SunGuide SM Software Development Project Test Readiness Review (TRR) Meeting November 1, 2005.

Similar presentations


Presentation on theme: "SunGuide SM Software Development Project Test Readiness Review (TRR) Meeting November 1, 2005."— Presentation transcript:

1 SunGuide SM Software Development Project Test Readiness Review (TRR) Meeting November 1, 2005

2 November 1, 2005SunGuide TRR Meeting 2 Agenda TimeItem Lead 1:30 – 1:35Introductions Liang Hsia 1:35 – 1:40Logistics Steve Dellenback 1:40 – 1:55Testing Process Test Procedures Steve Dellenback / Robert Heller 1:55 – 2:00Hot Wash-up Meeting Steve Dellenback 2:00 – 2:15Questions / Comments All

3 November 1, 2005SunGuide TRR Meeting 3 Introductions

4 November 1, 2005SunGuide TRR Meeting 4 Agenda TimeItem Lead 1:30 – 1:35Introductions Liang Hsia 1:35 – 1:40Logistics Steve Dellenback 1:40 – 1:55Testing Process Test Procedures Steve Dellenback / Robert Heller 1:55 – 2:00Hot Wash-up Meeting Steve Dellenback 2:00 – 2:15Questions / Comments All

5 November 1, 2005SunGuide TRR Meeting 5 Logistics Test location: –FDOT Lab Meetings: –Conf Room: B block Break: –C2C Lab Lunch –SwRI Cafeteria Internet: –Available in the lobby (100baseT connection)

6 November 1, 2005SunGuide TRR Meeting 6

7 November 1, 2005SunGuide TRR Meeting 7 Document Status Documents delivered to FDOT over the last month: –Software Requirements Specification (SRS) –Software Integration Plan (SIP) –Software Integration Case Procedures (SICP) –Database Design Document (DBDD) –Software User’s Manual (SUM) –Version Description Document (VDD) –Training Plan (TP) Other deliverables: –Rational RequisitePro database –Source CDs –Installation CDs Outstanding Deliverable: –Software Design Document (SDD)

8 November 1, 2005SunGuide TRR Meeting 8 Agenda TimeItem Lead 1:30 – 1:35Introductions Liang Hsia 1:35 – 1:40Logistics Steve Dellenback 1:40 – 1:55Testing Process Test Procedures Steve Dellenback / Robert Heller 1:55 – 2:00Hot Wash-up Meeting Steve Dellenback 2:00 – 2:15Questions / Comments All

9 November 1, 2005SunGuide TRR Meeting 9 Purpose of TRR Purpose: –Review preparations for testing –Walk through the test procedures at a very high level and determine if anyone has any comments Ground Rules: –Testing will not depart from the written procedures –Any requested “ad hoc” testing will occur after the formal testing process Approvals: –FDOT/SwRI will witness each test case (on “Master SICP”) –At the conclusion, FDOT will sign SICP cover page to acknowledge all tests were executed as written/noted in the “Master SICP”.

10 November 1, 2005SunGuide TRR Meeting 10 Schedule for Testing Date / TimeItemLead November 1 1:30 – 2:00 Test Readiness Review (TRR) Meeting:  Discuss testing process  Review test procedures Steve Dellenback November 1 2:00 – 6:00 Testing using the Software Integration Case Procedures document (“rolling” breaks) SwRI Team November 2 8:30 – 5:00 Testing using the Software Integration Case Procedures document (1 hour lunch and “rolling” breaks) SwRI Team November 3 8:30 – 2:00 Testing using the Software Integration Case Procedures document (1 hour lunch and “rolling” breaks) SwRI Team November 3 2:00 – 3:30 Retest of any previously identified test failuresSwRI Team November 3 3:30 – 4:30 Hot Wash-up Meeting (to discuss testing results) Steve Dellenback / Robert Heller “Free Play” in the lab if we are done early

11 November 1, 2005SunGuide TRR Meeting 11 Test Case Example

12 November 1, 2005SunGuide TRR Meeting 12 Release 1.1 Integration Cases IC-1: Core Processes: –User (AS) –Status Logger (SL) –Executive Handler (EH) –Data Distribution (DD) –Operator Map (OM) IC-2: Dynamic Message Sign (DMS) IC-3: Video (CCTV) IC-4: Transportation Sensor Subsystem (TSS) IC-5: Incident Management (IM) General Requirements

