Presentation is loading. Please wait.

Presentation is loading. Please wait.

Bond Construction Update Citizens Oversight Committee Long Beach Community College District April 18, 2011 EDUCATE ENGAGE EMPOWER 1.

Similar presentations


Presentation on theme: "Bond Construction Update Citizens Oversight Committee Long Beach Community College District April 18, 2011 EDUCATE ENGAGE EMPOWER 1."— Presentation transcript:

1 Bond Construction Update Citizens Oversight Committee Long Beach Community College District April 18, 2011 EDUCATE ENGAGE EMPOWER 1

2 Agenda Completed Construction Projects LAC Parking Structure LAC Building O Complex PCC Walnut Ave. Arrival Court District Wide – Monument Signs Current Construction Projects LAC Building A – Student Services Retrofit LAC Infrastructure Improvements Project and District Wide – Energy Efficiency Project LAC Building I (Bookstore) LAC South Walkway Extension LAC W Trailers Demo LAC Master Landscape PCC MDAB (Multi-Disciplinary Academic Building) PCC Tech1 (Sheet Metal) Upcoming Construction Projects PCC Building CC Retrofit Q & A 2

3 Completed Construction Projects LAC Parking Structure – Measure E 2008 3 Spaces for 893 vehicles Solar generation system is commissioned and operational Project is complete and being used for student parking

4 Completed Construction Projects LAC Building O Complex – Measure E 2008 4 Two structures totaling 87,000 square feet Occupants for Building O2 are Foundation, ERD, LBNP and ALCI IITS and BMT are moved in, Warehouse Facility moving Project is complete with some punch walk items left

5 Completed Construction Projects 5 UU/VV demo completed Site converted to a parking lot April 4 th, 2011 PCC Walnut Ave. Arrival Court - Measure E 2008

6 Completed Construction Projects District Wide – Monument Signs Measure E 2008 Measure E 2008 6 District Wide Monument Signs Locations: LAC-Clark/Conant – completed January 8, 2011 PCC-20 th /Walnut Ave. – Completed March 30, 2011 Installation of building designators for LAC Bldg. O1 and O2 completed LAC Bldg. Designator LAC Monument Sign PCC Monument Sign

7 Current Construction Projects LAC Building A – Student Services Retrofit Measure E 2008 7 New home for A&R, Counseling, Health Services, Cashier, Transfer Center Project currently in demolition and structure upgrade Construction fence and temporary walkways complete End of construction anticipated Summer 2012

8 8 LAC Infrastructure Improvement Project and District Wide Energy Efficiency Project Measure E 2008 Current Construction Projects Total annual estimated savings of 1.5 mil. Kwh Project started Fall 2009; currently hydro seeding all affected areas(All phases) Majority of existing building HVAC systems to be upgraded and connected to the Central Plant Buildings C,D, G,H, & J are connected Buildings B and E will be scheduled by end of April Exterior lighting and controls upgrades All parking lots north of Lew Davis are on new system New Reclaimed Water tie-ins to irrigation connected New gas lines installed for Buildings B, C, D, E, G, H, J, M, N, and P New domestic lines installed for Buildings B, C, D, E, F, G, H, I Trailers, J, K,L, M, N, P Anticipated end of construction Winter 2011

9 Current Construction Projects 9 Adds additional 4,000 square feet to existing building Architecture to match LAC Mediterranean Theme G2K Construction working on demolition and utilities End of Construction anticipated Fall 2011 LAC Building I - Measure E 2008

10 Current Construction Projects LAC South Walkway Extension Measure E 2008 Measure E 2008 10 99% complete Palm trees to be replaced May 2011 Continues Master Plan pedestrian corridor

11 Current Construction Projects 11 Green Giant Construction has removed old W trailers Grading of lot to commence in this month Project will address storm run off issues with bio swales Site to be converted to a parking lot Estimated project completion Summer 2011 LAC W Trailers Demo - Measure E 2008

12 Current Construction Projects 12 Currently in Design Phase Quad areas North and South areas of Bldg. A bid Winter 2012 Remaining areas designed at 25% Scope includes new hardscape/landscape and pedestrian pathways LAC Master Landscape - Measure E 2008

13 Current Construction Projects PCC MDAB (Multi-Disciplinary Academic Building) Measure E 2002 and 2008 13 MDAB building remodel project Phase 1 of 2 currently under construction Project currently in demolition and structural reinforcement Phase 1 Project to be completed Summer 2012

14 Current Construction Projects 14 Currently in bid process Construction to start Summer 2011 Projected to be completed before Fall 2011 PCC Tech 1 (Sheet Metal) - Measure E 2008

15 Upcoming Construction Projects PCC Building CC Retrofit - Measure E 2008 15 Houses the Fitness Center, Gymnasium, Weight Room, and Faculty and Staff Offices Swing space located on PCC Campus (Bldg. GG) Approved by DSA on 1/27/11. Currently in bid process To be completed concurrently with MDAB project phase 1 Anticipated end of construction 2012

16 l i b e r a l a r t s Liberal Arts Campus Site Plan

17 p a c i f i c c o a s t Pacific Coast Campus Site Plan

18 QUESTIONS & ANSWERS EDUCATE ENGAGE EMPOWER 18


Download ppt "Bond Construction Update Citizens Oversight Committee Long Beach Community College District April 18, 2011 EDUCATE ENGAGE EMPOWER 1."

Similar presentations


Ads by Google