NGAO: Cost Comparison with First Light TMT AO Peter Wizinowich, Richard Dekany, Don Gavel with input & review by Brent Ellerbroek SSC Meeting November.

Slides:



Advertisements
Similar presentations
NGAO Construction Project Cost Estimation: Initial Thoughts Richard Dekany NGAO Team Meeting #12 December 13, 2007.
Advertisements

The Project Office Perspective Antonin Bouchez 1GMT AO Workshop, Canberra Nov
Trade Study Report: Fixed vs. Variable LGS Asterism V. Velur Caltech Optical Observatories Pasadena, CA V. Velur Caltech Optical Observatories Pasadena,
W. M. Keck Observatory’s Next Generation Adaptive Optics Preliminary Design & Path Forward Peter Wizinowich, Sean Adkins, Rich Dekany, Don Gavel, Claire.
NGAO System Design Review Response Peter Wizinowich, Rich Dekany, Don Gavel, Claire Max for NGAO Team SSC Meeting June 18, 2008.
NGAO System Design Phase Update Peter Wizinowich, Rich Dekany, Don Gavel, Claire Max, Sean Adkins for NGAO Team SSC Meeting February 20, 2008.
Build to Cost Meeting: Goals, Agenda & New Directions Peter Wizinowich NGAO Team Meeting September 11-12, 2008.
1 NGAO Instrumentation Studies Overview By Sean Adkins November 14, 2006.
WMKO Next Generation Adaptive Optics: Build to Cost Concept Review Peter Wizinowich et al. ~ March 20, 2009 February 5, 2009 DRAFT.
LIGO-G M LIGO Laboratory1 Adv. LIGO Installation (INS) Plans, Schedule, Costs, Team Plan, Schedule Costs Team.
1 Laser Guide Star Wavefront Sensor Mini-Review 6/15/2015Richard Dekany 12/07/2009.
Functional Requirements Status and Plans Christopher Neyman W. M. Keck Observatory Viswa Velur California Institute of Technology Keck NGAO Team Meeting.
1 Keck NGAO Proposal: Management Overview Presenter: P. Wizinowich SSC Meeting June 21, 2006.
NGAO System Design: AO System (WBS 3.2) & Laser Facility (WBS 3.3) Design Inputs & Outputs Peter Wizinowich NGAO Team Meeting #9 August 24, 2007.
California Association for Research in Astronomy W. M. Keck Observatory KPAO Keck Precision Adaptive Optics Keck Precision AO (KPAO) SSC Presentation January.
Build to Cost Directions & Guidelines Peter Wizinowich SSC Meeting November 3, 2008.
NGAO Meeting #3 Introduction NGAO Meeting #3 Peter Wizinowich December 13, 2006.
WFS Preliminary design phase report I V. Velur, J. Bell, A. Moore, C. Neyman Design Meeting (Team meeting #10) Sept 17 th, 2007.
NGAO Alignment Plan See KAON 719 P. Wizinowich. 2 Introduction KAON 719 is intended to define & describe the alignments that will need to be performed.
NGAO Cost Estimation Guidelines Richard Dekany January 25, 2008.
WBS & AO Controls Jason Chin, Don Gavel, Erik Johansson, Mark Reinig Design Meeting (Team meeting #10) Sept 17 th, 2007.
NGAO Management Update Peter Wizinowich NGAO Meeting #11 November 5, 2007.
WBS 3.3 Laser Facility Jim Bell, Jason Chin, Erik Johansson, Chris Neyman, Viswa Velur Laser Architecture Meeting Oct 1 st, 2007.
NGAO System Design Phase Management Report - Replan NGAO Meeting #6 Peter Wizinowich April 25, 2007.
NGAO Status R. Dekany January 31, Next Generation AO at Keck Nearing completion of 18 months System Design phase –Science requirements and initial.
NGAO Team Meeting Management Peter Wizinowich May 26, 2009.
NGAO System Design Phase System & Functional Requirements Documents NGAO Meeting #6 Peter Wizinowich April 25, 2007.
WBS 3.3 Laser Facility Jim Bell, Jason Chin, Erik Johansson, Chris Neyman, Viswa Velur Design Meeting (Team meeting #10) Sept 17 th, 2007.
NGAO Team Meeting Management Peter Wizinowich March 19, 2009.
Major Management & Systems Engineering Ideas for Reducing Costs Peter Wizinowich NGAO Team Meeting September 11-12, 2008.
NGAO Meeting #5 Introduction NGAO Meeting #5 Peter Wizinowich March 7, 2007.
