV/c e- beam at DESY Simultaneous operation of SVD layers L3 to L6 SVD + PXD combined setup Beam test setup (@ DESY T24/1 hall)

Ladder Performance for Tracking (DESY results) Tracking event display Residual distribution reconstructed track SVD ladders Layer-3 p-strips Layer-3 n-strips preliminary preliminary Consistent with expectation DSSD hit inefficiency (= 1-efficiency) Excellent SVD performance was confirmed during the April 2016 testbeam @ DESY Layer-5 p-strips Layer-5 n-strips preliminary preliminary Single hit efficiencies above 99%

Summary SVD ladder construction is now in full swing Expect to finish by November 2017 SVD assembly at KEK Procedures are now being finalized Final assembly at KEK will start in February 2017 SVD will be ready for integration with PXD by the end of 2017 Full BEAST phase 2 geometry has been successfully tested in DESY in April 2016

backup

Ladder Anatomy (L6 ladder) DSSDs 2 small rectangular (L3) 2-4 large rectangular (L4-6) 1 trapezoidal (L4-6) Origami hybrid APV25 Origami hybrid Flexible circuit to transmit detector signals to the ladder ends APV25 Readout ASIC of the strips PA0 PF2 FlexPA (PA/PF/PB) Flexible circuit to transmit detector signals to the APV25 PF1 AIREX PB2 PA1 PA2 DSSD PA0 Flexible circuit glued on the Origami hybrid to transmit n-side detector signals to the APV25 PB1 AIREX Thermal insulator between the DSSD and APV25 Rib

Ladder production schedule End of L3 production: Sep 2016 End of L6 production: Nov 2017