Presented By Jack D. Gillum, P.E. Configuration Management Benchmarking Group Conference June 6 – 9, 2004 Kansas City, MO © 2004 CMBG Hyatt Regency Walkway.

Slides:



Advertisements
Similar presentations
PRESENTATION ON TURNKEY CONSTRUCTION.
Advertisements

Special Inspections
Process and Product Quality Assurance (PPQA)
Configuration Management
SUBMITTALS PROCESSING Fall 2008 ARCH 330
Finding Errors in Structural Designs How is it Typically Done? James Hanson, Ph.D., P.E. Rose-Hulman Institute of Technology Voted #1 Eight Consecutive.
Ensure Vendor/Engineer of Choice Product Quality
The Hyatt Regency walkway collapse
1 Engineering Ethics Seminar Richard O. Mines, Jr., Ph.D., P.E. Hodge Jenkins, Ph.D., P.E. February 2005 Mercer University School of Engineering.
Chapter 7: Key Process Areas for Level 2: Repeatable - Arvind Kabir Yateesh.
Hyatt Regency Walkway Collapse & the TV Antenna Collapse
The Kansas City Hyatt Regency Walkway Collapse “The Worst Structural Disaster In the United States”
Ron DeJuliis, Commissioner of Labor and Industry Rob McGeeney, Program Manager Larry Kreseski, Chief inspector Department of Labor, Licensing, and Regulation.
Chapter 18 Working Drawings.
Presentation to CAREGROUP Board of Directors Governing Your Networked IT Organization Ken Peffers Applicable IT Research, Inc. November 21, 2002.
PROCEDURES FOR SELECTING THE CONTRACTOR
Mike Scharfenstein CF Breakout - 12 November 2008 SLAC National Accelerator Laboratory 1 ES&H Status of Construction and Technical.
The Camp Audit “Keep your friends close and your auditor closer”
Types of Drawings University of Palestine Eng. Nagham Ali Hasan
M. Scharfenstein - ES&H Coordinator 8 June 2009
Seminar on FORENSIC STRUCTURAL ENGINEERING SUPERVISED BY: Dr. M. K. Shrimali (H.O.D.) DR. S. D. BHARTI (Associate Professor) Dept. Of Structural Engg.
2001 Winter Presentation. Site Location Site View.
CE 332 Page 1 Contract Documents. CE 332Page 2 Background The principle project objectives are to build a project within budget, on time, and according.
CVE 1000 Construction Engineering The Project Delivery System Prof. Ralph V. Locurcio, PE.
REVIEW AND QUALITY CONTROL
ARCH 330- Materials/Methods The course will cover the systems associated with construction materials methods and sequencing primarily in building construction.
CHAPTER 5 Infrastructure Components PART I. 2 ESGD5125 SEM II 2009/2010 Dr. Samy Abu Naser 2 Learning Objectives: To discuss: The need for SQA procedures.
Group # 18: Child Safety Device Group Members: Jacob Sutton, Zainab Alamri Samuel Wood, Reem Al Alshikh.
Commissioning of Fire Protection and Life Safety Systems Presented by: Charles Kilfoil Bechtel National Waste Treatment Plant Richland WA.
S oftware Q uality A ssurance Part One Reviews and Inspections.
Software Quality Assurance Activities
1 What is Precast Concrete? Precast concrete consists of a mixture of cement, water, aggregates and admixtures. This mixture is cast into a specific shape.
Configuration Management Non Government Std: EIA Standard-649 “A management process for establishing and maintaining consistency of a product’s performance,
Hyatt Regency Walkway Collapse
The Construction Phase Problem Solving Problems will Develop. How problems are managed often determines the success or failure of a project.
Code Officials and the Code Process.  To design the interior of the building in conjunction with codes, standards and federal regulations required in.
REVISED May 2009STATE MATERIALS OFFICE Goals in this Session To understand:  The Sampling & Testing process  The Project Certification process  The.
 Definition of a quality Audit  Types of audit  Qualifications of quality auditors  The audit process.
Group 1 – Ethics Presentation
Responsibility & Authority Module #2 Prepared by Dr. Randy R. Rapp July 2005.
Hyatt Regency Walkway Collapse
Project management Topic 7 Controls. What is a control? Decision making activities – Planning – Monitor progress – Compare achievement with plan – Detect.
The New Steel Erection Rule Developed by S teel E rection N egotiated R ulemaking A dvisory C ommittee (SENRAC) in 2001 Occupational Safety and Health.
Management Approaches. Construction Management Customer appoints Design team and Management team.
1 DESIGN RESPONSIBILITIES Contract Information Supplied by Design Team Responsibility of the Precaster Option I Provide complete drawings and specifications.
Code Officials and the Code Process.  Concentrates on the code process as a whole.  Different type of code officials  Various steps that are taken.
Kansas City Hyatt Regency Walkway Collapse By: Ian Thompson Stephen Conlon David Martin Laura Devane.
McDonough Bolyard Peck Educational Series Building Commissioning Presented by: Doug Wrenn Steve Baxter July
McDonough Bolyard Peck Educational Series HVAC Commissioning Presented by: Doug Wren Steve Baxter September 30, 2003.
Managing Quality with Quality Through the Construction Management Leadership Manual Presented by: Aleksandr Sergek, PE, PMP Allison Justiniano, LEED AP.
Field Office Construction, Technical Assistance and Quality Assurance NEDC Construction Inspection for Field Office Activities USDA is an equal opportunity.
Procurement of Professional Services.  Professional Services:  Architects, Engineers  Surveyors  Geotechnical engineers  Nonprofessional Services:
Group 16 Ian Bray Aodhin Mc Bride John McElwee. Background Collapsed January 18 th 1978 – 5 years after construction Large snowstorm caused heavy loading.
QUALITY ASSURANCE MODULE 3. Definitions Quality Assurance - A process/effort that ensures that processes are followed, that the processes of doing right.
SCC P2P – Collaboration Made Easy Contract Management training
The Port of New Orleans - As-Needed Consultant Selection Process for Professional Services June 9, 2016.
THE WORST STRUCTURAL DISASTER IN U.S. HISTORY
Position Statement on Sealed Truss Placement Diagrams for the State of Texas Overview Revised 3/23/2017.
Flooding Walkdown Guidance
Temporary Works Co-ordination
FIVE PROJECT PHASES 5C-3 Sun. 8:00-10:00am 21/ 2/2016.
Mastering Change Control
THE WORST STRUCTURAL DISASTER IN U.S. HISTORY
Leo Associates Services
Pathways 2017: HLC Accreditation Overview
SNC/SCANA – New Build Configuration Management
Position Statement on Sealed Truss Placement Diagrams for the 2012 or 2015 International Residential Code Overview Revised 3/23/2017.
DOE Review of the LCLS Project October 2006
HYATT REGENCY HOTEL IN KANSAS CITY COLLAPSE – A CASE STUDY
Construction Management Services April 16, 2018
Presentation transcript:

