Bond Construction Update Facilities Advisory Committee Long Beach Community College District September 1, 2010 1.

Slides:



Advertisements
Similar presentations
Facilities Improvements and Bond Construction Update Facilities Advisory Committee Long Beach Community College District December 2, 2008 EDUCATE ENGAGE.
Advertisements

Bond Construction Update Citizens Oversight Committee Long Beach Community College District April 21, 2008 BUILDING TOMORROW TODAY Cordoba Corporation.
Bond Construction Update Citizens Oversight Committee Long Beach Community College District July 21, 2008 BUILDING TOMORROW TODAY 1.
Bond Construction Update Citizens Oversight Committee Long Beach Community College District April 20, 2009 EDUCATE ENGAGE EMPOWER 1.
Draft FMP Priorities For Discussion Facilities Committee 3/5/13.
Bond Construction Update Citizens Oversight Committee Long Beach Community College District April 18, 2011 EDUCATE ENGAGE EMPOWER 1.
Bond Construction Update Citizens Oversight Committee Long Beach Community College District November 1, 2007 BUILDING TOMORROW TODAY Cordoba Corporation.
April 14, 2009 Los Angeles Valley College Prop J Master Plan Town Hall Presentation.
BOND PROGRAM UPDATE Long Beach Community College District Citizens’ Oversight Committee Meeting October 11, 2004.
Bond Construction Update Citizen’s Oversight Committee Long Beach Community College District October 2008 EDUCATE  ENGAGE  EMPOWER 1.
BOND PROGRAM UPDATE Building Tomorrow Today Long Beach Community College District Citizens’ Oversight Meeting October 9, 2006.
Bond Construction Update Citizen’s Oversight Committee Long Beach Community College District January 31, 2011 EDUCATE  ENGAGE  EMPOWER 1.
Bond Construction Program Long Beach City College District November 2006.
Bond Construction Update Citizen’s Oversight Committee Long Beach Community College District October 19, 2009 EDUCATE  ENGAGE  EMPOWER 1.
Bond Construction Update Citizen’s Oversight Committee Long Beach Community College District July 20, 2009 EDUCATE  ENGAGE  EMPOWER 1.
MENDOCINO COLLEGE MASTER PLAN Mendocino College Faculty and Staff Presentation December 10, 2008.
Bond Construction Update Citizens Oversight Committee Long Beach Community College District August 8, 2011 EDUCATE  ENGAGE  EMPOWER 1.
PINOLE VALLEY HIGH SCHOOL FACILITIES SUBCOMMITTEE MEETING December 13, 2011.
Bond Construction Update Citizen’s Oversight Committee Long Beach Community College District January 25, 2010 EDUCATE  ENGAGE  EMPOWER 1.
Bond Construction Update Citizen’s Oversight Committee Long Beach Community College District October 25, 2010 EDUCATE  ENGAGE  EMPOWER 1.
Bond Construction Update Citizens Oversight Committee Long Beach Community College District April 25, 2012 EDUCATE  ENGAGE  EMPOWER 1.
Accredited with “Distinction in Performance” St. Clair R-XIII School District.
Bond Construction Update Facilities Advisory Committee Long Beach Community College District September 2, 2008 BUILDING  TOMORROW  TODAY 1.
Bond Construction Update Facilities Advisory Committee Long Beach Community College District April 14, 2010 EDUCATE  ENGAGE  EMPOWER 1.
BOND PROGRAM UPDATE Building Tomorrow Today Long Beach Community College District The Long Beach Rotary Flex Day,March 28, 2007 Flex Day, March 28, 2007.
BOND PROGRAM UPDATE Long Beach Community College District Board of Trustees Meeting July 13, 2004.
Finance and Administration Advisory Group June 30, 2010.
St. Ambrose University Main Campus Planned Institutional District Application December 15, 2011.
Bond Construction Update Citizens’ Oversight Committee Long Beach Community College District January 28, 2008 BUILDING  TOMORROW  TODAY Cordoba Corporation.
BOND PROGRAM UPDATE Long Beach Community College District Citizens’ Oversight Committee Meeting July 12, 2004.
HIGHLAND PARK BOND WORK The final results will be AMAZING!
Bond Construction Program Long Beach City College District March 2007.
Facilities Improvements and Bond Construction Update Facilities Advisory Committee Long Beach Community College District Septmeber 24, 2009 EDUCATE  ENGAGE.
You can achieve 100% Energy Saving WHEN YOU TURN OFF THE LIGHTS.
STAFFORD COUNTY PUBLIC SCHOOLS ENERGY MANAGEMENT PROGRAM 2009 UPDATE Bob Randall CEM,,BEP, CBCP Energy Manager Energy Manager.
1 Fall Convocation Presented by Henry D. Shannon, Ph.D August 11,
Foothill College & Space Science Center Bill Kelly Viron Energy Services (510) ext 13,
Brentwood Union Free School District 2006 Bond Referendum Capital Improvement Program Pool Phase, Phase IA, II, III, and IV. April 28, 2008 Prepared by:
Torrance Unified School District Bond Measure Y Bond Measure Z Quarterly Construction Update September 30, 2009.
Designing and Programming Schools As Community Learning Centers Firestone/Litchfield Community Learning Center Community Update September 27, 2011 Community.
Paradise Valley Community College CLC Update Jacalyn A Askin, Vice President of Administrative Services May 8, 2009.
Facilities Modernization Program Funded by Measure B Project Report April 19, 2010.
10/19/20151 Building a Legacy Rebuilding Providence Public Schools 2008 Q1 Report Volume III.
Bond Expenditure Report Per A.R.S. § (K) 7/1/13 - 6/30/14.
Eden Central School District Board of Education Meeting Eden CSD 2020 Project Update September 16, 2015.
Brentwood Union Free School District 2006 Bond Referendum Capital Improvement Program Pool Phase, Phase IA, II, III, and IV. August 2007 Prepared by:
Bond Construction Update Facilities Advisory Committee Long Beach Community College District November 17, 2010 EDUCATE  ENGAGE  EMPOWER 1.
Bond Construction Update Citizens Oversight Committee Long Beach Community College District October 24, 2011 EDUCATE  ENGAGE  EMPOWER 1.
California State University, Sacramento Facilities Services May 19, 2008.
Bond Construction Update Citizens Oversight Committee Long Beach Community College District January 23, 2012 EDUCATE  ENGAGE  EMPOWER 1.
Facilities Modernization Program Funded by Measure B Project Report September 21, 2015.
 Board of Trustees Meeting June 25,  Topics of Discussion 1. District 5-Year Construction Plan 2. Cost Components of Construction 2.
Bond Construction Update Facilities Advisory Committee Long Beach Community College District April 26, 2010 EDUCATE  ENGAGE  EMPOWER 1.
Bond Construction Update Facilities Advisory Committee Long Beach Community College District April 6, 2011 EDUCATE  ENGAGE  EMPOWER 1.
Bond Construction Update Citizen’s Oversight Committee Long Beach Community College District July 26, 2010 EDUCATE  ENGAGE  EMPOWER 1.
Bond Construction Update Facilities Advisory Committee Long Beach Community College District September 14, 2011 EDUCATE  ENGAGE  EMPOWER 1.
Bond Construction Update Facilities Advisory Committee Long Beach Community College District March 3, 2010 EDUCATE  ENGAGE  EMPOWER 1.
Mt. San Jacinto Community College District Five Year Construction Plan
HCS Energy Master Plan Update
Building Services Summer 2016 Update
Southwestern Community College District Facilities Master Plan and
City of Rifle 2007: Potential Growth.
Facilities Update November 17, 2017
MIRACOSTA COMMUNITY COLLEGE DISTRICT
BOND PROGRAM- Door Lock & Building Access
Facilities Modernization Program
College Council Meeting September 7, 2018
EAST PENNSBORO AREA SCHOOL DISTRICT
Facilities Update Garden Grove Unified School District
Presentation transcript:

Bond Construction Update Facilities Advisory Committee Long Beach Community College District September 1,

Agenda Latest Completed Construction Projects LAC Bldg. J – Theater lighting control panel replacement LAC Bldg. E – Renovation upgrades LAC CDC – new carpet installation PCC Bldg. II – Added new landscaping around perimeter Current & Upcoming Construction Projects LAC Building A, Student Services Retrofit LAC Math Technology Building LAC Parking Structure LAC Building O Complex LAC Infrastructure Improvements and District Wide – Energy Efficiency Project LAC Building I (Bookstore) PCC MDAB (Multi-Disciplinary Academic Building) PCC Building CC Retrofit District Wide – Electronic Signage Plan LAC South Walkway Extension LAC Building P FPP Planned Phasing of Future Projects Q & A 2

Current and Upcoming Construction Projects LAC Building A – Student Services Retrofit Measure E Awaiting DSA Final approval on Structural portion Adds 6,500 Sq. Ft. to existing building Will house A&R, Counseling, Health Services, Cashier, Transfer Ctr., etc. Estimated start of construction end of Fall 2010

Current and Upcoming Construction Projects Completed Schematic Design Will house Math and Culinary Arts instructional program as well as Reprographics Estimated start of construction Winter 2013 LAC Math Technology Building – Measure E

Current and Upcoming Construction Projects LAC Parking Structure – Measure E Spaces for 900 Vehicles Photovoltaic Electrical Generation Array on top level To be located Southeast corner of Lot J adjacent to the Verizon building Outfitted with single-axis tracking system Minimum 450 KW+ output Curriculum building opportunity Exhibit classroom Construction started Summer of 2010 Anticipated end of Construction Fall 2011