WMKO Next Generation Adaptive Optics: Build to Cost Concept Review Peter Wizinowich et al. December 2, 2008 DRAFT.
NGAO Instrumentation Preliminary Design Phase Planning September 2008 Sean Adkins.
1 NGAO Science Instrument Reuse Part 1: NIRC2 NGAO IWG December 12, 2006.
WMKO Next Generation Adaptive Optics: AO System Design Impact of Cost Savings Ideas Don Gavel December 19, 2008.
Trade Study Report: NGAO versus Keck AO Upgrade NGAO Meeting #5 Peter Wizinowich March 7, 2007.
Design Team Report: AO Operational Tools (aka Acquisition and Diagnostics) Christopher Neyman W. M. Keck Observatory (for the Operational tools team) Keck.
What Requirements Drive NGAO Cost? Richard Dekany NGAO Team Meeting September 11-12, 2008.
NGAO Controls Team Kickoff Meeting August 5, 2008 Erik Johansson.
Cost Management Week 6-7 Learning Objectives
S/W Project Management
MCAO Adaptive Optics Module Mechanical Design Eric James.
Common PDR Problems ACES Presentation T. Gregory Guzik March 6, 2003.
NCSX Management Overview Hutch Neilson, NCSX Project Manager NCSX Conceptual Design Review Princeton, NJ May 23, 2002.
NEDM Construction Project Cost & Schedule Philosophy Vince Cianciolo, ORNL Physics Division Internal Cost & Schedule Review 02/11/2005.
DVA Series Work Flow P. Dewdney Apr 15, SPDO DVP Work Flow 2 DVA-1 CPG.
August 2 and 3, 2010 Project Cost, Schedule, Risk and Contingency Jay Elias.
U.S. MICE Schedule, Cost, & Risks Peter H. Garbincius Mark Palmer, Alan Bross, Rich Krull Fermilab Presented at RAL – November 13, 2013.
1 BROOKHAVEN SCIENCE ASSOCIATES NSLS-II Project Baseline Jim Yeck NSLS-II Deputy Project Director NSLS-II PAC Meeting November 20, 2007.
3.1 Optomechanical systems (1) Scientific and engineering resources are available to carry out the optomechanical work on DECam. The highly distributed.
Concluding Summary WBS1.1.2 SCT Subsystem A. Seiden BNL March 2001.
OFFICE OF SCIENCE 2.3 Infrastructure and Installation Sims, Edwards 1.Does the conceptual design and planned implementation satisfy the performance specifications.
Oct 17, 2001SALT PFIS Preliminary Design Review1 PFIS/ IMPALAS Issues Outside Reviewer's Comments Post-PDR tasks Valuation Issues.
3.1.1 Optics, Optical Corrector, Mechanical Systems M. Johns, C. Claver.
Copyright , Dennis J. Frailey CSE7315 – Software Project Management CSE7315 M16 - Version 8.01 SMU CSE 7315 Planning and Managing a Software Project.
AURA New Initiatives Office. GSMT SWG Meeting L. Stepp, July 30, 2002 NSF Science Working Group Support Available from AURA NIO Available Personnel Current.
1 Global Design Effort: Controls & LLRF Controls & LLRF Working Group: Tuesday Session (29 May 07) John Carwardine Kay Rehlich.
SRR and PDR Charter & Review Team Linda Pacini (GSFC) Review Chair.
Power Upgrade Project SNS September 21-22, TBM Cost Estimate Cost Estimate Schedule Approach Tom Mann October 27, 2005.
Keck Next Generation AO Next Generation Adaptive Optics Meeting #2 Caltech November 14, 2006 P. Wizinowich for NGAO Executive Committee.
Theme 2 AO for Extremely Large Telescopes Center for Adaptive Optics.
Time to resolve Design Issues 1. Disclamer Due to the engineering meeting last week I have not had time to coordinate this material with Tim or the L3.
What is a WBS? A Work Breakdown Structure is not a list of tasks, a schedule or an organization chart. Rather it provides the basis on which a task.
Cost and Schedule Paul Weinman Pacific Northwest National Laboratory.
Camera PDR/CD1 Planning 19 September 2008
Jim Fast Pacific Northwest National Laboratory
(Additional materials)
NGAO System Design Project Plans and Schedule
Management Breakout: MREFC Budget Summary Victor L
Advice to Industry Panel – Contract Management Perspective
Presentation transcript:

