April 29, 2004 Project Status Meeting Liang Y. Hsia, P.E. ITS Engineer Administrator Florida Department of Transportation.

Slides:



Advertisements
Similar presentations
Current Status of the FDOT SunGuide SM Software Project Robert W. Heller, Ph.D. March 16, 2005.
Advertisements

FDOT Central Office ITS Software Update
FDOT District 6 ITS Project Update Manuel Fontan, E.I. ITS Project Manager.
HOW TO MAKE A CLIMATE GRAPH CLIMATE GRAPHING ASSIGNMENT PT.2.
Planning a Mentoring Program A CALENDER FOR A FIRST-YEAR TEACHERS’ PROGRAM.
ISSUES TO CONSIDER IN YOUR PROJECT This is a short presentation from issues discussed in a meeting of MCS3 on Tues 2 nd March 2004.
Statewide Transportation Management Center Software Library System Status Meeting February 17, 2004.
SunGuide SM Software Development Project Status Meeting February 23, 2005 CDRL
1 ITS America Palm Springs, CA June 6, 2007 SunGuide SM Software – Florida's ITS Software ITS America Palm Springs, CA June 6, 2007 Trey Tillander, P.E.
FDOT District 1 ITS Project Update Katherine Duvall ITS Project Manager.
SunGuide SM Software Development Project Status Meeting March 9, 2004.
SunGuide SM Software Development Project Status Meeting (via teleconference) October 4, 2005 CDRL
Statewide Transportation Management Center Software Library System (SunGuide SM ) TIM & SunGuide SM Coordination Meeting October 21, 2004 Orlando, Florida.
SunGuide SM Software: Development Status Robert W. Heller, Ph.D. July 14, 2004.
SunGuide SM Software Development Project Status Meeting December 7, 2004.
SunGuide SM Software Development Project Test Readiness Review (TRR) Meeting November 1, 2005.
SunGuide SM Software Development Project Status Meeting July 13, 2004.
WORD JUMBLE. Months of the year Word in jumbled form e r r f b u y a Word in jumbled form e r r f b u y a february Click for the answer Next Question.
Section Events IES Annual Planning/Reporting District Events July New Officers and Board of Managers Aug President to Schedule Section BOM Yearly Meeting.
SunGuide SM Software Development Project Status Meeting May 10, 2005 CDRL
SunGuide SM Software Development Project Status Meeting November 9, 2004.
Constellation Space Transportation Planning Office July 30, 2009.
SunGuide SM Software Development Project Status Meeting April 29, 2004.
SunGuide SM Software Development Project Status Meeting October 13, 2004.
December 16, :00 – 2:45. MPM Team Agenda 1.Review of MPM Program and Team 2.Consensus items document 3. Upcoming activities 4. Discussion.
2011 Calendar Important Dates/Events/Homework. SunSatFriThursWedTuesMon January
The National Grants Partnership March 11, 2008 Michael Pellegrino
SunGuide SM Software Development Project End of the Year ITS Working Group Meeting December 7, 2005.
FDOT Annual ITS Working Group Meeting ITS Updates.
July 2007 SundayMondayTuesdayWednesdayThursdayFridaySaturday
Finance Department Environmental Services City of Superior Superior Water Light & Power Wastewater Billing.
Finance Department Environmental Services
Jan 2016 Solar Lunar Data.
Baltimore.
SunGuideSM Software: Development Status Steven W. Dellenback, Ph. D
Broward County Consolidated Communication Committee Update
RC Ohio Valley Region Strategic and Annual Planning Process January – September 2016 Notes Fr John says greeting and reflects on 75 anniversary and then.
80-Hour SHARP Certification Course Schedule
BUSINESS OWNER MEETING
Agenda Time Item Lead 10:00 – 10:05 Introductions Liang Hsia
13-block rotation schedule

I.E.S. Universidad Laboral
Due Dates subject to change. Watch for dashboard updates.
Irregularities in DoRIS
Q1 Q2 Q3 Q4 PRODUCT ROADMAP TITLE Roadmap Tagline MILESTONE MILESTONE
FY 2019 Close Schedule Bi-Weekly Payroll governs close schedule
PCS Day - Feedback 23th November 2016, Vienna.

