Shutdown 2012 ES&H Friday April 27, 2012J. Anderson Jr. Page 1 Draft Schedule Beam off to Experiments 0000 Monday April 30 th Linac continues operations.

Slides:



Advertisements
Similar presentations
Transition from the Long Shutdown to Hot Checkout: Pre-Hot Checkout Steve Suhring Operability Manager 6/6/13.
Advertisements

Total Loss Monitor Report All experimenters meeting 5/12/14 A. Leveling.
New Radiation Safety Interlock System for the SPring-8 Accelerator Complex C. Saji, M. Toko, T. Matsushita, R. Furuta, H. Hanaki, S. Hashimoto 1), Y. Hashimoto,
Maintenance and Accelerator Support RHIC Run 12. RHIC species change completed: Major works in RHIC: Major works in RHIC: Power supply reconfigure (DO.
Radiation Safety & Compliance External Beam –Electrons (linacs) –Photons (linacs, Gamma Knife) –Protons (Summer 2013) Brachytherapy –Sealed Sources –Radiopharmaceuticals.
July 01, Shutdown Machine Status:  NTF Treatments and Dosimetry as scheduled  Proton Source Commissioning and Studies RFQ Injector.
Proton Plan PMG 7/26/07 E Prebys 1 Proton Plan Status June Eric Prebys.
1 Proton Upgrades at Fermilab Robert Zwaska Fermilab March 12, 2007 Midwest Accelerator Physics Collaboration Meeting Indiana University Cyclotron Facility.
Booster Radiation Damage Facility (RDF) Some History The Radiation Damage Facility originated in the AP4 beam line, used primarily for testing the D0 Vertex.
KICKOFF AS PRESENTED 6/17/11, SEE THIS WEEKS SCHEDULE FOP THE LATEST UPDATE Shutdown Shutdown ‘11.
Gauges and well logging
1 BROOKHAVEN SCIENCE ASSOCIATES Review of May 29 Excursion Bob Casey.
08/24/07Shutdown’07 Week 3 F.G. Garcia1 MTA beam line installation Weekly Report August 24, 2007 Period covered: August 17 th to August 24 th (Week 3)
Michael P. Andrews NuMI Shutdown & Facility Coordinator LBNE Project ESH Manager AD ESH Special Projects Coordinator.
Proton Plan PMG 3/22/07 E Prebys 1 Proton Plan Status February Eric Prebys.
Machine Advisory Committee Review APS Upgrade Installation Plan and Schedule John Noonan November 15, 2006.
NuMI NuMI Overview NBI 2002 S. Childress (FNAL) 14 March ‘02 NuMI / MINOS Overview.
Fermilab 1 AP Dept. Activities Report September 20, 2006Dixon Bogert AP Dept. - Activities Report Dixon Bogert - AP Dept. Meeting September 20 th, 2006.
Muon Campus Projects Jerry Annala Jan 23, µ AIP Scope Recycler RF system to provide needed bunch structure to future Muon Experiments Recycler RF.
Maintenance and Accelerator Support RHIC run10. Last Wednesday: Nice recovery Nice recovery Good work all especially: Good work all especially: HP, RF,
NuMI DoE Review of the NuMI Project May 2004 ESH, SA, SAD N. Grossman Page 1 ESH, Shielding Assessment (SA) & SAD: Outline SB&O Construction Phase ESH.
ANU Shutdown Status AEM meeting Cons Gattuso 7 May 2012.
NUMI NuMI Internal Review July 12, 2001 Infrastructure: Radiation Safety Page 1 Technical Components NuMI Beamline Radiation Safety Issues Radiation Safety.
August 05, Startup 2013 Machine Status:  Proton Source Commissioning and Studies RFQ Injector Line (RIL) Linac Booster  Main Injector Startup.
Proton Plan Director’s Review 8/15/06 Prebys 2006 Shutdown Eric Prebys, FNAL Accelerator Division.
All Experimenters’ Meeting November 03, 2014 Photo by Greg Vogel.
All Experimenters’ Meeting February 09, Accelerator Operation Summary Calendar Week # 06 NuMI Weekly Integrated Intensity 6.69 E18 protons Beam.
HINS 6-Cavity Test 3 Month Plan Jan 12, Current Schedule 2-3 day shutdown scheduled to start Jan 18 (Wednesday) to upgrade BPM system and reinstall.
Lockout/Tagout Training Presented by Resource Training Group.
Shutdown Summer 10 4-week. Who Main Injector Duration Mike Frett/John Featherstone Remove Sand From MI40 penetrations Install when finished (PLUS) 4w.
Maintenance and Accelerator Support RHIC Start Up 12.
1 BROOKHAVEN SCIENCE ASSOCIATES Redundancy Requirements for Critical Devices R. Casey August 8, 2007.
F Proton Plan Eric Prebys, FNAL Accelerator Division.
08/31/07Shutdown’07 Week 4 F.G. Garcia1 MTA beam line installation Weekly Report August 31, 2007 Period covered: August 24 th to August 31 st (Week 4)
