Chiho Wang ATLAS TRT Duke University CERN, Feb. 2005 1 TRT Barrel assembly status & schedule Feb. 9, 2005.

Slides:



Advertisements
Similar presentations
Davide Piccolo INFN Napoli Muon Annul Review Cern 15 September 2003 Chamber Production QA/QC MUON ANNUAL REVIEW On RESISTIVE PLATE CHMABERS CERN, 15 September.
Advertisements

Preparation for ATLAS SCT/ID Endcap Completion at CERN Jo Pater Manchester, 4 January 2006.
Seog Oh/ Duke University/June, 2003 TRT/ ATLAS week at CERN Duke Production Status.
R.Becker (MIT) 15/10/02 UGBS Main Plate Patrick Schmid (left) of ETHZ did the CNC machining of the plate. Urs Horisberger (ETHZ) Completed follow up machining.
26 September 2000 High Voltage Plates and Capacitors Jack Fowler.
LAr ROD Status Arno Straessner and Alain, Daniel, Annie, Manuel, Imma, Laurent, Eric, Jean-Pierre, Gilbert,... ATLAS Geneva DPNC January 12 th, 2005.
Walls crates cables gas chambers electronics CERN adb.
Summary of Fuse Testing for Barrel Module Fuse Boxes Duke University Jack Fowler.
Chiho Wang ATLAS TRT Duke University Dubna, May Fuse Box Production Chiho Wang/Jack Fowler.
Seog Oh/ Duke University/September, 2003 TRT Workshop/ Peniscola, Spain Duke TRT Progress.
ISR Work Progress Report Muon Week April 10 th 2003 A. Benvenuti INFN Bologna.
1 HBD Construction status Itzhak Tserruya DC meeting, BNL, February, 2006 Plans for Run-6 Box construction GEM assembly and testing Status of urgent items.
Chiho Wang TRD Conference Duke University Bari, Sep Design and Construction of the ATLAS Barrel TRT Chiho Wang Duke University.
Chiho Wang ATLAS TRT Duke University CERN, Feb Fuse Box Status Chiho Wang Duke University.
Setting up the Ricoh C305 Press F5 to start the Presentation
Seog Oh/ Duke University/June, 2003 TRT/ ATLAS week at CERN Status of Gain Mapping at Duke.
ATLAS Upgrade ID Barrel: Services around ‘outer cylinder’ TJF updated According to the drawing ‘Preparation outer cylinder volume reservation’
Malte HildebrandtDC Status Report, Dear MEG Committee,PSI, April 14 th 2009 this is the first report concerning the drift chamber status as.
CMS ECAL End Cap Meeting CERN 19 June to 23 June 2000 A.B.Lodge - RAL 1 ECAL End Cap High Voltage Cards and 2000 Electrical/Thermal Model. Progress on.
V. Cindro, Jožef Stefan Institute, Ljubljana, Slovenia DAQ, DCS, Power Supply and Cables Review CERN, March Electrical PP1 Basic features Electrical.
ATLAS TRT Barrel Design Review, 1998 Barrel TRT Electronics Cooling Chiho Wang Duke University.
May 2001, Istanbul Workshop High Voltage Plates and Capacitor Status Jack Fowler.
Ronald Lipton PMG June Layer 0 Status 48 modules, 96 SVX4 readout chips 6-fold symmetry 8 module types different in sensor and analog cable length.
ATLAS SCT End-Cap C Integration 1.Introduction: to the SCT within ATLAS 2.End-Cap C Reception at CERN 3.Final Assembly 4.Integration with the TRT 5.Combined.
18 July 2006A.Ciocio -SCTSG1 SCT Services Installation ID week full report (July 4) SCT Cables Web page
ATLAS TRT CO 2 cooling system project status Beaufort 12: “Hurricane” (>119 km/h) Saffir-Simpson 5: “catastrophic damage” (>250 km/h) (CO 2 distribution.
16/04/20031PNPI / LHCb Muon EDR Wire Pad Chambers PNPI design for regions R4 in Stations M2,M3,M4  4 gas gaps of 5mm±70µm;  Active area: 1224x252.8 mm².
Straw Working Group Status assembly at CERN Plans 10/2/14Straw WG.
Mechatronics Task Force, 26-nov-02 Olivier Teller, CERN EP-CMA1 Cooling Mechatronics Schedule.
Neil JacksonUK-V RAL 8th September Module to Disc Assembly Infrastructure –Services and test box –Evaporative cooling system –Disc Handling Tests.
LNF activities on WPC Panels Construction of prototypes and layout Status of tooling Proto 0, open items, plan,...