GANTT CHART can be used for scheduling generic resources as well as project management. They can also be used for scheduling production processes and.
SunGuideSM Software Development Project Status Meeting and Demonstration April 5-6, 2005 CDRL

Irregularities in DoRIS
Omnibus IV Contract Overview Elieen Emond Contract Specialist
Text for section 1 1 Text for section 2 2 Text for section 3 3
Text for section 1 1 Text for section 2 2 Text for section 3 3
Text for section 1 1 Text for section 2 2 Text for section 3 3
Text for section 1 1 Text for section 2 2 Text for section 3 3
Q1 Q2 Q3 Q4 PRODUCT ROADMAP TITLE Roadmap Tagline MILESTONE MILESTONE
JUNE 2010 CALENDAR PROJECT PLANNING 1 Month MONDAY TUESDAY WEDNESDAY
Text for section 1 1 Text for section 2 2 Text for section 3 3
Text for section 1 1 Text for section 2 2 Text for section 3 3
Text for section 1 1 Text for section 2 2 Text for section 3 3
Text for section 1 1 Text for section 2 2 Text for section 3 3
Text for section 1 1 Text for section 2 2 Text for section 3 3
PLAYMATES LEARNING CENTER CALENDAR
Budget Planning Calendar
Q1 Q2 Q3 Q4 PRODUCT ROADMAP TITLE Roadmap Tagline MILESTONE MILESTONE
2015 January February March April May June July August September
Presentation transcript:

April 29, 2004 Project Status Meeting Liang Y. Hsia, P.E. ITS Engineer Administrator Florida Department of Transportation

SunGuide SM Software Project Licenses Licenses Schedule Schedule

Software License Issues SwRI / FDOT LicenseSwRI / FDOT License –License executed before the contract started. –TxDOT informed SwRI on January 22, 2004 that TransGuide software was on “hold”. –License amended on April 12, 2004 (to support District 2 and name change) For a FDOT / TxDOT partnership to occur two things are needed:For a FDOT / TxDOT partnership to occur two things are needed: –MOU: *FDOT provided TxDOT with comments and legal opinion on March 2, 2004 *TxDOT Provided FDOT with updated draft MOU –TxDOT Software License (solves TransGuide license issue) *TxDOT provided FDOT with a draft license & MOU on March 16, *FDOT provided recommendation to TxDOT on April 12, *Al Kosik of TxDOT to address license the week of April 19, 2004

Software License Issues FDOT / WSDOT Term of Use (TOU):FDOT / WSDOT Term of Use (TOU): –WSDOT provided FDOT with standard TOU on February 11, –FDOT provided recommendation on to WSDOT on March 13, FDOT / MDX Joint Program Agreement (JPA)FDOT / MDX Joint Program Agreement (JPA) –FDOT provided MDX with preliminary JPA on December 3, 2003.

District 4 Broward County RTMC

District 4 Schedule Jun 2004 District 4 Moves Equipment to New TMC; SunGuide SMJun - Jul, 2004 SunGuide SM Software Team performs Milestone Demonstration; SunGuide SMNov 2004 SunGuide SM Software Team setup the District 4 software;

District 4 Schedule SunGuide SMDec 2004 SunGuide SM Software Team Provides TMC Operators with Software Training; Dec Jan 2005 CCTV / video switch solution to be selected; and Jan 2005 District 4 TMC Grand Opening.

District 6 RTMC

District 6 Schedule Jun 25, 2004 New TMC Grand Opening; Jul 2005 I 95 Package B Project Completion; Jun 2005 Ramp Metering Subsystem To Be Installed and Tested SunGuide SMAug 2005 SunGuide SM Software Release 2a Deployment Oct 1, 2005 Ramp Metering System Deployment

Miami-Dade Expressway (MDX) Authority

MDX Schedule 04/07/2003MDX Sent Letter to ITS Office About Participating in SunGuide SM Project 04/25/2003FDOT Responded to MDX ‘s Letter Welcoming MDX’s Participation 12/03/2003FDOT Provided MDX With A Draft Joint Program Agreement May 2004 MDX TMC Systems Manager Is Scheduled To Be On Board; SunGuide SMSep 2005 SunGuide SM Software Release 2a Deployment at MDX

District 7 RTMC

District 7 Schedule Nov 2005Building Construction Finish Apr 2006TMC Operation Start

District 2 RTMC

District 5 RTMC

Turnpike RTMC

Turnpike Schedule Mar 2004SunNav Test Apr 2004SunNav Development Sep 2005 Observation of D 4, D 6, MDX C2C Deployment

District 1

District 3

Broward County Lee County Bridge Incident Management City of Aventura

Project Development Team

Center-to-Center (C2C) Communications

C2C Schedule 02/16/2004 C2C Project Team scheduled to complete Interface Control Document (ICD) 02/20/2004 SunGuideSM & C2C Project Coordination Teleconference 03/09/2004 SunGuideSM & C2C Project Coordination Meeting Sep 2005 C2C Deployment Among D4, D6, & MDX

Schedule Summary STMCSLS development team:STMCSLS development team: –Release 1: September 2004 or 5.75 Months after Notice To Proceed for Engineering Change Order No. 1 –Release 2a: August 2005 –Release 2b: November 2005 –Three Milestone Demo: Anytime after June,