July 15, 2013 Photo by Greg Vogel. Shutdown 2012 - 2013 Machine Status:  Proton Source Commissioning and Studies RFQ Injector Line (RIL) Linac Booster.

Similar presentations


Presentation on theme: "July 15, 2013 Photo by Greg Vogel. Shutdown 2012 - 2013 Machine Status:  Proton Source Commissioning and Studies RFQ Injector Line (RIL) Linac Booster."— Presentation transcript:

1 July 15, 2013 Photo by Greg Vogel

2 Shutdown 2012 - 2013 Machine Status:  Proton Source Commissioning and Studies RFQ Injector Line (RIL) Linac Booster  Main Injector Tunnel work on Saturday Power Supply studies on weekends TeV & Muon Rings – Partially available for tours with approval and appropriate training

3 MSS Bypass Project

4 MSS Bypass Project – Impact Areas  Project Completion Date July 16 th (Adding on additional PS3 work)  Main Ring Road Closure and Power Outages Main Ring Road reduction at A1 (Restriction lifted on 7/16/13) Power off to A1, A2, & A3 (Last power outage will be 7/15/13)  PS3 Power Outage July 17 th from 0800 – 1630 Work in manhole to prepare for further work about 1.5 weeks away.

5

6 MSS Bypass Project – Impact Areas Cont.  CHL ~5 day outage/reduction (only house power available) Monday, June 24 th through Friday, June 28th Two 5 minute power outages needed Monday, June 24 th @ 0730 – 0735 (Completed) Friday, June 28 th @ 0700 – 0705 (Completed) Cable pulls and splices in PMH 210  Meson Two 15 minute outages one week apart Monday, June 17 th @ 0700 – 0715 (Completed) Monday, June 24 th @ 0700 – 0715 (Completed) Monday, June 24 th @ 0815-1215 (Bonus MCC-2 outage @ MS3) Cable pulls and splices in PMH 110 Impacts MCC, Holometer, MW9, all enclosures, systems, and buildings

7 Kautz Road SubStation  Status MI backfed from Master SubStation ○ Using Feeder 45 for MI conventional power which is normally T85 on KRS We ordered 6+ new surge arrestors (4.7k each) from Hubbell and wait for delivery in ~1 week Schedule a ~1 day KRS outage (not really an outage, we can’t run power supplies) to replace all surge arrestors on transformers T85 & T87 There will be a 20 minute outage to remove the backfeed after the surge arrestors are installed

8 MI Startup Activities (~1 Week)  Turn on power supplies and establish ramps  Establish 8 Gev beam  Match MI8 line lattice with IPM  Tune abort line @8 Gev  Establish 120 Gev beam  Smooth orbits up the ramp  Tune abort line @ 120 Gev  High field Orbit smoothing (quad moves)  Requires tunnel access (2x8 hrs)  Calibrate tune table  MI8 line lattice matching  Dedicated beam study  Extraction line tune up (NuMI)  Tune up for operation  Deliver low intensity beam to NuMI beam line for target scans  Estimated to take an additional week after MI is tuned up for operations

9

10 Shutdown 2012 Schedules and Links: Schedule can be accessed from the Operations Home Page - Schedules -> Operations ScheduleOperations Schedule Direct link to schedule - http://www-ad.fnal.gov/ops/schedule.htmlhttp://www-ad.fnal.gov/ops/schedule.html