Presented By Jack D. Gillum, P.E. Configuration Management Benchmarking Group Conference June 6 – 9, 2004 Kansas City, MO © 2004 CMBG Hyatt Regency Walkway Collapse “A Personal Perspective & Insight” Presented By: Jack D. Gillum, P.E.

Two Walkways Collapsed 114 People Lost Their Life Failure of Hanger Rod Connection (4th Floor) Kansas City Hyatt July 17, 1981

OWNER: Crown Center Redevelopment Corp. DESIGN TEAM: ARCHITECTS Patty Berkebile & Nelson Herbert Duncan Monroe - Lefbvre Marshal & Brown STRUCTUAL ENGINEERS: Gillum Colaco Concordia Project Management Havens Structural Steel Eldridge & Son Construction General Testing Laboratories The Team Owner/Design & Construction Team

Entrance Hyatt General Layout

Entrance to Hotel and Atrium Kansas City Hyatt

29 N Tower Function Block 4 TH & 2 ND FLOOR BRIDGES 3 RD FLOOR BRIDGE Bridge Plan

29’ -Typical 15’-2+” 29+=120’ Atrium Roof Plan

N Guest Tower Function Block Atrium Connections Des. by Fabricator Physical description – Bridge Plan

Fast Track Project Project Engineer Leaves Project Designer Leaves QC Problems during construction SE request to perform inspection: Refused Screen Wall Changes Bridge Hanger Changes Portion of Atrium Roof Collapsed Walkway Bridge Collapsed Major Events Occurring Design Phase CHRONOLOGY OF EVENTS

