Shutdown Summer 10 4-week. Who Main Injector Duration Mike Frett/John Featherstone Remove Sand From MI40 penetrations Install when finished (PLUS) 4w.

Similar presentations


Presentation on theme: "Shutdown Summer 10 4-week. Who Main Injector Duration Mike Frett/John Featherstone Remove Sand From MI40 penetrations Install when finished (PLUS) 4w."— Presentation transcript:

1 Shutdown Summer 10 4-week

2 Who Main Injector Duration Mike Frett/John Featherstone Remove Sand From MI40 penetrations Install when finished (PLUS) 4w John Featherstone/Mike Frett Rauchmiller Michael Moore Jack ( CT) Zolli Tim (CT) Johnson Sean Main Injector Corrosion repair (beam tubes) 4d-6d John Featherstone/Mike Frett Burk Dave Campbell Matt Chlebek Mark Folkie Jim

3 Who Tevatron Duration Scott McCormick Warm A3 (PLUS) 4w Scott McCormick Dymond Bill Williams James Aponte, Sabina Lambert Dan (ct) Plant Derek Greskoviak Jason Warm Straights (PLUS) 4w Scott McCormick Sylejmani Sali Jones Robert Stone Brent

4 Who P-Bar Duration Henry Gusler New gauges and leak check Ln2 rough vacuum 2d Henry Gusler Crabtree Phil Shaffer Earl Sellberg Greg Rehose SMA Magnets 2w Kelly Doug Samayavong Inpeng Sorenson Steve

5 Who Dave Augustine (ALL) Ext: 4451 Pager (630) 905-5081 augustine@fnal.gov John Featherstone (MI) Ext: 5605 Pager (630) 266-5457 feather@fnal.gov * Taking over for Merill Albertus Scott McCormick (Tev) Ext: 3691 Pager (630) 722-6795 smc@fnal.gov Mike Frett*(MI) Ext: 4663 Pager (630) 722-1057 mfrett@fnal.gov Henry Gusler Ext: 2675 Pager (630) 722-5209 smc@fnal.gov Oliver Kiemschies (TD) Ext: 3925 Cell (630) 364-6533 ollie@fnal.gov

6 What MI (Team 1) (~4 weeks) Install lead blankets at MI40 kickers Leak check flourinert side of MI40 kickers Remove Sand from MI40 penetrations; install when finished Install shield Wall 307 Remove lead blankets from MI40 kickers MI (Team 2) (4-6 days) Corrosion repair; Replace beam tube clamps on the MI Beam tube ring wide. Some areas will be hot. Buff off any rust on beam tube

7 What PBar (Team 1) New Gauges and Leak Check LN2 rough vacuum (2 days) Pbar (Team 2) Rehose SMA Magnets (~2 weeks) Tev Talk to Scott A1 warm up and repair cold leaks, F1 warm up only if time allows. E0: Install V-Goniometer, repair leaky bellows and install Pixel detector. E11- replace flying wire, E17 replace flying wire, B48 install e-cloud detector, A0 TEL2 install new beam screen and F sector has 2 turbo 151 installations

8 Where Usually keys are given out in MCR (Tev may get from Scott early) There WILL be permanent shutdown keys (i.e. keys that you don’t have to turn in at the end of the day) for most You will be given a card by a task master with which to get a key with.

9 Location of the MCR

10 Layout of MCR <- Keys <- TeV LOTO MI & Booster LOTO -> <- NuMI LOTO Usually RWP’s are next where keys are. At the beginning of this shutdown, the RWP’s will be in the room next to the MCR, along with RSO’s

11 LOTO

12 When Day 0 (Sunday, July 18th) Tev – We are setting up a meeting with Scott McCormick Thursday or Friday to work out details Day 1 (Monday, July 19th) Everyone Else. No access until 8am Some people may be shuffled as jobs complete

13 Why We will try to have separate job & task numbers for tunnel jobs (http://tdserver1/project/jobfiles/Current_Jobs/TD_work_for_AD/refmenu.htm) AD Pays for OT (see me for the task number) Still working on approval process (doesn’t sound like you’ll have to “hand” a sheet to anyone though)

14 Good Luck! Stay Safe! This presentation can be found at: http://tdserver1.fnal.gov/AcceleratorSupport/Shutdown/