Miller Driscoll Building Committee Update Tuesday, January 7, 2016 5:00 PM - 7:00 PM Presented by: Turner Construction, CMA 1 Additions & Alterations Miller-Driscoll.

Slides:



Advertisements
Similar presentations
Neighborhood Meeting No.2 Golden Gate Bridge, Highway and Transportation Districts San Francisco Mid-Day Bus Parking Facility Contract No BT-1 March.
Advertisements

Presentation Hampton Wick Infants School Parent & Community Evening Chris Saville, John Chapple & Pete Russell Tuesday 5 th February 2013.
MARPLE NEWTOWN SCHOOL DISTRICT FACILITIES. Maintenance & Small Projects Planned for Summer 2007 New carpet at Worralls office New fencing at Worralls.
17 May, 2011 BOARD PRESENTATION MAY 17, 2011 SUMMER PROJECTS UPDATE.
Update on FCPS Construction/Renovation Projects April 2009.
With the passage of the May 2009 NLISD Bond Election, campuses made improvements and repairs. New flooring in the elementary schools, updated kitchen.
Leestown Middle – Renovation Architect: Lucas/Schwering Architects General Contractor: D.W. Wilburn, Inc. Substantial Completion Date:August, 2010 GC Contract.
WJJ Middle School Facility Study Tri Board Meeting February 5, 2015.
Russell Cave Elementary – Renovation Architect: Pearson & Peters Architects General Contractor: Congleton-Hacker Construction Substantial Completion Date:August,
1 BROOKHAVEN SCIENCE ASSOCIATES Site Preparation Lessons Learned Michael P. Bromfield, Construction Engineer Convention Facilities Advisory Committee Review.
AMBLER BOILER HOUSE REDEVELOPMENT AMBLER BH DEVELOPMENT PARTNERS, LLC RT ENVIRONMENTAL SERVICES, INC.
1 BROOKHAVEN SCIENCE ASSOCIATES Central Chilled Water Facility – Phase II Alan Raphael MPO Project Manager CFAC Committee Review November 9, 2009 Sub-basement/Pipe.
Jess Albino Facility Advisory October 29, 2007 FACILITY ADVISORY COMMITTEE PLENARY CONVENTIONAL FACILITIES UPDATE October.
HIGHLAND PARK BOND WORK The final results will be AMAZING!
Russell Cave Elementary – Renovation Architect: Pearson & Peters Architects General Contractor: Congleton-Hacker Construction Substantial Completion Date:August,
Russell Cave Elementary – Renovation Architect: Pearson & Peters Architects General Contractor: Congleton-Hacker Construction Substantial Completion Date:August,
David McGiven FAC: Construction April 2006 Facility Advisory Committee (FAC) Construction Procurement David.
Stoughton Public Library Feasibility & Design Study Report by CBT January 28, 2011 Current Library Built in 1969Proposed Library for the Future.
1 BROOKHAVEN SCIENCE ASSOCIATES Construction Management Status Steve Sawch Assistant Director for Construction Management NSLS-II Conventional Facilities.
I.Program Update The following summarizes major activities completed or in progress as of September 30, II.Program Budget Summary (Attachment A)
BUILDING PROJECT AND THE FEASIBILITY STUDY August 20, 2012 Wachusett Regional High School MOUNTVIEW MIDDLE SCHOOL.
Board of Education Presentation 2015 Referendum Projects September 9, 2015 Update.
FACILITIES ADVISORY COMMITTEE Facilities Advisory Committee Annual Report.
ESPLOST Savannah-Chatham County Public Schools January 10, 2007.
ST. PETER CLAVER SCHOOL: THE NEW VISION! A FIVE YEAR VISION.
A presentation of The New Georgian Heights Alternative Elementary School for Columbus City Schools Board of Education 2 February 2010.
Project Status Project Phasing Questions 2 As of Today Project released for Bid February 7, 2011 Notice of Bid sent to 80+ Contractors on February 2,
Report to the Board of Trustees Presented by: Ashton Cumberbatch, Bobby Jenkins, and Eliza May November 23, Community Bond Oversight Committee.
Department of Correctional PRESENTATION ON THE DEVELOPMENT OF THE “NEW GENERATION” CORRECTIONAL FACILITY PROTOTYPES DEPARTMENT OF CORRECTIONAL SERVICES.
Sullivan Trail Junior High Pocono Summit, Pennsylvania Andrew Mellow Goals Background Drawings Site Plan Schedule April 13, 2005.
2014 construction bond planning Needs assessment- what are we missing Site visits- in and out of district Safety concerns Life cycle evaluations- where.
SHDH Perimeter Radiation Improvements Town Hall Meeting – June 23, 2015.
TCUSD New K-5 Construction PROJECT UPDATE NOVEMBER 4,
New Building Construction Plan Neighborhood Briefing November 19,
Phase III – SHDH Air Handler Upgrade Project Town Hall Meeting – July 21, 2015.
Campus Plan Roosevelt Island campus > Laboratory of innovation > Open and inviting to the public > Sustainable and energy-efficient.
Wilton Public Schools Town of Wilton, Connecticut Miller-Driscoll School Public Presentation Public Presentation October 14, 2015.
Russell Cave Elementary – Renovation Architect: Pearson & Peters Architects General Contractor: Congleton-Hacker Construction Substantial Completion Date:August,
Salmon River CSD Capital Project Phase II Monthly Status Report March & April 2016.
1 Guinn School Restoration Update Presented by Transportation and Public Works Department February 17, 2009.
Bond Oversight Committee February Time Topic Presenter 6:00 PM Introduction Curt Martin and David Slattery Staff Reports 6:10 PM Finance Karen Wilson.
Miller Driscoll Building Committee Construction Update Thursday April 7, :00 PM - 7:00 PM Presented by: Turner Construction, CMA 1 Additions & Alterations.
Miller Driscoll Building Committee Construction Update Thursday February 4, :00 PM - 7:00 PM Presented by: Turner Construction, CMA 1 Additions &
Building Committee Presentation March 03, MAIN ENTRANCE.
PORT OF TACOMA. Agreement Lincoln Avenue Grade Separation – Utility Relocation Request authorization for the Executive Director to Execute an Agreement.
1 EASTERN MUNICIPAL WATER DISTRICT Public Access Areas Renovation Project Debbie Hoffman, PE Civil Engineer II, Project Engineer July 1, 2015.
Overview of MSBA Building Process and Project Timeline
Overview of MSBA Building Process and Project Timeline
CAM CONSTRUCTION 21st Century School Buildings Plan
Chapin Elementary School
FLCC GENEVA CAMPUS CENTER PROJECT
Pre-Construction Services
Bond Oversight Committee
4 November 2013 LEHIGHTON AREA SCHOOL DISTRICT.
Reach 4 Air Valve Replacements Award of Construction Contracts
Facilities Modernization Program
Organics Waste Processing Facility Construction Progress Update December 15, 2010
Welcome.
Meeting of the LCLS Facilities Advisory Committee
Facilities Projects Update
Mount Vernon Community School
Capital Outlay Workshop
Building & Property Committee 12 December 2018
PUBLIC INFORMATION SESSION
Presentation Overview
Stoughton Public Library
EAST PENNSBORO AREA SCHOOL DISTRICT
Q2 Updates on 2019 Board Priorities
Q2 Updates on 2019 Board Priorities
PROJECT.
Presentation transcript:

