Russell Cave Elementary – Renovation Architect: Pearson & Peters Architects General Contractor: Congleton-Hacker Construction Substantial Completion Date:August,

Slides:



Advertisements
Similar presentations
Update on FCPS Construction/Renovation Projects June 2009.
Advertisements

Update on FCPS Construction/Renovation Projects July 2009.
West Elementary School May 16, % Construction Documents.
Update on FCPS Construction/Renovation Projects September 2009.
Update on FCPS Construction/Renovation Projects May 2009.
Update on FCPS Construction/Renovation Projects April 2009.
05/07/12 – 5/13/12 Phase 1 Demolition at West Entry Complete; Drilled Piers and footers Started.
Cigarroa Middle School Cigarroa High School Ashley Humphries & Sanchez Architects Construction Documents phase Administration Classroom Bldg. Storage Storage.
Harding Elementary School Exterior Repairs & Select Roofing Replacement 08/12/2014.
Coronado Elementary School Project Status Update 05/13/14.
Update on FCPS Construction/Renovation Projects August 2009.
April 21, 2010 Barbara C. Jordan Elementary School Update Presented by.
Bryan Station Middle – Renovation Architect: Clotfelter-Samokar Architects General Contractor: Preston Construction Group Substantial Completion Date:August,
Progress Report 12/13/11. Progress Schedule December 2011 Work Completed December: Installed Concrete topping on roof Rough In M&E East side screen wall.
Education Campus What a Difference a Year Makes! Takoma.
Remsenburg – Speonk Union Free School District Elementary School Bond Planning Presentation October 12, 2010 BBS Architects and Engineers and Triton Construction.
Arlington Elementary – Renovation Architect: RossTarrant Architects General Contractor: W/S Construction Substantial Completion Date:August, 2010 Contract.
October 2009 Construction Progress. University City School District Bond Wolfe Architects – architect McCarthy Construction – construction manager Barbara.
Leestown Middle – Renovation Architect: Lucas/Schwering Architects General Contractor: D.W. Wilburn, Inc. Substantial Completion Date:August, 2010 GC Contract.
SHEPHERD ELEMENTARY SCHOOL PHASE I SHEPHERD ELEMENTARY SCHOOL PHASE I SITE PLAN.
Cassidy Elementary – Renovation Architect: Tate.Hill.Jacobs: Architects General Contractor: D.W. Wilburn, Inc. Substantial Completion Date:August, 2010.
Facilities Modernization Program Funded by Measure B Project Report April 16, 2012.
Bryan Station Middle – Renovation Architect: Clotfelter-Samokar Architects General Contractor: Preston Construction Group Substantial Completion Date:August,
PIONEER HIGH SCHOOL WEST STADIUM PHASE 1. EXECUTIVE SUMMARY Erickson Hall (EHCC) was the awarded the Pioneer High School Phase 1 Construction Contract.
Russell Cave Elementary – Renovation Architect: Pearson & Peters Architects General Contractor: Congleton-Hacker Construction Substantial Completion Date:August,
Russell Cave Elementary – Renovation Architect: Pearson & Peters Architects General Contractor: Congleton-Hacker Construction Substantial Completion Date:August,
LISD Board of Trustees Construction Committee Meeting Tuesday, December 11, 2001.
Board of Education Presentation 2015 Referendum Projects September 9, 2015 Update.
Progress Photos Goodnoe Elementary School Additions and Renovations Project November 2013 Goodnoe Elementary School.
Facilities Modernization Program Funded by Measure B Project Report March 19, 2012.
Facilities Modernization Program Funded by Measure B Project Report November 21, 2011.
Update on FCPS Construction/Renovation Projects March 2009.
Example NAMEROLE Ron LilleyProject Manager ???Project Inspector ????County Planner ????Zoning Inspector HBACivil Engineer ????Architect ????Mechanical.
Abney Enterprises L.L.C. Concessions International Cooler Addition Phase II Project.
1 Facility Construction Committee February 11, :30 PM Facility Construction Department Construction Status Report Presentation to the by the.
New Middle School Geneva, Il Greg Kemerer AE Senior Thesis 2006 – CM Option.
