Presentation is loading. Please wait.

Presentation is loading. Please wait.

Bond Construction Update Facilities Advisory Committee Long Beach Community College District March 3, 2010 EDUCATE  ENGAGE  EMPOWER 1.

Similar presentations


Presentation on theme: "Bond Construction Update Facilities Advisory Committee Long Beach Community College District March 3, 2010 EDUCATE  ENGAGE  EMPOWER 1."— Presentation transcript:

1 Bond Construction Update Facilities Advisory Committee Long Beach Community College District March 3, 2010 EDUCATE  ENGAGE  EMPOWER 1

2 Agenda Latest Completed Construction Projects LAC South Quad Complex (January 2010) PCC Industrial Tech Phase 1 (January 2010) Los Coyotes Property Upgrades (December 2009) Bldg. F - Conversions of rooms F104 and F106 to new classroom space. (November 2009) Bldg. G and H – Repainting (November 2009) Current & Upcoming Construction Projects LAC Building A, Student Services Retrofit LAC Math Technology Building LAC Parking Structure LAC Building O Complex LAC Infrastructure Improvements LAC Building I (Bookstore) LAC Building I (Bookstore) PCC MDAB (Multi-Disciplinary Academic Building) PCC Building CC Retrofit District Wide – Electronic Signage Plan Upcoming Projects Planned Phasing of Future Projects Q & A 2

3 Latest Completed Construction Projects Space includes Approx. 68,000 ASF 32 modern classrooms and labs 38 faculty offices Executive offices Multipurpose room State of the art Board Room South Quad Complex – Measure E 2002 3

4 Latest Completed Construction Projects Modern facility houses Welding Department and other trade programs Replaces existing antiquated structures New Northern face of the campus PCC Industrial Technology Center Phase 1 Measure E 2002 4

5 Current and Upcoming Construction Projects LAC Building A – Student Services Retrofit Measure E 2008 5 Plans submitted to DSA September 2009 Adds 6,500 Sq. Ft. to existing building Will house A&R, Counseling, Health Services, Cashier, Transfer Ctr., etc. Estimated start of construction end of Fall 2010

6 Current and Upcoming Construction Projects Completed Schematic Design Will house Math and Culinary Arts instructional program as well as Reprographics Estimated start of construction Winter 2013 LAC Math Technology Building – Measure E 2008 6

7 Current and Upcoming Construction Projects LAC Parking Structure – Measure E 2008 7 Spaces for 900 Vehicles Photovoltaic Electrical Generation Array on top level To be located Southeast corner of Lot J adjacent to the Verizon building Outfitted with single-axis tracking system Minimum 450 KW+ output Curriculum building opportunity Exhibit classroom Groundbreaking anticipated March, 2010

8 Current and Upcoming Construction Projects LAC Building O Complex – Measure E 2008 8 Two structures totaling 87,000 square feet Current Occupants: ERD, Foundation, Warehouse Facility, and one leasee Future Occupants: IITS and BMT Potential rental spaces being assessed Anticipated start of construction of building O1 Spring 2010

9 9 LAC Infrastructure Improvement Projects Measure E 2008 Current and Upcoming Construction Projects Project to be completed in a phased construction schedule Total annual estimated savings of 1.5 million Kwh Project started Fall 2009. Anticipated completion Summer 2011 Upgrades include; Reclaimed Water, Domestic Water, Data, etc. Majority of existing building HVAC systems to be connected to new infrastructure Landscaping upgrades to be implemented in conjunction with infrastructure project phasing

10 Current and Upcoming Construction Projects 10 Add additional 4,000 square feet to existing building Architecture to match LAC Mediterranean Theme Submitted for DSA review Construction scheduled for Summer 2010 LAC Building I - Measure E 2008

11 Current and Upcoming Construction Projects PCC MDAB (Multi-Disciplinary Academic Building) - Measure E 2002 11 Received reviewed plans from DSA. Currently in construction drawing technical review phase Install portables for swing space at PCC Spring/Summer 2010 Anticipated start of MDAB construction Summer 2010 Project to be completed in two phases

12 Current and Upcoming Construction Projects PCC Building CC Retrofit - Measure E 2008 12 To be designed by Hill Partnership Architects Houses the Fitness Center, Gymnasium, Weight Room, and Faculty and Staff Offices Swing space to be located on PCC Campus (Bldg. GG) To be completed concurrently with MDAB project phase 2 Anticipated start of construction Summer 2011