13 November 1, 2005SunGuide TRR Meeting 13 Release 2.0 Integration Cases IC-6: Subsystem Updates: –Graphical User Interface (GUI) –Closed Circuit Television (CCTV) –IM IC-7: Trailblazer IC-8: Safety Barrier (SB) IC-9: Roadway Weather Information System (RWIS) IC-10: Highway Advisory Radio (HAR) IC-11: Ramp Metering Subsystem (RMS) IC-12: Center-to-Center (C2C) IC-13: Web Server (WS) IC-14: Emergency Evacuation (EE) IC-15: Inventory and Maintenance Subsystem (IMS) IC-16: Data Archiving (DA) IC-17: Travel Times (TvT) General Requirements (not attributed to any one IC)

14 November 1, 2005SunGuide TRR Meeting 14 Questions About Test Cases?

15 November 1, 2005SunGuide TRR Meeting 15 Computer Layout

16 November 1, 2005SunGuide TRR Meeting 16 Documents Available in the Lab Paper: –Concept of Operations (ConOps) –Software Requirements Specification (SRS) –Software User’s Manual (SUM) –Functional Configuration Audit (FCA) –Software Integration Plan (SIP) –Software Acceptance Test Plan (SATP) –Software Integration Case Procedures (SICP): master copy and individual copies for all participants –Contractual Documents (Scope of Services, Requirements, ECO #1, draft ECO #1.1) Electronic: –All

17 November 1, 2005SunGuide TRR Meeting 17 Next Steps… (after this week) Deployment to District 6 –Scheduled to start the week of Nov 7 th –Training during the week of Nov 15 th and/or 21 st based on D6 staff availability –Factors to simplify installation: Recent milestone demonstration overcame a number of communication issues SunGuide SM D6 database is fairly mature Future development –Based on FDOT approval –Planned enhancements will be 2.x (no formal FAT)

18 November 1, 2005SunGuide TRR Meeting 18 Test Preparation Document cleanup –Published final versions of Release 2.0 documents Prepared VSS and Clear Case repository of Release 2.0 software (source code and installer) to the FDOT Central Office Test director led several dry runs through the SICP –Anomalies within the SICP corrected –Anomalies within the Release 2.0 software corrected

19 November 1, 2005SunGuide TRR Meeting 19 Project Factoid Development activities (25 months): –Began October 7, 2003 –Ended November 3, 2005 –Initial project schedule requested by FDOT: 25 months –Staff time: 48,577 hours Costs: –Release 1: $4,335,554 (spent $4,321,459) –Release 2: $2,732,303 (projected $2,307,432) –Development under-run: $225K Lines of code: 925K SLOC (generic framework saved SLOCs)

20 November 1, 2005SunGuide TRR Meeting 20 Agenda TimeItem Lead 1:30 – 1:35Introductions Liang Hsia 1:35 – 1:40Logistics Steve Dellenback 1:40 – 1:55Testing Process Test Procedures Steve Dellenback / Robert Heller 1:55 – 2:00Hot Wash-up Meeting Steve Dellenback 2:00 – 2:15Questions / Comments All

21 November 1, 2005SunGuide TRR Meeting 21 Hot Wash-Up Meeting Purpose: –Anomalies identified during testing are discussed and everybody agrees on what happened –Results are captured in a Hot Wash-Up minutes (one set of minutes for the entire week of testing) After the testing period, SwRI will develop a Software Test Reports which contains: –Summary narratives of the test results –Identification of problems or failures –Recommended resolutions of anomalies observed –Copies of witnessed data sheets

22 November 1, 2005SunGuide TRR Meeting 22 Agenda TimeItem Lead 1:30 – 1:35Introductions Liang Hsia 1:35 – 1:40Logistics Steve Dellenback 1:40 – 1:55Testing Process Test Procedures Steve Dellenback / Robert Heller 1:55 – 2:00Hot Wash-up Meeting Steve Dellenback 2:00 – 2:15Questions / Comments All

23 November 1, 2005SunGuide TRR Meeting 23 Questions / Answers