Prof Ralph V. Locurcio, PE CON 2001 CVE Sequence Single Family House - 3,000 square feet Duration 1 General Conditions 21 2 Apply for Permits.
Cassidy Elementary – Renovation Architect: Tate.Hill.Jacobs: Architects General Contractor: D.W. Wilburn, Inc. Substantial Completion Date:August, 2010.
F ACILITIES, P LANNING, AND C ONSTRUCTION November 16, 2015 – Monthly Construction Report Report.
F ACILITIES, P LANNING, AND C ONSTRUCTION December 14, 2015 – Monthly Construction Report.
Cassidy Elementary – Renovation Architect: Tate.Hill.Jacobs: Architects General Contractor: D.W. Wilburn, Inc. Substantial Completion Date:August, 2010.
South Halls: Ewing-Cross Renovation AE Senior Thesis: Tech. 1 Quaid Spearing CM Option September 16, 2013.
Elevating the Quality of Life in the District. Agenda  SITE VIEW  SECTIONS  CONSTRUCTION STRATEGY  TIMELINE – JUNE 2013 TO JULY 2015  TIMELINE –
Russell Cave Elementary – Renovation Architect: Pearson & Peters Architects General Contractor: Congleton-Hacker Construction Substantial Completion Date:August,
October 19, 2011 Construction Progress Report. Construction Progress Report – October 19, 2011 Contract sum to date:$ 162,736,722* Total completed to.
Salmon River CSD Capital Project Phase II Monthly Status Report March & April 2016.
DAVIS SR. HIGH SCHOOL ALL-STUDENT CENTER (MULTIPURPOSE BUILDING) PROGRAMMING OPTIONS August 6, 2015.
1 Guinn School Restoration Update Presented by Transportation and Public Works Department February 17, 2009.
Miller Driscoll Building Committee Update Tuesday, January 7, :00 PM - 7:00 PM Presented by: Turner Construction, CMA 1 Additions & Alterations Miller-Driscoll.
1 Punch list / Close Out - Project Completion Best Practices May 2016.
Miller Driscoll Building Committee Construction Update Thursday April 7, :00 PM - 7:00 PM Presented by: Turner Construction, CMA 1 Additions & Alterations.
LIFE CYCLES OF AIKEN COUNTY PUBLIC SCHOOLS CONSTRUCTION PROJECT October 8, 2013.
White Pigeon Community Schools
April 2016 Bond / Facilities Update Presentation
Bond Oversight Committee
UPDATE ON DOE RUN ELEMENTARY CONSTRUCTION PROGRESS
Construction Documents
BURROUGHS HIGH SCHOOL PROJECT STATUS REPORT February 2017 Fast Facts
G R E A T L A K E S B U I L D E R S A Re-construction Company Specializing in Structural Remediation and Alterations.
HANDICAPPED PEOPLE RESIDENT
Progress Report 11/10/11.
Minuteman Vocational Technical Regional High School Progress
2007 Bond Issue Capital Improvement Program
Construction Engineering Change Order - 2 Prof. Ralph V. Locurcio, PE
Construction Engineering Change Order - 2 Prof. Ralph V. Locurcio, PE
Lincoln Common Redevelopment Construction Update.
Capital Outlay Workshop
Minuteman Vocational Technical Regional High School Progress
PULSE Building Renovation
North Augusta High School – Phase 2A and 2B
Presentation transcript:

Russell Cave Elementary – Renovation Architect: Pearson & Peters Architects General Contractor: Congleton-Hacker Construction Substantial Completion Date:August, 2010 Contract Sum:$5,001,150 Change Orders to Date:$0 Current Phase:1 (On Schedule) Estimated Completion:6% June 2009

Russell Cave Elementary – Renovation Rendering of Final Façade June 2009

Russell Cave Elementary – Renovation Work Completed in Last 30 Days: Footing and foundation walls continue: 40 feet of footings poured and 38 feet of foundation wall have been poured Interior wall footings: 200 feet have been poured. Footings at new mechanical enclosures have been poured. Pads for mech units at kitchen and new transformer and generator have been poured. Current Work Effort (June): Additional work on footings and foundation at the new addition will continue. New floor slab will be poured in two weeks, weather permitting. Installation of the new leach fields for the septic system will begin installation in the front lawn of the building. Kitchen/Cafeteria demolition and renovation will begin. Renovation of (4) classrooms on the south side will begin. Masonry restoration on the existing building will begin the week of June 8 th. June 2009

Russell Cave Elementary – Renovation Foundation Work June 2009 Foundation Work