Miller Driscoll Building Committee Update Tuesday, January 7, :00 PM - 7:00 PM Presented by: Turner Construction, CMA 1 Additions & Alterations Miller-Driscoll School

Christmas Break Work Summary – Secured the Construction Site with Fencing – Separated the “Peach Core” from the building – Installed temporary walls, Sound Blankets and safety measures on the existing school – Abated asbestos roof flashing at the Driscoll Building where classrooms are being demolished – Abated PCB at the Driscoll Building where classrooms are being demolished 2

3 Phasing Plan Miller-Driscoll Phase 1a Demolition of Peach Core December 2015 to January 2016 Building Demolition

Unknown Existing Conditions – Phone Lines to Hedgies & Lady Bug Cottages – Fiber Line to the Kitchen for Chartwells use – Frozen Pipe in Hallway of Hedgies Cottage – Neighbor concerns with site lines 4 Additions & Alterations Miller-Driscoll School

5 Frozen Pipe Fiber Line for Café

Neighbor Sight Lines 6 Additions & Alterations Miller-Driscoll School Existing Condition Current Condition Condition Location

7 Additions & Alterations Miller-Driscoll School Peach Core DemolitionSound Blankets

8 Additions & Alterations Miller-Driscoll School Temporary Wall InstallationDemolition of Driscoll Classrooms

Project Contractor Status – Last 9 contracts: – Executed by Contractors – 6 – Executed by the Town – 3 – Remaining Contracts to be executed by Contactors – 3 9 Additions & Alterations Miller-Driscoll School

Material Testing Agency Proposals – Six Testing Agencies Invited to Bid – Four Testing Agencies Bid Independent Material Testing Laboratories Inc. Special Testing Laboratories Test-Con Incorporated Tri State Materials Testing Lab, LLC – Recommend Special Testing Laboratories – Estimated Cost of Material Testing = $133,000 – Budget for Material Testing = $145,000 10

11 Additions & Alterations Miller-Driscoll School Material Testing Agency Proposals

12 Additions & Alterations Miller-Driscoll School

Critical Schedule Milestones – Complete Demolition of Peach Core – PCB Removal February Break to – Concrete Footings begin – Structural Steel Start – FFE Review Committee – Start Planning for the Summer Renovation 13 Additions & Alterations Miller-Driscoll School

Public Out Reach – Parent Committee Mtg – Teacher Meet & Greet on – Administration Communication 14