SVD Status Markus Friedl (HEPHY Vienna) SVD-PXD Göttingen, 25 September 2012.

Similar presentations


Presentation on theme: "SVD Status Markus Friedl (HEPHY Vienna) SVD-PXD Göttingen, 25 September 2012."— Presentation transcript:

1 SVD Status Markus Friedl (HEPHY Vienna) SVD-PXD Göttingen, 25 September 2012

2 What Happened Since February?  Sensors  Micron delivered trapezoidal sensors with new atoll design  Construction database under development  Ladder assembly  Double-origami ladder built at IPMU, Japan  4 construction sites for series production  Mechanics  Design completed for all layers  Cooling  Detail design converging  Mockup tests ongoing  Electronics  DC/DC converters and other parts tested  FADC design completed, layout in progress 24 September 2012M.Friedl (HEPHY Vienna): SVD Status2 Concerns/recommendations In Feb 2012 BPAC report (all addressed)

3 SVD Schedule  In early 2012, a detailed schedule was worked out and is now maintained by Christian  More than 200 unique items with dependencies, duration and responsible persons  MS Project & PDF versions are available at http://www.hephy.at/project/belle/belle2svd/schedule http://www.hephy.at/project/belle/belle2svd/schedule  Present schedule: start of physics run on 30 November 2015 24 September 2012M.Friedl (HEPHY Vienna): SVD Status3

4 24 September 2012M.Friedl (HEPHY Vienna): SVD Status4 Sensors Ladder Assembly Mechanics Cooling Electronics Summary

5 Sensors  HPK  About 70% of sensors delivered already  Micron  3 new wafers (big trapezoidal + baby sensors) delivered in August 2012  Now with atoll type p-stop very similar to HPK design  Sensor tests show excellent quality  Will be tested in beam & irradiated & tested again in October 2012  Construction Database being developed 24 September 2012M.Friedl (HEPHY Vienna): SVD Status5

6 Sensors Milestones  HPK  12 November 2012: L3 sensor order  April 2013: L4-6 sensor delivery to be completed  July 2013: L3 sensor delivery to be completed  Micron  November 2012: beam test & irradiation analysis  3 December 2012: place order with Micron  September 2013: final Micron sensor delivery  Ladder assembly starts in July 2013 24 September 2012M.Friedl (HEPHY Vienna): SVD Status6

7 24 September 2012M.Friedl (HEPHY Vienna): SVD Status7 Sensors Ladder Assembly Mechanics Cooling Electronics Summary

8 Ladder Assembly Sites  Discussion among all parties during summer 2012 B2GM  Plan for sharing of production:  L3: Melbourne  L4: Tata (at CERN due to export restrictions)  L5: HEPHY Vienna  L6: IPMU  We also agreed that it is important to keep some flexibility in our plan, so that one site can help another if trouble/delay occurs 24 September 2012M.Friedl (HEPHY Vienna): SVD Status8

9 Ladder Assembly  Single Origami modules (HEPHY, 2010 and 2011)  Double Origami module (IPMU, 2012)  Both: collaborative effort of HEPHY, IPMU and Tata 24 September 2012M.Friedl (HEPHY Vienna): SVD Status9

10 Ladder Assembly Milestones  Prototype  December 2012/January 2013: full L5 prototype ladder  Thereafter: final optimization of jigs  Series Production  L3 starts in July 2013  L4-6 start in September 2013  Duration 1 year for each layer  SVD Assembly  Starting in September 2014 @ KEK 24 September 2012M.Friedl (HEPHY Vienna): SVD Status10

11 24 September 2012M.Friedl (HEPHY Vienna): SVD Status11 Sensors Ladder Assembly Mechanics Cooling Electronics Summary

12 Mechanics  Detailed design for all layers completed 24 September 2012M.Friedl (HEPHY Vienna): SVD Status12

13 Mechanics: Open Issues  Ladder mount on end rings  Not finalized yet, but converging  Thermal Contact for L3 hybrids  heat pipes look promising 24 September 2012M.Friedl (HEPHY Vienna): SVD Status13

14 Mechanics Milestones  Collaborative support  Regular “brain-storming meetings” with experienced engineers from MPI Munich & DESY (many thanks!)  Machining support by MPI, DESY and Cracow  Mockups  Exist for all parts (some in early stage, others matured)  Precise (close to final) overall SVD mockup to be built at KEK from November 2012 until April 2013 24 September 2012M.Friedl (HEPHY Vienna): SVD Status14

15 24 September 2012M.Friedl (HEPHY Vienna): SVD Status15 Sensors Ladder Assembly Mechanics Cooling Electronics Summary

16 Cooling  Cooling Mockup at DESY  Operated with XFEL CO2 unit (similar to MARCO which will become available by the end of 2012)  Distribution & Routing  Number of lines is defined  First design for manifolds and routing available, to be optimized for available space and cable paths  2 options for transfer lines  Expecting close-to-final state in 2013 24 September 2012M.Friedl (HEPHY Vienna): SVD Status16

17 24 September 2012M.Friedl (HEPHY Vienna): SVD Status17 Sensors Ladder Assembly Mechanics Cooling Electronics Summary

18 Electronics: Front-end  All Origami versions and most other parts (edge hybrids, pitch adapters) are ready  Remaining parts can simply be derived from existing designs and will be ready by the end of 2012  New idea: all barrel sensors to be read out with Origami? 24 September 2012M.Friedl (HEPHY Vienna): SVD Status18

19 Electronics: Junction Box  Junction Box 24 September 2012M.Friedl (HEPHY Vienna): SVD Status19  Rad-hard DC/DC converters instead of regulators  Tested with APV25 hybrids: no noise penalty

20 Electronics: FADC Milestones  FADC  Design completed  Analog & digital level translation boards built and tested OK  Now working on PCB layout  Surrounding components  FADC Controller, Buffer, Backplane  Will be designed after FADC  Full prototype system to be built in Q1/2013  Based closely on existing readout system built in 2007  Big system test with PXD and beam in October 2013 @ DESY 24 September 2012M.Friedl (HEPHY Vienna): SVD Status20

21 Electronics: FTB (DAQ Link)  Firmware development ongoing  Optical link tests at 2.54 and 3.175 Gb/s successful  Second iteration of PCB for minor corrections underway 24 September 2012M.Friedl (HEPHY Vienna): SVD Status21

22 24 September 2012M.Friedl (HEPHY Vienna): SVD Status22 Sensors Ladder Assembly Mechanics Cooling Electronics Summary

23  Lots of progress in all fields  Detailed (and maintained) schedule available on the web  Sensors  all deliveries to be completed in 2013  Ladder assembly  Prototype ladder in early 2013, series production in late 2013  Mechanics  Overall geometry solved, now optimizing details  Cooling  Mockup tests at DESY  Electronics  DC/DC converters tested OK, FADC layout in progress 24 September 2012M.Friedl (HEPHY Vienna): SVD Status23


Download ppt "SVD Status Markus Friedl (HEPHY Vienna) SVD-PXD Göttingen, 25 September 2012."