Bond Construction Update Facilities Advisory Committee Long Beach Community College District April 6, 2011 EDUCATE  ENGAGE  EMPOWER 1.

Similar presentations


Presentation on theme: "Bond Construction Update Facilities Advisory Committee Long Beach Community College District April 6, 2011 EDUCATE  ENGAGE  EMPOWER 1."— Presentation transcript:

1 Bond Construction Update Facilities Advisory Committee Long Beach Community College District April 6, 2011 EDUCATE  ENGAGE  EMPOWER 1

2 Agenda Completed Construction Projects LAC Parking Structure LAC Building O Complex PCC Walnut Ave. Arrival Court Current Construction Projects LAC Building A – Student Services Retrofit LAC Infrastructure Improvements Project and District Wide – Energy Efficiency Project LAC Building I (Bookstore) LAC South Walkway Extension LAC W Trailers Demo PCC MDAB (Multi-Disciplinary Academic Building) District Wide – Monument Signs Upcoming Construction Projects PCC Building CC Retrofit Q & A 2

3 Completed Construction Projects LAC Parking Structure – Measure E 2008 3 Spaces for 893 Vehicles Solar generation system is commissioned and operational Project is complete and being used for student parking

4 Completed Construction Projects LAC Building O Complex – Measure E 2008 4 Two structures totaling 87,000 square feet Occupants for Building O2 are Foundation, ERD, LBNP and ALCI IITS and BMT are moved in, Warehouse Facility moving Project is complete with some punch walk items left

5 Completed Construction Projects 5 UU/VV demo completed. Site converted to a parking lot April 4 th, 2011. PCC Walnut Ave. Arrival Court - Measure E 2008

6 Current Construction Projects LAC Building A – Student Services Retrofit Measure E 2008 6 New home for A&R, Counseling, Health Services, Cashier, Transfer Center Project currently in demolition and structure upgrade Construction fence and temporary walkways complete End of construction anticipated Summer 2012.

7 7 LAC Infrastructure Improvement Project and District Wide Energy Efficiency Project Measure E 2008 Current Construction Projects Total annual estimated savings of 1.5 mil. Kwh Project started Fall 2009; currently hydro seeding all affected areas(All phases) Majority of existing building HVAC systems to be upgraded and connected to the Central Plant Buildings C,D, G,H, & J are connected Buildings B and E will be scheduled by end of April Exterior lighting and controls upgrades All parking lots north of Lew Davis are on new system New Reclaimed Water tie-ins to irrigation connected New gas lines installed for Buildings B, C, D, E, G, H, J, M, N, and P New domestic lines installed for Buildings B, C, D, E, F, G, H, I Trailers, J, K,L, M, N, P Anticipated end of construction Winter 2011

8 Current Construction Projects 8 Adds additional 4,000 square feet to existing building Architecture to match LAC Mediterranean Theme G2K Construction working on demolition and utlitites End of Construction anticipated Fall 2011 LAC Building I - Measure E 2008

9 Current Construction Projects LAC South Walkway Extension Measure E 2008 Measure E 2008 9 99% complete Palm trees to be replaced May 2011 Continues Master Plan pedestrian corridor

10 Current Construction Projects 10 Green Giant Construction has remove old W trailers Grading of lot to commence in this month Project will address storm run off issues with bio swales Site to be converted to a parking lot Estimated project completion Summer 2011. LAC W Trailers Demo - Measure E 2008

11 Current Construction Projects PCC MDAB (Multi-Disciplinary Academic Building) Measure E 2002 and 2008 11 MDAB building remodel project Phase 1 of 2 currently under construction Project currently in demolition and structural reinforcement Phase 1 Project to be completed Summer 2012

12 Current Construction Projects District Wide – Monument Signs Measure E 2008 Measure E 2008 12 District Wide Monument Signs. Locations:  LAC-Clark/Conant – completed January 8, 2011  PCC-20 th /Walnut Ave. – Completed March 30, 2011 Installation of building designators for LAC Bldg. O1 and O2 completed Estimated construction completion Spring 2011. LAC Bldg. Designator LAC Monument Sign PCC Monument Sign

13 Upcoming Construction Projects PCC Building CC Retrofit - Measure E 2008 13 Houses the Fitness Center, Gymnasium, Weight Room, and Faculty and Staff Offices Swing space located on PCC Campus (Bldg. GG) Approved by DSA on 1/27/11. Currently in bid process To be completed concurrently with MDAB project phase 1 Anticipated end of construction 2012

14 l i b e r a l a r t s Liberal Arts Campus Site Plan

15 p a c i f i c c o a s t Pacific Coast Campus Site Plan

16 QUESTIONS & ANSWERS EDUCATE  ENGAGE  EMPOWER 16