Chiho Wang Duke University 1 TRT Barrel integration Status / Schedule Chiho Wang.
November 04 Jason Tarrant CCLRC1 SCT EC Interconnects l Progress of SCT EC Interconnects »Services (Required for Disc Insertion 2004 / Integration 2005)
Long Bo for LAPD Hans Jostlein10/20/2011 December 15, 2015 Long Bo for LAPD 1.
Workshop Chamonix XV27-January-2006 DivonneMassimiliano Ferro-Luzzi 1 State of LHCb for the Sector Test  Overview  Agreement  Status of –VELO –exit.
Compressor Replacement – ODU
4-Jan-16S.Movchan Straw manufacturing and QC1 Straw tracker manufacturing procedure Dubna: assembly halls procedure conclusion Presented by S.Movchan.
Production Readiness Review at PNPI Chamber assembling: Main production and quality control steps 30 January 2004 – G.Alkhazov 1.Input components control.
M. Gilchriese Pixel Update October 3, M. Gilchriese 2 Outline Barrel status and repair strategy Revised ATLAS installation schedule Finishing pixel.
8 June 2006A.Ciocio - SCTSG1 Status of Type IV Cables Cables production –resumed in February after 3 months stop –See ID week February ‘06 Delivery of.
Chiho Wang ATLAS TRT Krakow Workshop Duke University May, HV Plate Design & Assembly Chiho Wang Duke University.
9/12/2003Ivan Hruska1 First box prototype –Box design in July ‘03 –Box produced during August ’03 Tested last week in few fingers Small changes necessary.
PSD upgrade: concept and plans - Why the PSD upgrade is necessary? - Concept of the PSD temperature stabilization and control - Upgrade of HV control system.
Chiho Wang ATLAS TRT Duke University IU, Oct Fuse Box Design & Mounting Chiho Wang Duke University.
Executive Committee, Toronto August 3, 2005 TRT Barrel WBS 1.2/3.2 Harold Ogren Indiana University.
Gas System Construction Status Oct FH. General Construction is proceeding well, (nearly on-schedule). Testing of Racks is longer than foreseen Testing.
STEREO IMPACT SEP Critical Design Review 2002-Nov-21/22 TvR1 SEP Mechanical Design Sandy Shuman, GSFC ) Tycho.
Chiho Wang ATLAS TRT Istanbul Workshop Duke University May, Fuse Boxes Chiho Wang Duke University.
Chiho Wang ATLAS TRT Barrel Duke University U. Penn. Workshop, 2000 Module Thermal Analysis Chiho Wang Duke University.
Chiho Wang ATLAS TRT Duke University CERN, Sep Barrel integration status.
Chiho Wang ATLAS TRT Duke University CERN, Feb Fuse Box & Capacitor Status Chiho Wang Duke University.
CMS-UK Oversight Committee 17/11/06 D.J.A. Cockerill - RAL 1 The CMS Electromagnetic Calorimeter UK Responsibilities Procurement and testing of VPTs Design.
CPA: Decisions, Issues, Next steps Francesco PIETROPAOLO CERN / INFN-Padova Field Cage CPA and Integration/Installation week, BNL, March 11th, 2016.
Tracker cooling plant refurbishment Project status Revised plan Financial impact.
Chiho Wang ATLAS TRT Duke University CERN, Feb Gas-Flow Measurements Chiho Wang Duke University.
USCMS Pixel PMG, Nov 29, Mechanics Status Disks, ½ Service Cylinders Installation USCMS FPIX FNAL PMG Joe Howell Bruno Gobbi Nov. 29, 2006.
ATLAS TRT Duke University CERN, Feb Fuse Box Status Duke University.
Chiho Wang ATLAS TRT Duke University Dubna, May Barrel integration status May 24, 2005.
Service channels between Tracker and PP1
Service channels between Tracker and PP1
Acceptance test at Duke
new straw end plug: D=10.6 mm straws support frame Levan option
End-cap Mechanics FDR Overview of the Project
Jack Fowler Duke University Spain Workshop
Open Issues Modification of Cactus Arm bending tool required
Summary of Fuse Testing for Barrel Module Fuse Boxes
Module Production and Testing at Duke
Radiation Laboratory Meeting
LST Module Installation
Limited Streamer Tube Project Summary
Presentation transcript:

Chiho Wang ATLAS TRT Duke University CERN, Feb TRT Barrel assembly status & schedule Feb. 9, 2005

Chiho Wang ATLAS TRT Duke University CERN, Feb All modules installed! Feb. 3, 2005

Chiho Wang ATLAS TRT Duke University CERN, Feb Snap shot Feb. 8 snap shot  Type 1: u All modules installed & tested u All electronics installed u 20 modules cooling tube installed  Type 2: u All modules installed & tested u 18 side A electronics installed  Type 3: u All modules installed u 28 modules with protection boards and tested Feb. 06, 2005

Chiho Wang ATLAS TRT Duke University CERN, Feb Module installation time line 30 module mounting days

Chiho Wang ATLAS TRT Duke University CERN, Feb Module placement  Final dead wire distribution:  Type = 1.17%  Type 2 121=0.73%  Type =2.26%

Chiho Wang ATLAS TRT Duke University CERN, Feb Final dead wire distribution  Whole barrel: u 817 = 1.55%

Chiho Wang ATLAS TRT Duke University CERN, Feb Mechanical Assembly Processes

Chiho Wang ATLAS TRT Duke University CERN, Feb Module preparation (done, except for spares)  Capacitor installation (~1-2 days/module) u Insert capacitors u Check capacitor connectivity u Check HV traces u HV test: caps + wires u Seal capacitors  Pre-insertion prep. (6 modules/day/2 person) u Check ground wire u Check cooling sleeve u Check mounting holes u Active gas fittings, custom made for each module: connection & leak test u Glue purging gas gasket u Tape HV kapton for protection u Glue thermal sensors as needed (4 modules each type)

Chiho Wang ATLAS TRT Duke University CERN, Feb Module installation & tests (4 last modules)  Procedures & tests u Fold HV kapton and cover with protection plates u Insert module & fix one corner u Set module z position to middle of BSS u Fix module 2 nd corner & attach set screws u Check purging gas flow Type L/min < 10% loss Type L/min < 15% loss Type L/min < 20% loss u Unfold HV kapton & check HV traces u Attach & glue active gas fittings u Plug & seal unused active gas inlets. u Leak test active gas volume (1mB/B/min) u Install protection boards u HV test with Ar-CO2 u Check active gas path for obstruction (flow rate test)

Chiho Wang ATLAS TRT Duke University CERN, Feb Cooling lines installation (on going)  After the electronics have been: u Installed u Continuity check u Noise check  The cooling lines are: u inserted through both corners of the module u 90 bend forced on one end u Attachment to cooling plate at each end. u (T1 – 20 modules)  Cooling flow measurement is made. u (T1- 20 modules)

Chiho Wang ATLAS TRT Duke University CERN, Feb Module repairs & modifications  Components modification u Peek tubes for module cooling reduced from 0.123”-0.127”  0.116” ” (done) u Fuse box brackets dimension change u Fuse box screws changed from Nylon to Ultem u CO2 flushing tube redesigned with corrigated PEEK. u De-magnetized stainless steel screws for active gas inlet plugs (started from type 2 modules)  Module repair: u Wire removal (2 bad wires + some retroactive decisions from acceptance group) u HV trace broken, shares from neighboring line (1) u Cooling sleeve replacement (4) u Three wires removed from BSS. (2 drawing excess current, 1 shorted). u Two modules (T1) show a connection between 2 signal wires (double joints) at one end. Left for now.

Chiho Wang ATLAS TRT Duke University CERN, Feb Remaining mechanical work  Finish testing the last 4 type 3 modules (~1week)  Continue to install module cooling tubes as electronics are installed  Install outer cylinder u After all modules are tested (~ March, ~1week) u Before manifold can be installed  Install services after electronics are installed u Cooling manifold (contract, deliver ~ April) u Active gas manifold (drawing/review ~ this week) u Purging gas manifold (parts)  Install fuse boxes u Need to solve fuse problem and resume production u 3 possible windows for installation (in descending preferences) Before TRT/SCT system test ~ Oct. Before going in the pit ~ Feb. 06 In the pit, same time as harness or before (?)  MTF migration: Data base structure defined, entering data.

Chiho Wang ATLAS TRT Duke University CERN, Feb Electronics installation  Type 1: u Completed Jan. 24, 2005  Type 2: u Side A (2B): 18 modules installed 22 boards in repair process, ~ 10 finished u Side C (2F): started stuffing at ACAMAS. Should have pre- series at CERN ~end of Feb.  Type 3: u Side A (3B): Pre-series at CERN and tested. Feedback to ACAMAS. No known issue. u Side C (3F): All bare board received. Need to start pre- series.

Chiho Wang ATLAS TRT Duke University CERN, Feb Electronics schedule  3B will be the next to arrive (followed by 2F and 3F) and available for installation ~April 11.  After that we will be saturated with boards.  Installation is the slowest part. u 3 weeks per side for type 2 u 1 month per side for type 3  Will need to run more than one shift to finish installation in June.

Chiho Wang ATLAS TRT Duke University CERN, Feb Services Manifolds

Chiho Wang ATLAS TRT Duke University CERN, Feb Sector Tests

Chiho Wang ATLAS TRT Duke University CERN, Feb Current Integration Schedule

Chiho Wang ATLAS TRT Duke University CERN, Feb Summary  All modules installed!  Electronics installation is well under way. u All type 1 installed u >1/4 type 2 installed.  Parts, procedures, and drawings are in good shape  Manifolds could cause delays and need to be carefully followed.  Active Roof Boards remain the critical path and need to be carefully followed  Fuse problem need to be solved