October 2009 Construction Progress. University City School District Bond Wolfe Architects – architect McCarthy Construction – construction manager Barbara.

Similar presentations


Presentation on theme: "October 2009 Construction Progress. University City School District Bond Wolfe Architects – architect McCarthy Construction – construction manager Barbara."— Presentation transcript:

1 October 2009 Construction Progress

2 University City School District Bond Wolfe Architects – architect McCarthy Construction – construction manager Barbara Jordan Elementary Ameresco Engineering – performance contractor Flynn Park Elementary School Jackson Park Elementary School Brittany Woods Middle School High School

3

4 Barbara C. Jordan Elementary

5 BP-A ENVIRONMENTAL OPERATIONS, INC. –WC-1 HAZARDOUS WASTE ABATEMENT - 100% BP-B SPIRTAS WRECKING COMPANY –WC-2 BUILDING DEMOLITION - 90% BP-C KUESEL –WC-3 EARTHWORK (TREE PROTECTION) - 1% –WC-4 SITE UTILITIES - 1% CONSTRUCTION ACTIVITY TO DATE BP-A ENVIRONMENTAL OPERATIONS, INC. –WC-1 HAZARDOUS WASTE ABATEMENT - 100% BP-B SPIRTAS WRECKING COMPANY –WC-2 BUILDING DEMOLITION - 100% BP-C KUESEL –WC-3 EARTHWORK (TREE PROTECTION) - 1% –WC-4 SITE UTILITIES - 1%

6 FUTURE ACTIVITIES BP-D –WC-5 CONCRETE - 7 BIDS Awarded to Wilson Concrete MBE Commitment – 15% WBE Commitment – 8% Minority Workforce Commitment – 10% –WC-6 STEEL - 3 BIDS Awarded to Ben Hur Steel MBE Commitment – 15% WBE Commitment – 5% Minority Workforce Commitment – 10% BP-E and F –WC-7 thru WC-23 Bidding December and January Completes all work

7 MBE/WBE PARTICIPATION BP-A ENVIRONMENTAL OPERATIONS, INC. –MBE Participation - 29% –WBE Participation - 0% –Minority Workforce - 32% BP-B SPIRTAS WRECKING COMPANY –MBE Participation -15% –WBE Participation - 10% –Minority Workforce - 22%

8 Master Budget Set at $13M Current Post DD Estimate $13.3M $200K savings on Concrete and Steel Recent Bidding Favorable Market Conditions Includes: –Sustainable design –LEED Certification –Desired Program Space BUDGET UPDATE

9

10

11

12

13

14

15 University City High School Switchback Ramp Gym Restrooms Cafeteria Restrooms Entry/Auditorium Exterior ADA Parking Third Floor Science Wing Renovation Flynn Park Brittany Woods Jackson Park

16 Maplewood-Richmond Heights School District Ameresco Engineering – performance contractor Flynn Park Elementary School Jackson Park Elementary School Brittany Woods Middle School High School

17 University City High School - Switchback Ramp Work to Date: Complete

18 University City High School - Gym Restrooms Work to date: Demo is complete New mechanical duct and exhaust fans are installed All plumbing rough in is complete Wall are blocked and tiled Walls are tiled, ceiling is complete Desco floor is installed Door frames are set Paint is complete Plumbing trim started 10-15-09 Toilet partitions are complete University City High School - Gym Restrooms Future work over the next three weeks: Doors, hardware, toilet accessories Bradley sink Electrical trim out Punch list for a few complete items

19

20 University City High School – Cafeteria Restrooms Work to date: Abatement and demo is complete All major mechanical, electrical and plumbing relocations are complete, including electrical feeder relocation New mechanical duct and exhaust fans are installed Plumbing underground rough-in is complete Hydronic/chilled water piping has been rerouted Trenches have been backfilled and concrete floor has been poured back Plumbing rough in is complete Wall are blocked and tiled Desco floor is installed Ceiling is installed Door frames are set Painting is complete Plumbing trim began 10-21-09 University City High School – Cafeteria Restrooms Future work over the next three weeks: Excavate and construct elevator pit, including sump pump installation Electrical rough in will wrap up Doors, frames, hardware, toilet accessories Electrical trim out Plumbing and electrical trim out

21

22 University City High School – Entry/Auditorium Work to date: Wood is cleaned up and sealed, new paint, terrazzo repair, stone cleaning and temporary interior lights University City High School – Entry/Auditorium Future work over the next several weeks: Lobby lights will continue to be restored and look to be installed by the end of the month Aisle lighting and carpet

23

24 University City High School – Exterior Work to date: Front entry elevation is washed, tuck pointed, various stones repaired and caulked Front steps are reset and broken treads have been replaced Lintel replacement has begun along Balson and Jackson streets Planter walls at front entry are caulked Caulked half the joints at entry steps, have the other half to go once first half cures Water main in the limits of our excavation was replaced Waterproofing and backfilling is complete Retaining wall will be wrapped up late this week or early next week. University City High School – Exterior Future work over the next several weeks: Exterior cleaning, tuck pointing, caulking and misc. repair a long with lintel replacement will continue around the structure

25 University City High School – ADA Parking Along Balson Work to date: Complete except signage

26

27 University City High School – Third Floor Science Wing Renovation Work to date: Phase 1, 2 and 3 abatement is complete. All demo will be wrapped by end of day 10-23-09 Wall framing has commenced and roughly 30% complete Plumbing rough in has commenced and roughly 30% complete HVAC Daikin cassette are in our warehouse and starting arrive on side for installation Hanging of drywall has begun along with taping University City High School – Third Floor Science Wing Renovation Future work over the next several weeks: MEP chase rough in from lower level up Installation of Daikin cassettes

28

29 Flynn Park Work to date: Foundation has been excavated, power washed, and a footing drain installed Windows have been removed and reinstalled to their new configuration and masonry infill has begun New neutral air unit is in place, wired and started Asphalt drive re-opened Perimeter drain is installed Openings are in-filled with masonry Back-fill is complete Interior windows are trimmed out Flynn Park Future work over the next several weeks: Fluid cooler repairs Tie in all downspouts

30 Brittany Woods Work to date: New neutral air units in place, wired and started Brittany Woods Future work over the next several weeks: Fluid cooler repairs

31 Jackson Park Work to date: Waterproofing and backfilling is complete

32 Current MBE/WBE Participation and Workforce: MBE participation is 16% WBE participation is 5% MBE workforce is 28% WBE workforce is 1%