Presentation is loading. Please wait.

Presentation is loading. Please wait.

Flooding Walkdown Guidance

Similar presentations


Presentation on theme: "Flooding Walkdown Guidance"— Presentation transcript:

1 Flooding Walkdown Guidance
George Attarian, Progress Energy April 6, 2012

2 Guidance based on approach to IER 11-1 walkdowns
Current Status Guidance based on approach to IER 11-1 walkdowns Draft prepared and sent to the NRC and industry on March 9 Currently being reviewed by NRC Comments discussed during March 15 and 27 webinars NRC comments on key concepts will need to be resolved

3 Guideline Content Introduction Purpose Definitions Scope Methodology
Acceptance Criteria Monitoring and Maintenance Reporting Results

4 Purpose Verify that permanent and temporary SSCs, related procedures, and associated manual actions credited in the external flooding licensing basis are in acceptable condition and capable of performing their intended function

5 Definitions Deficiency: A condition that prevents a plant flood protection feature from performing its intended function during a licensing basis flood event. This condition shall be determined by the Corrective Action Program.

6 Definitions Inaccessible areas are areas that cannot reasonably be inspected due to significant personnel safety hazard, Very High Radiation Areas, major equipment disassembly, or no reasonable means of access (e.g., buried).

7 Definitions Reasonable simulation is a walk-through of a procedure or activity to verify the procedure or activity can be executed as specified/written. Reasonable simulation may require the actual performance of these activities if there has never been a demonstration that the activity can be completed in the credited time.

8 Walkdown Team Selection and Training
Experienced personnel trained for visual inspections of plant structures, systems, and components within the walkdown scope Trained to Walkdown guidance Walkdown packages being performed Flooding related items in enclosures 2 and 4 of 50.54(f) letters Recommend 2 staff on each visual inspection team Training content described in Appendix C of guidance

9 Scope Compare current plant configuration and procedures to features in existing design and licensing basis that are credited for protection and mitigation of external floods Comparison to UFSAR, current drawings, and procedures Inspection does not include the initiators that cause the floods Inspection of upstream dams WILL NOT be required, but inspection of the flood protection features that are credited to protect against or mitigate the effects of a dam failure WILL BE required

10 Methodology General Examples are in Appendix B
Permanently installed passive SSCs Permanently installed active SSCs Temporarily installed passive SSCs Temporarily installed active SSCs Examples are in Appendix B

11 Methodology Protection features All Temporary
Assess the capability to perform the required function (visual inspection of SSC, review of operating procedures and PMs) Any observation that cannot be immediately judged as acceptable must be entered into the Corrective Action Program for disposition Temporary Verify accessibility, transportability, staging and function of necessary supplies, and feasibility of installation

12 Methodology Functional tests/PM’s All equipment
Assess appropriateness of the test Tests completed with acceptable results within their required frequency (if applicable) and at least once

13 Methodology Procedures and associated manual actions
Reasonable simulation Actions must be feasible considering conditions that may exist at the time of the flood Must consider station staffing limitations and site access concerns Staff must be trained Ensure that site warning procedures are in place

14 Acceptance Criteria Flood protection features are considered acceptable if no conditions adverse to quality were identified during walkdowns, verification activities, or program reviews as determined by the licensee’s Corrective Action Program. Conditions adverse to quality that prevent the flood protection feature from performing its credited function during a design basis external flooding event are “deficiencies” and must be reported to the NRC in the response to the 50.54(f) letter.

15 Walkdown Documentation
Walkdown record form in Appendix B Description of feature Results of Visual inspection Functional test Procedure walk through Maintenance and monitoring Conclusion Photographs should be considered for visual inspection documentation

16 Reporting Requested information in 50.54(f) letter
Additional considerations Deficiencies Schedule for inspecting features that were not inspected Reasonable assurance that flood protection function of inaccessible features will be met

17 Estimated Schedule for Guidance
Draft provided to NRC March 9 NRC meetings to discuss comments Apr 11, Apr 25 Submit final draft to NRC and industry Early May NRC endorsement Late May Utility commitment to use (90 day response) June 10

18 Other Considerations Utilities should use walkdowns to prepare for flooding hazard evaluations and Integrated Assessment Look for potential vulnerabilities and available margin Assess implications of All plant configurations Full flood duration Separate guidance will be provided


Download ppt "Flooding Walkdown Guidance"

Similar presentations


Ads by Google