Current and Upcoming Construction Projects LAC Building O Complex – Measure E Two structures totaling 87,000 square feet Current Occupants: ERD, Foundation, Warehouse Facility, and one leasee Future Occupants: IITS and BMT Start of construction of Building O1 began April 2010 Anticipated completion October 2010

7 LAC Infrastructure Improvement Project and District Wide Energy Efficiency Project Measure E 2008 Current and Upcoming Construction Projects Project to be completed in a phased construction schedule Total annual estimated savings of 1.5 million Kwh Project started Fall 2009; currently working on phase 6, 9, & 10 Landscaping upgrades to be implemented in conjunction with infrastructure project phasing Majority of existing building HVAC systems to be upgraded and connected to the Central Plant Exterior lighting and controls upgrades in progress Anticipated end of construction Winter 2011

Current and Upcoming Construction Projects 8 Received Final DSA approval Adds additional 4,000 square feet to existing building Architecture to match LAC Mediterranean Theme Currently in Bid Phase Construction scheduled for Fall 2010 Bookstore Swing Space relocated July 2010 LAC Building I - Measure E 2008

Current and Upcoming Construction Projects PCC MDAB (Multi-Disciplinary Academic Building) - Measure E Received Final State (DOF) approval NTP issued on 7/29/10; Contractor mobilizing Installed portables for swing space Summer 2010 Anticipated start of MDAB construction Fall 2010 Project to be completed in two phases

Current and Upcoming Construction Projects PCC Building CC Retrofit - Measure E Currently in DSA for plan check (Structural) Houses the Fitness Center, Gymnasium, Weight Room, and Faculty and Staff Offices Swing space to be located on PCC Campus (Bldg. GG) To be completed concurrently with MDAB project phase 1 Anticipated end of construction 2012

Current and Upcoming Construction Projects District Wide – Electronic Signage Plan Measure E 2008 Measure E District Wide Signage Plan complete for LAC & PCC Daktronics digital signs currently in fabrication Installation of footings to begin on 9/1 Anticipated construction completion of Marquee Signs Fall 2010

l i b e r a l a r t s Liberal Arts Campus Site Plan

p a c i f i c c o a s t Pacific Coast Campus Site Plan

Planned Phasing of Future Projects Begin infrastructure construction – Fall 2009  Master landscaping implementation will follow this project Parking Structure – groundbreaking anticipated May 2010 Building O2 occupancy scheduled  BMT and IITS – Fall 2010 Install portables for swing space at PCC – Summer 2010 Begin construction of Buildings DD and EE at PCC  Anticipating Fall 2010 start Anticipating swing space move for Building A at LAC – Summer 2010 Marquees complete – Fall 2010

Planned Phasing of Future Projects Begin construction of Building I (Bookstore) and move to portable swing space – Summer 2010 Retrofit completion of Building Z – Spring 2010 Begin construction of Building A at LAC – Fall 2010 Begin Schematic Design for Buildings C and F at LAC  Submit plans to DSA no later than Summer 2011

Planned Phasing of Future Projects Infrastructure project complete at LAC – Summer 2011 Submit plans to DSA for Math/Technology Building at LAC – Summer 2012 Construction completion of Buildings DD and EE at PCC – Fall 2011 Begin construction of Buildings AA, BB and CC at PCC – Fall 2011 Anticipated construction completion of Building I (Bookstore) at LAC – Fall 2011 Anticipated construction completion of Parking Structure at LAC – Spring 2012

Planned Phasing of Future Projects Move Buildings C and F programs into Swing Space (M/N Building) and begin construction – Summer 2012 Anticipated Construction completion of Building A at LAC – Summer 2012 Submit plans to DSA for M/N Building at LAC and Building MM (Phase 1) at PCC – Summer 2012 Begin Schematic Design for Building P at LAC and Building MM (Phase 2) at PCC – Summer 2012  Submit to DSA – Spring 2013 Begin construction of Math/Technology Building at LAC – Winter 2013

Planned Phasing of Future Projects (continued) Begin Schematic Design for Building D and E renovations – Fall 2013 Anticipated Construction completion of Buildings AA, BB and CC at PCC – Summer 2013

Planned Phasing of Future Projects Anticipated Construction completion of Buildings C and F at LAC – Fall 2013 Begin construction of Buildings M/N at LAC and MM (Phase 1) at PCC – Fall 2013 Submit plans to DSA for Buildings D and E renovations at LAC – Fall 2013 Schematic design for Performing Arts Building (G & H) and Building R at LAC – Spring 2014

Planned Phasing of Future Projects Anticipated Construction completion of Math/Technology Building at LAC – Summer 2014 Begin construction on Buildings D and E at LAC – Fall 2014 Submit plans to DSA for Performing Arts Building and Building R (Gym) at LAC – Spring 2015  Anticipate construction start – Spring 2016 Anticipated construction completion of Buildings M/N at LAC and MM at PCC – late Spring 2015 Begin construction on Buildings P at LAC and MM (Phase 2) at PCC – Spring 2015

QUESTIONS & ANSWERS 21