MOM Report Paul Soler MICE Operations Manager University of Glasgow MICO April 20, 2009.

Slides:



Advertisements
Similar presentations
K. Long, 18 April, 2015 Beam-line status — red sky at night?
Advertisements

14 June 2007VELOEddy Jans 0 Recent VELO-installation++ activities June 14, 2007 Potmeter calibration Bake-out Cabling & Commissioning.
Russ Rucinski, PPD/MD/DZero Ops DZero Solenoid status November 29, 2004.
MOM Report Ray Gamet MICE Operations Manager University of Liverpool MICO 18 th May 2009.
June 26, 2009TLH, NFMCC Friday Meeting1 MICE Updates MICE News Overview ISIS and MICE Schedules DAQ Review Spectrometer Update Aspirational Schedule Terry.
MOM report 23/9 – 28/9 G.CECCHET. MOM report Hall PPS commissioning Target tests last night MOM laptop.
MOM Summary 19/01/10 Water Now the ice has cleared I am able to get on the roof again. Could do with getting the conductivity readings fed back similarly.
MOM Summary 11/01/10 Due to the Inclement Weather it has perhaps been quieter than usual Water - Tank has been holding water fine. Some ice has been forming.
MOM Report Paul Soler MICE Operations Manager University of Glasgow MICO April 27, 2009.
MOM Report Michael S. Zisman MICE Operations Manager Center for Beam Physics Lawrence Berkeley National Laboratory MICO March 16, 2009.
MOM Report Paul Soler MICE Operations Manager University of Glasgow MICE Video Conference April 22, 2010.
Linda R. Coney – 24th April 2009 MOM Update Linda R. Coney 21 September, 2009.
Linda R. Coney – 24th September 2009 MOM Update End of Sept Run Linda R. Coney 05 October, 2009.
MOM Report Linda R. Coney MICE Operations Manager University of California, Riverside MICO March 23, 2009.
Project Report Paul Drumm CM15, FNAL June MICE Schedule Overview First beam September/October 2007 –Shutdown from January 2007 –Eight months for.
Acceptance Criteria for the Decay Solenoid Tom Bradshaw Mike Courthold Matthew Hills.
MOM Report Ray Gamet MICE Operations Manager University of Liverpool MICO 11 th May 2009.
MICO 22 nd February 2010 Terry Hart (MOM) - Decay Solenoid and Target - MICE Machine Physics runs - User Run Plans.
MICO Meeting, 1 st March 2010 Terry Hart (MOM) - Decay Solenoid - Targets - DAQ - March User Runs Plans - Suggestions.
MOM Report Paul Soler MICE Operations Manager University of Glasgow MICO April 12, 2010.
MOM - M.ApollonioMICO meeting - RAL - 17/3/20081 NEXT steps + proposed aims Today - START Cherenkov INSTALLATION (?) Tuesday 25 MARCH - MICO Meeting (?
M. apollonioAccel. R&D/Physics and IADR - RAL - 19/3/ Magnets Dry Run ISIS Scheduling Meeting Latest news on Target Ready to run ? Summary of: Magnets.
MOM Report. Shield Wall – Gone Before During After 2.
Detector Systems Update MICO March 3, MICE Detector Systems  CKOV u CKOV humidity (HIH4000) and temperature (LM35) sensors in hand for installation.
Pierrick Hanlet MICO June 6, 2011 MICE Operations Manager Report.
MOM Report Paul Soler MICE Operations Manager University of Glasgow MICO April 26, 2010.
MOM Report Paul Soler MICE Operations Manager University of Glasgow MICO May 5, 2009.
Spectrometer Solenoid Fabrication & Testing Update Steve Virostek Lawrence Berkeley National Lab MICE CM24 at RAL June 1, 2009.
MOM Report Linda Coney MICE Operations Manager University of California, Riverside MICO Meeting June 7, 2010.
MOM Report Paul Soler MICE Operations Manager University of Glasgow MICO April 4, 2011.
MOM Report Linda R. Coney MICE Operations Manager University of California, Riverside MICO April 6, 2009.
MICO 8 th February 2010 Terry Hart (MOM) - Decay Solenoid and Target - MICE Machine Physics runs - Problems and Issues.
MOM Report Paul Soler MICE Operations Manager University of Glasgow MICO April 19, 2010.
MICO 15 th February 2010 Terry Hart (MOM) - Decay Solenoid and Target - MICE Machine Physics runs - User Run Plans.