CHRONOLOGY TIMELINE MID 1977 Schematic Design (750 Rms, 35 Flr, 120’ Atrium Jan 1978 Fast-Track Design/ Construct-Contract w/GC

CHRONOLOGY TIMELINE April 1978 Structural Contract “All Structural Eng. Serv.” Jan - Aug 1978 Design continues during construction SE requested owner to be retained for inspection services DENIED

29 N Guest Tower Function Block Atrium Connections Des. by Fabricator Physical description – Bridge Plan

No rod size No reaction No rod strength Design Phase – Bridge Connection Evolution

Changes During Shop Drawings Requested two rods by phone Approved by phone with caveat “submit through channels” Design Drawings v.s. Shop Drawings The shop drawings are checked by a technician who did not work on the project. Questions are raised about the strength of the rod

THIS CONNECTION WAS NEVER DRAWN NOR SUBMITTED FOR APPROVAL CONNECTION AS BUILT

Summer 1979 Erection of Steel for Atrium Contractor omits embedded inserts in Concrete for steel connection Needs to be modified by Engineer Owner (again) refuses Engineer request for field representation third time Owner fires testing lab due to poor performance during inspection of const. Chronology (Continued)

Construction Collapse / Design Checks Problems at connections along expansion joint at the interface between steel and concrete structures

Chronology (Continued) October 1979 Atrium roof collapse Deficiencies in modified construction at concrete/steel interface discovered Engineer initiates in-house check of Atrium roof Outside Peer Review Initiated & Completed

ATRIUM ROOF:STEEL TO CONCRETE CONNECTIONS Engineer Designed & Modified

Problems at the screen wall are uncovered EOR in-house check EOR issues correction details for screen wall Screen wall corrections are made in the field Problem with the bridge connection is not discovered Independent design check and field inspection does not uncover either error Construction Collapse / Design Check

* DURING THE SHOP DWGS Horizontals supporting splice points are moved for architectural reasons. The splice points on the truss drawings are not moved Design Phase – Screen Wall Changes

Chronology ( Continued ) Late-1979 to July 1980 Gen’l Contractor goes bankrupt and Crown Center takes over as contractor using personnel of Gen’l Contractor July 1980  Hotel Opened July 17, 1981  Walkway bridges collapse

Double rod connection failed Connection that failed was never shown on ANY drawings!! Engineering or Detailer Connection that failed was never designed Bridge Collapse

Video of Collapse

Why Did It Happen? Combination of :Personnel Errors A.Design Deficiencies B.Inadequate Oversight & Review Process C.Missed opportunities to discover error D.Poor Communication

Standard of Practice (During this period of time 1950’s -1980’s) Standard of Practice in the profession was for the Fabricator to design and detail all structural steel details (includes design of connections) unless detailed by the Structural Engineer Standard Originated with the fabricator’s to insure a least costly and practical connection from the fabrication viewpoint

Factors That Contributed to the Collapse Fast Track Process  Architectural design changes & conceptual re-designs  Drafting Errors  Checking errors-Shop Drawings  Invalid initial design concept of hanger Senior engineer personnel changes  Phone changes w/o follow-up by detailer or engineer in writing

Factors That Contributed to the Collapse No Structural Site Representation (Refused several times) Engineer Relied (ASSUMED) based on past projects on design of connections by Fabricator, w/no follow-up by Project Manager

Fabricators in-house engineer transferred fabricator’s partial shop dwgs to outside firm who assumed connection was designed Engineers technician, checked piece size but not connection. (Not Drawn or submitted) Outside Peer Review didn’t check shop dwg Factors (Continued)

“Design Check” questions answers not verified In-house design check questions following atrium collapse were not verified. No Follow Up Poor Testing & Inspection Factors (Continued)

Warning Signs!!! Never Transmitted to Engineer Walkway deflection of 3/4” observed by workman who notified architect’s site representative seven weeks B4 July 80 opening. No Follow Up General Contractor's attorney reported : “….from date of full dead load loading of 4th and 2nd floor bridges (July 1, 1980), box beams began to distort and distortions were visible to naked eye.”