NGAO: Cost Comparison with First Light TMT AO Peter Wizinowich, Richard Dekany, Don Gavel with input & review by Brent Ellerbroek SSC Meeting November 3, 2008

2 Presentation Sequence SDR Reviewer comments leading to this cost comparison NGAO SDR Cost Estimate & Methodology Cost Comparison Goal, Products & Approach High-level Summary of Results Cost Comparison Conclusion Conclusion Preview: - We & TMT agree that NGAO is traceably less expensive than the 1 st light TMT AO system & we understand why - Larger NGAO contingency needed in some areas - Quote needed for laser & will be obtained soon

3 SDR Reviewer Comments “Based on the cost and schedule of past and planned projects of lower or similar complexity, the review panel believes that the NGAO project cost and schedule are not reliable and may not be realistic. Contingencies are also too tight. In particular, the time of 18 months allocated for manufacturing and assembly and 6 months for integration and test, is probably optimistic by a large amount.” Relevant to this point they also said: –“The review panel believes that Keck Observatory has assembled an NGAO team with the necessary past experience … needed to develop the Next Generation Adaptive Optics facility for Keck.” –“The proposed schedule and budget estimate have been carried out with sound methodology” Clarification: Reviewers thought our lab and telescope I&T durations were smaller by 2x than our plan (they are 6 & 12 months, respectively).

4 Response to SDR Reviewer Comments “We will develop another level of cost estimation during preliminary design.” –During system design, we considered project costs composed of hundreds of tasks and specific procurements –Reviewers noted “the budget book showed some pages not complete or no estimates for the words in the task”. Our choice to produce cost sheets for each WBS in each of 4 project phases resulted in blank sheets e.g., no subsystem work during the delivery & commissioning phase –During PD, we will revise the basis of estimate to move more items from engineering judgment and analogy to direct vendor quote basis –Reviewers felt that the laser procurement needs more time & should start much earlier. We agree. Requested next level of cost information for TMT NFIRAOS project to better understand the reasons for the cost estimate differences –This brings us to this presentation …

5 Cost Estimation Methodology (KAON 546) Cost estimation spreadsheets –Based on TMT Cost Book approach, simplified for SD phase –Prepared for each WBS element (~75 in all) –Prepared for each of 4 phases Preliminary design, detailed design, full scale development, delivery/commissioning –Prepared by technical experts responsible for deliverables –Process captures WBS dictionary Major deliverables Estimates of labor hours Estimates of non-labor dollars (incl. tax & shipping) & travel dollars Basis of estimate (e.g. vendor quote, CER, engineering judgment) Contingency risk factors & estimates Descope options –Standard labor classes, labor rates & travel costs used

6 Cost Comparison Goal, Products & Approach Goal of Comparison: –Increase confidence in the NGAO cost estimate Products –Updated cost estimation data base to take advantage of comparison information –Cost comparison presentation (this presentation) Approach –Identify differences between systems –Identify differences in assumptions –Identify similarities & differences in effort & procurement estimates, & resolve/justify these differences –As appropriate update the NGAO cost estimate –Identify other support for NGAO estimates –Respond to reviewer sense that “methodology good, but not fully executed” “NFIRAOS” used as shorthand for the full TMT 1 st light AO configuration –Updates to TMT cost estimate since 2006 (globally < 5%) not incorporated

