FAC, 4/16/07 D. Schultz 1 e-Beams Systems Update People ARR Linac Installation Undulator Production MMF Operations David Schultz.

Slides:



Advertisements
Similar presentations
Jose Chan FAC- Undulator System Installation & Assembly 10/30/07 1 Undulator System Installation & Assembly Schedule Jose.
Advertisements

Kathleen Ratcliffe BC2/Linac Installation April 16, BC2 / Linac Installation Coordination Kathleen.
Rodd Pope, SLAC Undulator System October 12-13, 2006 FAC Meeting 1 Undulator System Assembly Plans Rodd Pope, SLAC.
Rodd Pope, SLAC Undulator System April 16-17, 2007 FAC Meeting 1 Undulator System Assembly, Installation, and Integration.
Richard M. Boyce FAC Review – Accelerator Installation October 29-31, Installation – Accelerator Systems Installation Planning.
FAC review, 10/27 D. Schultz 1 e-Beams System Update Injector System Installation has started. Linac System Preparing for ’06 installation. Controls System.
FAC, 10/12/06 D. Schultz 1 e-Beams Systems Update Linac Injector Undulator Production MMF commissioning ARR David Schultz.
FAC, 4/20/06 D. Schultz 1 e-Beams System Update Linac System Preparing for downtime installation. Injector System Installation has started. Undulator System.
Hamid Shoaee Control System Installation 3/16/ Downtime Readiness Review Hamid Shoaee For LCLS Controls Group.
FAC 4/20/06 D. Schultz 1 The SAD and ARR for Commissioning The Status of the SAD Being written as a part of the SLAC Linac SAD The Status of the ARR Design.
Apr. 16, 2007 Undulator Breakout Dean R. Walters 1 Vacuum System Undulator Vacuum System Dean R. Walters Soon-Hong Lee, James Bailey, James.
Jose Chan and Kathleen Ratcliffe FAC Review- LTU/DUMP installation Status & 6/16/08 1 Linac Installation Status, Schedule.
LTU & Electron Beam Dump Linac Coherent Light Source Stanford Synchrotron Radiation Laboratory Stanford Linear Accelerator Center LCLS Technical Design.
John N. Galayda LCLS FAC 20 April Linac Coherent Light Source Overview and Charge Facility Advisory Committee John.
Jose Chan FAC - BC2/Linac Installation Status & 4/16/07 1 BC2/Linac Installation Status & Schedule Jose Chan.
Richard M. Boyce FAC April 16, LCLS Installation & Planning Integration process – IMT 2007 Installation Planning BTH.
Eric Bong LCLS FAC Injector-Linac October 27, 2005 Injector Design / Diagnostics / Gun & Linac RF Design E. Bong LCLS FAC.
Mark Reichanadter LCLS FAC April 20-21, 2006 Meeting of the LCLS Facilities Advisory Committee LCLS Project Management M.
LCLS Linac Long Lead Procurement Linac Coherent Light Source Stanford Synchrotron Radiation Laboratory Stanford Linear Accelerator.
John Arthur Photon October 29, Photon Systems Update FAC recommendations Current status New plan for Photon Systems.
Richard M. Boyce FAC October 29-31, Installation Planning Integration process – IMT update Installation Planning &
LCLS Linac System Management Linac Coherent Light Source Stanford Synchrotron Radiation Laboratory Stanford Linear Accelerator Center.
D. Schultz FAC 6/17/08 1 e-Beams Systems Update People Progress the last review LTU and Dump Installation Status Undulator.
Stephen Milton Undulator System 20 April, 2006 LCLS Undulator System Update S. Milton, ANL FAC, April 20 th, 2006.