May 06, 2013 Photo by Greg Vogel. Thursday, April 18, some tunnel work had to be suspended and many planned jobs had to be postponed due to the flooding.
TD Help for Shutdown 2012 Preliminary, will be updated April 18, 2012.
All Exp Mtg Apr 21, 2008 NuMI-MINOS Status Report – Alec Habig FAR DETECTOR: 99.7% live time (wall clock) 99.9% (pot weighted) Annual hoist inspection.
Proton Improvement Plan Bill Pellico April 19, 2013 NOvA collaboration Meeting Bill Pellico NOvA.
All Experimenters’ Meeting January 26, Accelerator Operation Summary Calendar Week # 03 NuMI Weekly Integrated Intensity 2.74 E18 protons Beam.
Maintenance Nov 28, Accelerator Access LINAC will remain on RA. It is not yet running. LINAC will remain on RA. It is not yet running. Booster-
Friday July 27, 2007 Page 1 Shutdown 2007 ES&H Enclosure Access  Linac Remains Operational until August 13 th  Booster RWP’s and enclosure access keys.
Friday April 7, 2006 J. Anderson Jr. Page 1 ES&H Safety System Upgrades  Data Acquisition System 95% Complete 16 of 17 Linux Ethernet Port Replicator.
October 4-5, Status of ARRA funded AIPs Stochastic Cooling Alex Zaltsman October 4, 2010 Stochastic Cooling cost and schedule.
SY120 to the Meson Test Facility (and KTeV?) - Chuck Brown – 23Feb04 – June/08 P2 P1 MI52 MCenter MTest 3 km beam line from MI52 to MT6 and MC7 2.5 km.
All Experimenters’ Meeting October 20, 2014 Photo by Greg Vogel.
All Experimenters’ Meeting December 8, 2014 Photo by Greg Vogel.
Machine Status  Proton Source Commissioning and Studies 8/13-8/14: Linac & Booster Maintenance Period  Main Injector MI30 vacuum ○ Work continues to.
Status of the Accelerator Complex Keith Gollwitzer Antiproton Source Accelerator Division Fermilab 2009 Fermilab Users’ Meeting.
Users' Mtg - 4 Jun 08 FNAL Accelerator Complex Status Ron Moore Fermilab – AD / Tevatron Dept.
Shutdown 2012 ES&H Friday May 11, 2012J. Anderson Jr. Page 1 Booster and 8 GeV line radiation surveys and enclosure re- cored to a shutdown access key.
July 15, 2013 Photo by Greg Vogel. Shutdown Machine Status:  Proton Source Commissioning and Studies RFQ Injector Line (RIL) Linac Booster.
All Experimenters’ Meeting September 23, Accelerator Operation Summary Calendar Week # 38 NuMI Weekly Integrated Intensity 4.57 E18 protons BNB.
TD Help for Shutdown 2015 Preliminary, will be updated July 6, 2015 – October 5, 2015.
August 12, Machine Status: 2013  Proton Source Commissioning and Studies RFQ Injector Line (RIL) Linac : Roof hatch installed Booster : Magnet.
Proton Source Meeting, August 8, 2003 – E. Prebys 1 Major Projects in Linac/Booster  New Linac Lambertson  (4) New EDWA magnets in MI-8 line  (3) New.
March 4, 2013 Photo by Martin Murphy. Shutdown 2012 Machine Status: Linac running with NTF Treatments, RFQ and Linac commissioning Booster beam commissioning.
All Experimenters’ Meeting November 4, Accelerator Operation Summary Calendar Week # 44 NuMI Weekly Integrated Intensity 5.97 E18 protons BNB.
July 29, Startup 2013 Machine Status:  Proton Source Commissioning and Studies RFQ Injector Line (RIL) Linac Booster  Main Injector Trying to.
Friday July 16, 2010 John Anderson Page 1 Shutdown 2010 ES&H Enclosure Access  Linac Remains on enclosure interlock key series. RWP’s in.
Accelerator Support and Maintenance Startup for Run 13.
Muon Department Meeting Jerry Annala Staged Commissioning of Muon Campus 17 December 2015.
09:00 Meeting Shutdown Update June 29 th 2015 Cons Gattuso AD Shutdown Manager.
Muon Long Term Schedule August 15, µ Points to discuss What is the schedule What is the schedule Shutdown schedules Shutdown schedules How do we.
5 July 2005T. Yasuda, Fermilab D0 Shift Captain Responsibilities Taka Yasuda Fermilab.
MI Shielding Machine Protection Credit D. Capista March 7,2010.
Proton PMG September 3 rd 2015 Cons Gattuso AD Shutdown Manager.
Maximum Credible Beam Loss in the Main Injector D. Capista January 26, 2012.
Proton PMG May 7 th 2015 Cons Gattuso AD Shutdown Manager.
Accelerated Protons and Personnel Doses
WARNING WARNING WARNING WARNING WARNING WARNING WARNING WARNING
Presentation transcript:

