18 July 2006A.Ciocio -SCTSG1 SCT Services Installation ID week full report (July 4) SCT Cables Web page

Similar presentations


Presentation on theme: "18 July 2006A.Ciocio -SCTSG1 SCT Services Installation ID week full report (July 4) SCT Cables Web page"— Presentation transcript:

1 18 July 2006A.Ciocio -SCTSG1 SCT Services Installation ID week full report (July 4) SCT Cables Web page http://www-atlas.lbl.gov/ciocio/SCTcables/http://www-atlas.lbl.gov/ciocio/SCTcables/ Workpackage https://edms.cern.ch/document/593278/https://edms.cern.ch/document/593278/

2 18 July 2006A.Ciocio -SCTSG2 Type II/III cables – Installation 3594 cables installed and tested All 2112 barrel cables (sectors 1,3,7,9,11,15) All endcap cables for sectors 1,3,7,9 494 (sector 11&15) will be installed in August Yield: <1% cables with defects or to replace - Mechanical defects - Damage during installation or preparation - Failed electrical test (most probably due to splice damage) after installation (replaced) Additional inspection of damage and final verification that individual wires are strongly fixed inside the JST and FCT when they will be disconnected from dPP1.

3 18 July 2006A.Ciocio -SCTSG3 Type II-III and Fibre Cables by Sector S5 S3S7 S1S9 S15S11 S13 US PP3 racks USA PP3 racks 384 Barrel 494 EC 384 Barrel 494 EC 336 Barrel 247 EC 336 Barrel 247 EC 336 Barrel 247 EC 336 Barrel 247 EC Level 7 Level 6 Level 2 Level 8 Level 5 & 2 Level 1 & 2 18 Fibre cables (EC) 27 Fibre cables (9 EC, 18 Barrel) 18 Fibre cables (Barrel) 27 Fibre cables (9 EC, 18 Barrel) Fibre Cables to USA15

4 18 July 2006A.Ciocio -SCTSG4 SCT Cables by Sectors Sequence Sector 5 (top) and Sector 13 (bottom) –heater cables, and DCS cables (completed) Sector 9 - Installation completed on May 1 –878 SCT cables (384 Barrel, 494 EC) –18 Fibre cables (EC) Sector 3 - Installation started on May 2 – completed on June 4 –583 SCT cables (336 Barrel, 247 EC) –27 Fibre cables (9 EC,18 Barrel) Sector 1 - started in parallel mid May – completed on June 13 –878 SCT cables (384 Barrel, 494 EC) –18 Fibre cables (Barrel) Sector 7 – started on June 7 – completed on June 29 –583 SCT cables (336 Barrel, 247 EC) –27 Fibre cables (9 EC,18 Barrel) Sectors 11, 15 – 336X2 barrel cables installed – July 18 –583 + 583 SCT cables (336 Barrel, 247 EC) –27 + 27 Fibre cables (9 EC,18 Barrel) Installation sequence in a sector is: –Tubes, fibres, heater cables, SCT cables, (Muon cables), –TRT cables, pixel cables

5 18 July 2006A.Ciocio -SCTSG5 Type IV Cables - Installation All type IV cables (2044+spares) going from PP3 racks in the ATLAS cavern to PS racks in US15 installed (+ connectors) Type IV going to USA15 almost completed –64 double harnesses to install (128 cables) –6 more days Testing in racks after installation and first cut ongoing Completed installation is expected in one week

6 18 July 2006A.Ciocio -SCTSG6 Type IV – Connectors in situ All connectors (2000+) in US15 completed on March 10 (a few were left but they are done now) Many racks are tested before and after plug into PS (Petr with Prague team) Very good yield but some rework was necessary One rack (the very first one made more than an year ago) needs cables rerouting (cables were cut too long by previous company) 2+1 CPE techs returned in mid-April for a few weeks –US side was reworked –Started 2 USA racks but left again because more USA15 racks were needed to be completed for the full team to operate efficiently A team of 6 techs (1 supervisor) will return this week Estimated completion of connectors in USA racks: End of August

7 18 July 2006A.Ciocio -SCTSG7 PP3 Assembly and Installation completed Checks for shorted units and problems in progress Plug-in of type IV cables Problems found after installation in the last few months –Insulation –Sliding units in subracks –Failed units (2+) PP3 units installed in racks Channel Spare units in racks 4261 4088 173 PP3 - failed (back for inspection and rework)10 Subracks (30 PP3 units in a shell)137 Subracks - special (shells of 30 partially filled with PP3 and the rest with empty boxes) 9 Subracks – mini (shells of 5 units for spares PP3 in a full rack) 4 Extra PP3 units Shells Mini shells Empty boxes 2 4 110

8 18 July 2006A.Ciocio -SCTSG8 Installation & Testing Activities Type IV Acceptance test (done) Test in rack after installation Test of cut cables after connector in situ work Plug-in cables into PS crates Test with feedtrough Type II-III Preparation ----ALL DONE Acceptance test (partial) Visual inspection Folding the shield and cut it the right amount, fix it Organize boxes with right cables to send for installation Type II-III Installation Mount dPPB1 and dPPF1 (Barrel) Squeezing the cables to fit between pin and clamp holder Plug-in of the delicate JST/FCI connectors to dPPB1 Placing the clamp (now), placing the clip (later) -- DONE (ENDCAP) crimp group of drain wires in a ferrule and catch the ferrule with the grub screws into clamp’s holes Plug in the dPPF1 Type II-III Testing Type II-III replacing bad cables PP3 Burn-in of units -- DONE Assembly into subracks -- DONE Installation into racks of subracks -- DONE Plug-in the cables to PP3 Test of whole chain

9 18 July 2006A.Ciocio -SCTSG9 Schedule Type II-III barrel installation completed today Endcap cables of sector 11&15 to install after the Solenoid Field Mapping (July 19- Aug 14) Type II-III installationmid-July (Barrel) end of August (last Endcap cables – 494) Type IV installation24 July Connector in situ+testingend of August PS cratesend-July (US side) – September (USA side) PP3 assembly, installation end-July All cables plugged into PP3mid-July- begin August (type IV) end-August (type II-III) Test of whole chainnow – mid September

10 18 July 2006A.Ciocio -SCTSG10 Plan

11 18 July 2006A.Ciocio -SCTSG11 PS priorities

12 18 July 2006A.Ciocio -SCTSG12 Issues PP3 –We find problems as we plug in and test –Type IV all connected by end of July –Hopefully OK when Type III are connected Tester –Different flavor that work with different configuration of cable chain –Multiple laptops failure (~ok now) –Need help at CERN of experts (Ljubljana) when testing whole chain Defective dPPF1 –Some faulty cables were actually due to a bad channel on dPP1 (3 endcap 3 barrel) –Still missing some dPPF1 Connector in situ –Delay will move installation of PS later Need more HELP with testing until end of August (mid September)