Warning Signs!!! Never Transmitted to Engineer Handrail Deflection noted on punch list of 130 items (Aug, 1980) Feb 1981 Box Beam Deformations noticed by dry wall installer. (No one notified)

What Should Have Occurred ? Single Rod Concept detail on engrs dwg noted as conceptual only Fabricator design connection Picked up during shop dwg check as not designed After atrium collapse picked up during design re-check which should have been a thorough design document check

What Should Have Occurred ? EOR provide full time inspection Engineer Notified of warnings! Rundancy All of above

Procedures must be implemented that assure that all connections are designed by a competent professional Peer reviews and design checks should include a review of shop drawings Lessons Learned

When questions come up look at surrounding issues for related problems EOR should be retained to provide full inspection during construction of structure Owner needs on site qualified representation Lessons Learned

Design and construction is a collaborative process that requires professional integrity, judgment, and integrity on the part of all participants We have not yet clearly defined the nature of the design and construction process and the information flow that is required for success in all respects We have not learned to respect and teach the history of the profession and fully disseminate information of problems that occur Lessons Not Learned

WHAT IS THE FUNDAMENTAL ISSUE? WHO TAKES THE RESPONSIBILITY FOR ENSURING THE WHOLE OF THE PROJECT CONFORMS TO THE DESIGN INTENT AND THE SAFETY OF THE GENERAL PUBLIC ?

ALL MEMBERS OF THE DESIGN TEAM ARE RESPONSIBLE FOR WHAT THEY DO!  Take the time to check your own work!  DON’T ASSUME SOMEONE ELSE WILL! Continuing Maintenance and Inspections by OWNER ! Final Responsibility? The Engineer of Record!! Where does the buck stop?

What Has Been Done NY State Board of Regents Proposed Amendment (Adopted 6/96)  Only ancillary to main components  Clearly specified performance criteria  Performed by licensed professional  Primary Design Team must check & approve, i.e... “Each designer responsible for own work”

What Has Been Done (Cont’d.) States of Florida and Connecticut added legislation relative to checking shop drawings. (Both are different) Combined with NY, only these 3 states in 20 years have any legislation relative to who does what.

FINALLY!! ASCE: “Quality in the Constructed Project”, 2000 ( After 20 years) PP : Shop Drawings for Structural Components Conn. design by Fabricator to tailor to fabrication methods EOR has authority & responsibility for overall Design of Project Fabricator responsible for connections & details ASCE: “Quality in the Constructed Project”, 2000 (After 20 years)

FINALLY!! ASCE: “Quality in the Constructed Project”, 2000 ( After 20 years) Complex Structures (Two Approaches OK) EOR performs complete engineering design (including conn.) Fabricator provides services of PE to design or supervise design of components not completely designed in the const.doc’s. EOR responsible to Ck shop dwgs and design for either method ASCE: “Quality in the Constructed Project”, 2000 (After 20 years)

CONFIGURATION MANGEMENT Strictly Regulated Industry by Government Regulations state that design, processes, documentation, changes and records must be managed This is up to Producer/Operator

CONFIGURATION MANGEMENT As the result of design problems,worker errors and equipment malfunctions of Three Mile Island and the Salem ATWS event in 1983, CM has continued to evolve and improve following the NRC Bulletin CM, reinvented under CMII and ISO Quality Management (3 tier/8 step program) Adoption of Risk-Informed Baseline Inspection Program

Configuration Management (cont’d) Non Regulated Industry Design and Construction have many similar problems Dissemination of problems (CR”s) and solutions to include CM processes and which includes all team members is important

Configuration Management (cont’d) Cost and time is always the problem Owners are reluctant to participate and have tight budgets if any during design, construction and very little(if any) after turn-over (exception may occur with with public, state and federal ownership

In Conclusion: While our industries are different the process remains essentially the same: Management Planning Programming Designing QC/QA Construction Turn Over Operation Maintenance Continual Inspection Oversight & Follow Through Requires: Integrity,teamwork, communication & personal responsibility by all involved in the process

“Responsibility issues in construction, as in most endeavors, can be effectively resolved by adhering to the principle that responsibility and authority must be exactly linked.” Consulting Engineer, Norman Scott recently wrote: The corollary principle is that everyone must be responsible for his or her own work and decisions