7 Cost Comparisons (in FY08 $ as reported at the SDR) Upgrades 1 st Gen 8-10m AO 2 nd Gen 8-10m AO 1 st Gen 30m AO

8 Major Differences between NFIRAOS & NGAO 30 m versus 10 m –~ 3x physical size of AO system –3x smaller image  more sensitive to image motion & vibrations –3x more perspective elongation  more laser power for same performance &/or better detectors –9x LGS focus change with zenith angle (1.4 m from zenith to 65  ) –Physical paths for laser beam transport much longer New versus existing telescope –Interfaces and observatory software not as well known for TMT –TMT, NFIRAOS & Instrument I&T could be overlapping –2 nd (or 3 rd ) Keck AO system versus 1 st TMT AO system –Need to be conservative for TMT first light system Architecture & Technologies –Different lasers (new laser suppliers have emerged since TMT 2006 CoDR) –MCAO versus MOAO (2 large high order DMs vs 1 lower order DM + MEMS; & different I&T issues) –NFIRAOS cooled to -30  C versus -15  C for NGAO

9 Major Differences between NFIRAOS & NGAO 9 x 4 x 3 m (blue) box NGAO (below) roughly to NFIRAOS (left) scale 3.8 m

10 High-level Results of Cost Comparison NGAO $42.2M SDR estimate is 48% of NFIRAOS $88.2M CoDR estimate –NGAO $34.5M without contingency is 52% of NFIRAOS $66.7M –All in FY08 $ Cost differences attributed to the following major factors: Modest contingency increase likely needed No significant adjustments required - differences largely understood Conclusions: Need quote for new laser

11 Cost Category Comparison All costs in FY08 dollars –NFIRAOS costs have been inflated by 4%/year for 2 years NFIRAOS cost estimate is 2.1x NGAO –$32.1M difference without contingency ($46.0M with contingency) Major difference is in non-labor (e.g., procurements) –Factor of 2.7 or $28.3M, but less TMT work is performed “in-house”. Other significant differences: –Factor of 1.3 or $4.5M in labor even though NGAO has 14% more labor –NFIRAOS uses 32% contingency versus 22% for NGAO

12 Labor Rate Comparison NFIRAOS average rate = 1.46x NGAO –NFIRAOS average rate = $101/hr –NGAO average rate = $69/hr –Benefit rates are the same –24% burden rate versus 19% at CIT & 0% at WMKO & UCO –NGAO uses actual CIT, UCO & WMKO rates 1.46x represents $6.5M of the $20.5M of NFIRAOS labor

13 WBS Category Comparison Start by removing Component Development & Facility Modifications –NFIRAOS investment (not needed for NGAO) in polar coordinate CCDs & readout electronics to address perspective elongation –NFIRAOS reserves $0.5M for NIR sensor development (NGAO to use available detectors) –NGAO modifications to telescope facility (not needed for NFIRAOS) for new AO system & laser, & to remove old systems > $1M > 5 wy

14 AO System Comparison Sorted by non-labor cost difference Cost of many items, especially LGS WFS & Optics, impacted by different scales of TMT & Keck Equipment & source simulators represent different philosophies –NFIRAOS equipment includes high resolution test WFS, jigs & fixtures, & a turbulence generator versus NGAO alignment tools

15 LGS WFS Assemblies Each lens is ~ 0.4m in diameter Entire ass’ly is ~ 0.5 x 0.5 m 3.1m Six zoom assemblies; 18 mechanisms Note: NFIRAOS PDR design corrects each WFS individually  > ~ $1M savings in lens costs compared with aspheric CoDR design

16 IR LOWFS Assemblies $2.8M versus $2.0M when use NFIRAOS labor rates ~3x tougher requirements for NFIRAOS NFIRAOS estimate to be updated based upon adoption of H1RG detector array

17 Source Simulator and Test Equipment NFIRAOS system ($2.0M hrs) –Source Simulator ($0.9M hrs) Internal to NFIRAOS, provides calibration for LGS and NGS WFS’s $0.67M lenses and 4 fold mirrors (complements the WFS zoom optics); $0.14M beamsplitter –High resolution test wavefront sensor ($0.1M hrs) –Misc Jigs & Fixtures ($0.07M hrs) –Turbulence Generator ($0.9M hrs) External test facility w/ static range Multiconjugate ‘spinning phase plate’ design $0.19M for design; $0.67M for 8 Spherical lenses from 190mm to 420mm diameter to simulate TMT telescope; $0.14M beamsplitter (based on JDSU vendor quote) 62% contingency on FAB phase costs NGAO system ($0.14M hrs) –Source simulator ($0.14M hrs) ‘Spinning phase plate’ design approach Little detail on simulator details (“extension of existing design”) 15% contingency on FSD phase costs –System Alignment Tools (1695 hrs) Tooling for alignment and registration of NGAO subsystems