Shutdown 2012 ES&H Friday April 27, 2012J. Anderson Jr. Page 1 Draft Schedule Beam off to Experiments 0000 Monday April 30 th Linac continues operations for NTF patient treatment MTA will continue operations for the first week Booster will continue operations for ~1-2 weeks Controlled Access keys available for cavity installation ~0700 Monday April 30 th MI will perform beam and power supply studies April 30 th NuMI power supply studies April 30 th and May 1 st Radiation surveys begin in non operating enclosures Monday morning April 30 th Most non operating enclosures available for access Tuesday May 1 st

Shutdown 2012 ES&H Friday April 27, 2012J. Anderson Jr. Page 2 Linac Initially remains in operations for NTF Remains on enclosure interlock key series Enclosure keys issued daily through the Main Control Room Booster Initially remains in operations the first week or two Will be re-cored to a shutdown access key series List of names for long term issue shutdown access keys has been received. Keys issued through the MCR LOTO to be done in the Main Control Room

Shutdown 2012 ES&H Friday April 27, 2012J. Anderson Jr. Page 3 Main Injector Radiation surveys will be on Tuesday May 1 st Will be re-cored to a shutdown access key series List of names for long term issue shutdown access keys has been received. Keys issued through the MCR LOTO to be done in the Main Control Room 8 GeV Line Will be re-cored to the MI shutdown access key series when Booster finishes operations

Shutdown 2012 ES&H Friday April 27, 2012J. Anderson Jr. Page 4 P-Bar Enclosures Rings will remain on the enclosure access keys but will be de-posted early in the shutdown to support approved tours Enclosure keys issued daily through the Main Control Room or AP-10 Pre-Target, Pre-Vault, Vault, and Transport enclosures will remain on the enclosure interlock keys Enclosure keys issued daily through the Main Control Room LOTO to be done in the Main Control Room

Shutdown 2012 ES&H Friday April 27, 2012J. Anderson Jr. Page 5 NuMI Power supply testing April 30 th and May 1 st Radiation surveys Wednesday May 2 nd Will be re-cored to a shutdown access key series List of names for long term issue shutdown access keys has been received. Keys issued through the MCR Underground access at MI-65 or MINOS requires badging in and out MI-65 LOTO to be done in the Main Control Room

Shutdown 2012 ES&H Friday April 27, 2012J. Anderson Jr. Page 6 MiniBooNE Remains on enclosure interlock key series Enclosure keys issued daily through the Main Control Room LOTO to be done in the Main Control Room Tevatron Will remain on interlock system access keys Enclosure keys issued daily through the Main Control Room Substation LOTO to be done in the Main Control Room

Shutdown 2012 ES&H Friday April 27, 2012J. Anderson Jr. Page 7 Switchyard, Meson and Neutrino Primary Enclosures Radiation surveys on Monday April 30 th G2 and N01 will be re-cored to a radiation job control key to support grout removal activities All other enclosures remain on the interlock key series Enclosure keys issued daily through the Main Control Room Individuals are responsible for LOTO of equipment to be worked on

Shutdown 2012 ES&H Friday April 27, 2012J. Anderson Jr. Page 8 Radiation Safety Wally Kissel has expanded the “Get Dose” electronic dose reporting system to include other divisions We need weekly employee reporting of dose exposure Must keep Radiation Safety Training current to keep long term issue keys RWP’s will be issued for the duration of the shutdown and do not need to be signed every 30 days Recommend reviewing survey maps when moving to a new work area

Shutdown 2012 ES&H Friday April 27, 2012J. Anderson Jr. Page 9 Individual Capabilities Many employees from other divisions Supervisors need to understand employee restrictions Need to ensure work tasks are compatible with employee abilities