Rodd Pope, SLAC Undulator System April 20-21, 2006 FAC Meeting 1 Undulator System Assembly Plans Rodd Pope, SLAC In collaboration.
Hamid Shoaee LCLS FAC Controls June 17, LCLS Control System Personnel Linac & BC2 Controls progress LTU, Dump Controls.
Eric Bong LCLS FAC Injector-Linac System October 27, 2005 Injector –Linac System Overview E. Bong LCLS FAC October 27, 2005.
E. Michael Saleski PPS and April 20, 2006 LCLS Personnel Protection System and Beam Containment System E. Michael Saleski.
David H. Dowell Injector April 29-30, 2004 LCLS Injector Overview D. H. Dowell, SLAC FAC Review April 29-30, 2004 Injector.
Hamid Shoaee LCLS FAC Review – October Control System Overview Hamid Shoaee Controls System Manager Injector control system commissioning & Support.
A U.S. Department of Energy Office of Science Laboratory Operated by The University of Chicago Argonne National Laboratory Office of Science U.S. Department.
Geoff Pile LCLS Und. System Fabrication FAC 29 th, 30 th & 31 st October 2007 LCLS Undulator System Fabrication Schedule FAC.
C.E. Rago Inj/Lin Design & 4_20_06 1 Injector / Linac Design & Fabrication C.E. Rago FAC Review 04_20_06.
FAC, 10/12/06 D. Schultz 1 Readiness for 2007 Startup Linac Injector Controls ARR David Schultz.
1 st All Hands Meeting Milton 20 Feb st ANL LCLS All Hands Meeting 20 February, 2006.
David Schultz Accelerator Readiness Dec. 2, ‘08 SLAC National Accelerator Laboratory 1 Undulator Complex Status LCLS Introduction.
LCLS Accelerator SLAC linac tunnel research yard Linac-0 L =6 m Linac-1 L  9 m  rf   25° Linac-2 L  330 m  rf   41° Linac-3 L  550 m  rf  0°
Marjorie Widmeyer LCLS Injector Magnet Power March 30, LCLS Injector, Sector 21 and BC1 DC Magnet Power and Control.
Hamid Shoaee Control LCLS ARR Oct 31, LCLS Accelerator Readiness Review Control System for Injector Commissioning.
Injector Performance Requirements Conventional Facilities Update
Injector –Linac Status & Schedule E. Bong LCLS FAC October 12, 2006
LTU/Undulator Installation Status
e-Beams Systems Update
Linac/BC1 Commissioning P
Electron Beam Systems ETC and Methodology
Injector / Linac Installation Current Status
LCLS Commissioning P. Emma, et al
Integrated Safety and Environmental Management
Electron Beam Systems Wrap-up
LCLS Undulator System Production Management
LCLS Undulator System Status
Shutdown Planning & Installation Schedule
LCLS Personnel Protection System and Beam Containment System
E-Beams Systems Manager
LTU/Undulator Installation Status
LCLS Injector System Overview D. H
Electron Beam Systems ETC and Methodology
Injector/Linac Design Status C. E
Undulators Subgroup Summary April FAC Review K. Robinson, J
Undulator Assembly and Installation Planning
LCLS e- Beams System Overview
Undulator and Magnet Production Status 25 October 2006
e-Beams Systems Update
BC2 / Linac Installation Coordination Kathleen Ratcliffe
LINAC System Engineering / Design Status C.E. Rago
LCLS Control System Personnel Linac & BC2 Controls progress
DOE Status Meeting of the LCLS Project
LCLS e- Beams Systems Manager
Injector/Linac RF Status
Control System Overview Hamid Shoaee LCLS Control System Manager
Presentation transcript:

FAC, 4/16/07 D. Schultz 1 e-Beams Systems Update People ARR Linac Installation Undulator Production MMF Operations David Schultz

FAC, 4/16/07 D. Schultz 2 New responsibilities in Linac and Undulator Jose Chan is the new Cost Account Manager for LCLS Injector and Linac Systems, taking over from Eric Bong. Geoff Pile is the new Cost Account Manager for Undulator Systems at ANL, taking over from Steve Milton.

FAC, 4/16/07 D. Schultz 3 Injector Accelerator Readiness Review

FAC, 4/16/07 D. Schultz 4 Injector Accelerator Readiness Review Safety Assessment Document The LCLS SAD for Injector Commissioning was approved Jan. 24 th. Accelerator Readiness Review (ARR) The ARR for Injector Commissioning was held October 31st. The committee (in part) reconvened March 14 th. The four pre-start items were cleared when the ARR report was released. Four comments from the SSO were also addressed. Approval to operate was given April 4 th.

FAC, 4/16/07 D. Schultz 5 Injector Commissioning First electrons from the gun 4/5/07 Courtesy P. Emma Injector Commissioning is underway. Commissioning has been impeded by faulty hardware Problems with profile monitors, toroids, FC Working on improving QA, in the shops, with vendors and during installation.

FAC, 4/16/07 D. Schultz Commissioning BC1 BLM LX L1 Ins/SAB Wall Laser stopper Sector 20 Sector 21 See P. Emma’s talk

FAC, 4/16/07 D. Schultz 7 SLAC linac tunnel research yard Linac-0 L =6 m Linac-1 L  9 m Linac-2 L  330 m Linac-3 L  550 m BC1 L  6 m BC2 L  22 m DL2 L =275 m ‘Wall region’ undulator L =130 m 6 MeV 135 MeV 250 MeV4.30 GeV13.6 GeV Linac-X L =0.6 m 21-1 b,c,d...existing linac L0-a,b rf gun 21-3b 24-6d X 25-1a 30-8c Now commissioning 2007 down Installation Schedule

FAC, 4/16/07 D. Schultz 8 Draft LCLS Installation and Commissioning Time-Line April 12, 2007 rmb AASSOONNDDJJFFMMAAMMJJJJAASSOONNDDJJFFMMAAMMJJJJ Drive- Laser Installed Drive-Laser Commissioning Gun/Inj/BC1 Commissioning Gun/Inj./BC1 Install linac/BC2 Install Linac/BC2 Commissioning LTU/Und/Dump FEE/NEH Install LTU/und. hall “ready” ControlsCheckout LTU/und. Commissioning First Spont. Light AASS CD-4a OONNDDJJFFMM PPS ControlsCheckout Checkouts ’08 inst. sched. under development

FAC, 4/16/07 D. Schultz 9 ’07 Downtime Installation Sept., Oct., Nov. 2007, a very tight schedule. Installation of BC2 and L3, not L2. Installation to support BTH-West Cable plant installation through the BSY Coordinated through the AD downtime schedule IRR held March 16 th. Kicker magnet design is still ongoing. Cable plant inst. schedule is tight. Scheduling and coordination between the different disciplines will be vital. See breakout talks

FAC, 4/16/07 D. Schultz 10 ’08 Installation LTU/Undulator/Dump Readiness for early occupancy held at Nov. 1, 2007 Begin installation with: Metrology Beamline supports Cable plant Installation scheduling to be coordinated by R. M. Boyce Installation contracts need to go to bid this summer. Need to complete designs to support these. See breakout talk

FAC, 4/16/07 D. Schultz 11 Undulator Systems Components Quadrupole magnets on order. Beam Finder Wire going to procurement. Wire card a SLAC responsibility, design underway. Support/Mover system going to procurement. RF Beam Position Monitor in development. Prototype being brazed. Vacuum Chamber – next slide These systems are all near the critical path. WPM/HLS FDR was held March 22nd See G. Pile’s talk

FAC, 4/16/07 D. Schultz 12 Undulator vacuum chamber - 4-Weld Design Two competing designs were carried to the prototype stage. Review of the Undulator Vacuum Chamber Design Options, Feb. 22 nd The 4-Weld design was selected to remain the baseline. Early 4-Weld prototype 2 full size prototypes have been produced and tested. Vacuum properties, mag. permeability, surface coating process, look good. Fabrication schedule identified as a problem. Ordering materials now, preparing the fab. bid package

FAC, 4/16/07 D. Schultz 13 Undulator Magnetic Measurement 35 undulators have been accepted at the vendors. 20 undulators are at SLAC. All undulators will be at SLAC by July. The MMF is in a production mode, but behind schedule. 3 undulators finished magnetically, but not RFI. 1 undulator in fine tuning, 1 in rough tuning. Production rate is approaching 1 per week. Learning to deal with the exceptional cases. See breakout talk

FAC, 4/16/07 D. Schultz 14 The ’07 downtime Linac installation schedule is very tight. Hardware availability is being closely monitored Kicker magnet, cable plant, are concerns Controls checkout (last) is at risk. The Undulator vacuum chamber is still on the critical path. This schedule is being pushed. RFBPM production schedule is close to critical. The MMF is in production. Need to solidly demonstrate throughput. Issues

FAC, 4/16/07 D. Schultz 15 end