18 Wavefront Correctors Comparison MCAO vs MOAO NFIRAOS DMs need to be developed NGAO DMs are commercially available –ROM for MEMS64 (being developed for GPI) Estimates based on quotes

19 RTC Comparison Similar complexity & parallel processing approaches NFIRAOS assumes $5.4M RTC contract based on quote –Includes ~ 6.9 work-years at industrial rates NGAO assumes mostly in-house development –Includes 6 extra work-years of labor vs NFIRAOS –NGAO hardware is based on quotes Need to add PSF RT boards ($100k should meet NGAO needs) –Vendor quotes to be obtained prior to PDR to better anchor our estimate Less complex systems for comparison: –NGWFC $2M, including $0.72M Microgate (3 RTC systems) subcontract –Gemini MCAO RTC subcontract was $0.88M –GPI $0.65M; PALM-3000 $0.60M

20 Laser Procurement Comparison Laser Differences –NFIRAOS assumes 3x 50W LMCT lasers quote $6M design & $8.4M construction in FY06 Reduced by ~ $1-2M at PDR by assuming fixed gravity vector –NGAO assumes 2x 50W SOR-type lasers NGAO estimate based on our previous experience trying to set up a company to build SOR-type lasers for Gemini & Keck –FASORtronics recently set up to commercialize this laser We are participating in ESO’s call for laser preliminary designs –ROMs will be available within a month –A fixed price quote will be available at PDR (Aug/09) The SDR reviewers questioned whether 100W would be adequate for the highest order correction –After re-assessment we believe that 100W has sufficient margin by a factor of at least 1.5

21 Laser System Comparison No major procurement differences ( > $1M) –TMT system physically larger Biggest difference is the launch facility labor –NGAO labor based on K1 LGS launch facility –NGAO asterism generator based on LGS WFS pick-off mechanisms NFIRAOS estimate may be somewhat conservative (CoDR level) NGAO may be slightly optimistic –Not obviously missing anything after comparison to NFIRAOS –At most could imagine adding 2 work-years to estimate

22 I&T Comparison NGAO has more labor in all but one category than NFIRAOS –NFIRAOS laser lab I&T includes a full off-telescope system test –NFIRAOS tel. I&T only covers to beginning of science commissioning ~ 25% of NGAO AO telescope I&T is for science commissioning NGAO estimate takes into account past experience with a detailed breakdown Possibility that we are not comparing apples to apples –NFIRAOS may cover some under system eng. & I&T contingency –NGAO assumes that each subsystem is complete & has met its requirements prior to lab I&T (presumably also true for NFIRAOS)

23 Contingency Comparison Management & System Engineering: –22% more NGAO labor pre-contingency –Both NGAO & NFIRAOS assume level of effort –Keck interfaces & telescope well known + 2 nd generation AO system AO & Laser systems: Contingencies fairly close RTC system: NFIRAOS at pre-CoDR study estimate, but have vendor quote –46% NGAO RTC contingency would require $300k more. Laser: NGAO 19% contingency too low. 50% would require $2M more. I&T: NGAO plan has ~1.7x more labor excluding science commissioning Contingencies generated using the same risk evaluation methodology –Will evaluate whether applied adequately & consistently for NGAO $7.7M NGAO contingency $22.0M NFIRAOS contingency

24 Conclusions NGAO is traceably less expensive than NFIRAOS & we understand why Some areas identified that require more work: –Contingency rates need to be re-evaluated At minimum should be increased for laser & potentially for RTC –Laser procurement estimate needs to be more solidly based Will have ROMs soon & a fixed price quote for PDR through ESO collaboration –Minor items: Laser system labor & cost of RTC labor NFIRAOS comparison was worthwhile for determining confidence in NGAO estimate. –Methodology largely gave us reasonable system design estimates A cost review will be part of the NGAO PDR –We will include NFIRAOS PDR estimate comparison