Spectrometer Solenoid Update Michael S. Zisman Center for Beam Physics Accelerator & Fusion Research Division Lawrence Berkeley National Laboratory MICO.
Hydrogen Delivery System – R&D Activities T W Bradshaw M Courthold M Hills J Rochford Daresbury Controls Group etc…
MOM Report Linda R. Coney MICE Operations Manager University of California, Riverside MICO March 30, 2009.
MOM Report Linda Coney MICE Operations Manager University of California, Riverside MICO Meeting May 24, 2010.
1 Summary of MICE beamline & hall installations This is a very rough summary of the progress since mid-December Richard Apsimon & Andy Nichols MICO meeting.
MICE - UK Project Progress Roy Preece 30 th April 2013.
1 Hall & Beamline Installation Richard Apsimon, Andy Nichols, Willie Spensley MICE Collaboration Meeting, th Feb 2008.
Linda Coney MC VC May 19, 2011 MICE Operations Manager Report.
Status of installed target Preparation of “demonstrator” target Chris Booth Sheffield 25 th January 2008.
Hydrogen system R&D. R&D programme – general points Hydrogen absorber system incorporates 2 novel aspects Hydrogen storage using a hydride bed Hydrogen.
Spectrometer Solenoids MICO 197 Steve Virostek LBNL August 15, 2012.
MOM Report Victoria Blackmore VC /06/11 1/7.
Click to add Text L. CONEY1 MICE Shifter Training June 2015.
Spectrometer Solenoid: Plans to Fix Magnet 2 Steve Virostek Lawrence Berkeley National Lab Spectrometer Solenoid Review November 18, 2009.
CM1 Thermal Cycle CM1 Warmup –1/4/12 (Wed.) to 1/6/12 (Fri.) (~50 hours) –Verified turbo interlock system works CM1 Cooldown –Began 1/9/12 (Monday) –At.
1 MICE Hall construction status Richard Apsimon MICE VC meeting 29th Nov 2007.
Linda R. Coney – 24th September 2009 MOM Update Linda R. Coney 24 September, 2009.
Spectrometer Solenoid Fabrication & Testing Update Steve Virostek Lawrence Berkeley National Lab MICE CM25 at RAL November 6, 2009.
MOM Report Paul Soler MICE Operations Manager University of Glasgow MICE Video Conference May 7, 2009.
1 MICE Hall and Infrastructure - Progress since CM18 Chris Nelson MICE CM19 Oct 2007.
MOM Report Paul Hodgson Paul Soler Victoria Blackmore VC-139: 14/04/111/8.
1 MICE PM Report Summary since CM21 Decay solenoid Infrastructure progress Step One Installation Worries MICE Video Conference, 19 th June, 2008.
1 MICE Beamline Installation, status & plans Contents: Upstream & Target, BPM Decay solenoid DSA, D2, Q4,5,6 cKOV support Q7,8,9 Open issues & concerns.
UK Update Package Managers Meeting 001 Roy Preece 13 th January 2014.
March 18, 2008 TJRMICE Beamline Status1 MICE Beamline Status (March 18, 2008) Tom Roberts Muons, Inc. Illinois Institute of Technology.
MICE Project Report Alan Bross (for Paul Drumm). Project Issues ● Key dates: – ISIS Synchrotron start-up scheduled for 1st August ● Shielded area around.
CM27 – 8 th July 2010 LH2 System Progress and Future Plans M Hills T Bradshaw M Courthold I Mullacrane P Warburton.
Running plan Step I.1 Basic radiation levels. I.1.1 ISIS running with beam elements on, target off, beam stop shut. Establish permanent MICE monitoring.
Pre-CM33 schedule planning SuperMICO meeting, June 6th Motivation: For all of us to understand the main drivers behind the top-level MICE schedule So that.
MOM Report Linda Coney MICE Operations Manager University of California, Riverside MICE Video Conference May 20, 2010.
Beamline Update Adam Dobbs, MICE CM38 Feb Contents Recent and Upcoming Activities Target Conventional magnets Decay Solenoid Proton Absorber Summary.
1 MICE PM Report Phase One installations to date Phase One remaining items Progress with Phase Two Worries Don’t have time for a detailed status report,
S A Griffiths CM42 June 2015 Electrical & Control.
MICE Hall Summer Workplan
Project Manager’s Report + DC/MoM Report
MICE PM Report Progress with the Infrastructure A few problems
Presentation transcript:

MOM Report Paul Soler MICE Operations Manager University of Glasgow MICO April 20, 2009

Commissioning Needs-Soler2 Commissioning Needs Working Decay Solenoid – Stands.. Many thanks to Matt, Jim, Mike, Willie, Linda, …. —Cooldown completed Thursday 16 April, temperature ~4.5K —Matt attempted turning on power supply on Friday 17 April (14:30) but quench protector light number 5 tripped o Helium vented from cryostat relief back up to buffer tank as expected (fridge trip signal not disabled). o Dewar emptied and temperature initially raised to K but by 17:00 dewar refilled to 80% and temperature back to 4.5K —One vacuum pump tripped over weekend (but isolated from circuit) —Successfully turned on power supply and ramped up to 400 A today o Evidence that all coils have gone superconducting (0V at stable current) o First indication that solenoid fix (ie. fitting Multi-Layer Installation) has solved quenching problem in magnet o Quench Protector keeps on tripping at turn on (it was bypassed for test) – light number 5 still trips o Solenoid warning lights now also working when AC contact on/off o Need to discuss when to go to full current (870 A) —Need PSI expert to ensure Quench Protector working

April 20, 2009Commissioning Needs-Soler3 Solenoid Control System

April 20, 2009Commissioning Needs-Soler4 DS Cooldown Sequence 4.6K

April 20, 2009Commissioning Needs-Soler5 DS Ramp Up 400 A* * Current badly calibrated in control system: 332A in plot corresponds to 400 A Polarity of circuit for C10 seems to be reversed Total voltage all coils

April 20, 2009Commissioning Needs-Soler6 Commissioning Needs Working target – Stands.. —one in R78 for demo —one in ISIS for data Detectors – —luminosity monitor o Brunel & Paul Soler working on this - ~£1300 for new PMTs —Tracker cryostats o Test Pressure Release valve by Alan this week – still to happen o Install emergency shutoff valves on cryostats – all 4 installed and working o Install exhaust filter – this week —CKOV o New temp and humidity monitoring device installed o Need network connection and power in the DSA – installed but info not yet logged (next week) o HV power supply crate died (spare) – removed and sent for repair Get Decay Solenoid magnet-on lights working —repositioned light on top of turret – both lights now working Air conditioning —6 holes in West Wall for A/C venting finished. Need supports for pipes

April 20, 2009Commissioning Needs-Soler7 Issues Main commissioning issue: when to remove shielding? —Need to make decision by 23 April —Willie suggests we wait till August shutdown to remove shielding since quench protection will not be verified Proposed schedule by Willie: 1.Wednesday 19th August erect scaffold 2.Twenty wooden pallets to be delivered to Synchrotron 3.Thursday 20th August commence removal of shield steel plate (Total mass 22.4 Tonne) 4.From Thursday - Sunday we need to remove 5.6 tonne's per/day 5.Monday 24th August strip down support frame 6.Monday 24th August re-position Dipole 1 7.Monday 24th August make a request to ISIS Teams Mechanical & Vacuum for the coupling of Water works to Dipole 1 and the re-installation of vacuum pipe work and Ion pump to commence 25th August Can accommodate schedule also if we have to wait 1 week for radiation cooldown Parallel work on target should not be issue since not in same area, different people involved and crane only needed for 1 day for target installation

April 20, 2009Commissioning Needs-Soler8 Issues Documentation inventory/overhaul - ongoing —Instructions for shifters – old documentation needs updating —Safety – need all relevant documents in one obvious place Computing —Need network connections to progress in Hall —Still cannot print on OKI printer in R76 —Wireless in R76 still not installed but network people aware of problem —Need Windows PC in MLCR – still pending —Need connection to GRID from MLCR – pending Need beamline magnets on to test alarm handler —Water will be restored to magnets – during this week