13 Current and Upcoming Construction Projects District Wide – Electronic Signage Plan Measure E 2008 Measure E 2008 13 District Wide Signage Plan complete Final site locations determined Construction bids received/NTP to be issued mid-March Anticipated construction completion of Marquee Signs Fall 2010

14 LAC Facility Site Plan l i b e r a l a r t s Liberal Arts Campus Site Plan

15 PCC Facility Site Plan p a c i f i c c o a s t Pacific Coast Campus Site Plan

16 Current and Upcoming Construction Projects 16 LAC Expansion of Building I (Awaiting DSA approval)  Bookstore swing space to be located West of J building. Relocate Bond Management Team Offices to O Building (Community Outreach and Services Facility) and removal of W trailers (Fall 2010)  Increase parking at Faculty and Lew Davis St. IITS relocation to O building Bldg. K – Roof extension over Kiln area Bldg. J – Theater lighting control panel replacement Bldg. E – Renovation upgrades CDC – new carpet installation Installation of Monument Signs at Conant/Clark and Bldg. O PCC Bldg. JJ – Add new landscaping around perimeter MDAB swing space preparation Install exterior lighting at Tech1 Demolition of UU and VV Installation of Monument Signs PCH/Walnut and 20 th /Walnut Upcoming Projects

17 Planned Phasing of Future Projects 17 2009-10 Begin infrastructure construction – Fall 2009  Master landscaping implementation will follow this project Parking Structure – groundbreaking anticipated March 2010 Building O2 occupancy scheduled  BMT and IITS – Fall 2010 Install portables for swing space at PCC – Spring/Summer 2010 Begin construction of Buildings DD and EE at PCC  Anticipating Summer 2010 start Anticipating swing space move for Building A at LAC – Summer 2010 Marquees complete – Fall 2010

18 Planned Phasing of Future Projects 18 2010-11 Begin construction of Building I (Bookstore) and move to portable swing space – Summer 2010 Retrofit completion of Building Z – Spring 2010 Begin construction of Building A at LAC – Fall 2010 Begin Schematic Design for Buildings C and F at LAC  Submit plans to DSA no later than Summer 2011

19 Planned Phasing of Future Projects 19 2011-12 Infrastructure project complete at LAC – Summer 2011 Submit plans to DSA for Math/Technology Building at LAC – Summer 2012 Construction completion of Buildings DD and EE at PCC – Summer 2011 Begin construction of Buildings AA, BB and CC at PCC – Summer 2011 Anticipated construction completion of Building I (Bookstore) at LAC – Fall 2011 Anticipated construction completion of Parking Structure at LAC – Spring 2012

20 Planned Phasing of Future Projects 20 2012-13 Move Buildings C and F programs into Swing Space (M/N Building) and begin construction – Summer 2012 Anticipated Construction completion of Building A at LAC – Summer 2012 Submit plans to DSA for M/N Building at LAC and Building MM (Phase 1) at PCC – Summer 2012 Begin Schematic Design for Building P at LAC and Building MM (Phase 2) at PCC – Summer 2012  Submit to DSA – Spring 2013 Begin construction of Math/Technology Building at LAC – Winter 2013

21 Planned Phasing of Future Projects 21 2012-13 (continued) Begin Schematic Design for Building D and E renovations – Fall 2013 Anticipated Construction completion of Buildings AA, BB and CC at PCC – Spring 2013

22 Planned Phasing of Future Projects 22 2013-14 Anticipated Construction completion of Buildings C and F at LAC – Fall 2013 Begin construction of Buildings M/N at LAC and MM (Phase 1) at PCC – Fall 2013 Submit plans to DSA for Buildings D and E renovations at LAC – Fall 2013 Schematic design for Performing Arts Building (G & H) and Building R at LAC – Spring 2014

23 Planned Phasing of Future Projects 23 2014-15 Anticipated Construction completion of Math/Technology Building at LAC – Summer 2014 Begin construction on Buildings D and E at LAC – Fall 2014 Submit plans to DSA for Performing Arts Building and Building R (Gym) at LAC – Spring 2015  Anticipate construction start – Spring 2016 Anticipated construction completion of Buildings M/N at LAC and MM at PCC – late Spring 2015 Begin construction on Buildings P at LAC and MM (Phase 2) at PCC – Spring 2015

24 QUESTIONS & ANSWERS EDUCATE  ENGAGE  EMPOWER 24


Download ppt "Bond Construction Update Facilities Advisory Committee Long Beach Community College District March 3, 2010 EDUCATE  ENGAGE  EMPOWER 1."

Similar presentations


Ads by Google