Rodd Pope, SLAC Undulator System April 16-17, 2007 FAC Meeting 1 Undulator System Assembly, Installation, and Integration.

Slides:



Advertisements
Similar presentations
Jose Chan FAC- Undulator System Installation & Assembly 10/30/07 1 Undulator System Installation & Assembly Schedule Jose.
Advertisements

Zachary Wolf Undulator Tuning November 12, Undulator Tuning Status Z. Wolf, S. Anderson, R. Colon, S. Jansson, D. Jensen,
Rodd Pope, SLAC Undulator System October 12-13, 2006 FAC Meeting 1 Undulator System Assembly Plans Rodd Pope, SLAC.
Experience Report with the Alignment Diagnostic System Georg Gassner September 17 th 2010.
Richard M. Boyce FAC Review – Accelerator Installation October 29-31, Installation – Accelerator Systems Installation Planning.
FAC review, 10/27 D. Schultz 1 e-Beams System Update Injector System Installation has started. Linac System Preparing for ’06 installation. Controls System.
FAC, 10/12/06 D. Schultz 1 e-Beams Systems Update Linac Injector Undulator Production MMF commissioning ARR David Schultz.
Geoff Pile FAC Review - Undulator 12 November 2008 LCLS Undulator System Overview and Fabrication Geoff Pile.
FAC, 4/20/06 D. Schultz 1 e-Beams System Update Linac System Preparing for downtime installation. Injector System Installation has started. Undulator System.
Marion M. White Undulator System 07 April 2005 LCLSLCLSLCLSLCLS Undulator System Tests Marion M. White ANL-ASD-LCLS.
Undulator Alignment Strategy – April 20, 2006 Heinz-Dieter Nuhn, SLAC / LCLS FAC 1 Undulator Alignment Strategy Heinz-Dieter Nuhn,
Geoff Pile LCLS Fixed support IDR 12 th January 2006 LCLS Fixed Support IDR Introduction and History Are special fixed supports needed?
Zachary Wolf Undulator Tuning June 17, 2008 Undulator Tuning Status Z. Wolf, S. Anderson, R. Colon, S. Jansson, S.Kaplunenko,
LCLS Undulators October 14, 2004 Heinz-Dieter Nuhn, SLAC / SSRL MMF Review Introduction to the LCLS Undulators Heinz-Dieter Nuhn,
Jose Chan FAC - BC2/Linac Installation Status & 4/16/07 1 BC2/Linac Installation Status & Schedule Jose Chan.
Geoff Pile FAC Review - Undulator 17 June 2008 LCLS Undulator System Status and Schedule Geoff Pile.
Richard M. Boyce FAC April 16, LCLS Installation & Planning Integration process – IMT 2007 Installation Planning BTH.
David H. Dowell Injector RF Design November 3, LCLS Injector RF Gun: Design, Fabrication & Tuning Plans D. H. Dowell,
Linac Coherent Light Source Stanford Synchrotron Radiation Laboratory Stanford Linear Accelerator Center LCLS Undulator Systems.
FAC, 4/16/07 D. Schultz 1 e-Beams Systems Update People ARR Linac Installation Undulator Production MMF Operations David Schultz.
M. White – June 28, 2004 LCLS Requirements Meeting In a project, we live or die by the schedule. After we’re “baselined” it is our plan for what we will.
Marion White Magnets & Supports April 16, 2007 Undulator Magnets and Supports Status.
Richard M. Boyce FAC October 29-31, Installation Planning Integration process – IMT update Installation Planning &
Robert Ruland Installation Alignment -Magnetic Measurements – Fiducialization April 7-8, 2005 FAC Meeting 1 Installation Alignment,
D. Schultz FAC 6/17/08 1 e-Beams Systems Update People Progress the last review LTU and Dump Installation Status Undulator.
Robert Ruland MMF Introduction, Schedule, Budget October 14, 2004 MMF Review 1 MMF Introduction, Schedule, Budget Robert Ruland.
Stephen Milton Undulator System 20 April, 2006 LCLS Undulator System Update S. Milton, ANL FAC, April 20 th, 2006.
Rodd Pope, SLAC Undulator System April 20-21, 2006 FAC Meeting 1 Undulator System Assembly Plans Rodd Pope, SLAC In collaboration.
Linac Coherent Light Source Stanford Synchrotron Radiation Laboratory Stanford Linear Accelerator Center LCLS Undulator Physics.
Bob Lill LCLS FAC June 16-18, 2008 RF BPM Status and Production Test Results.
Robert Ruland Intra Girder Assembly and Alignment - October 20, 2005 Internal LCLS Undulator Alignment and Motion Review 1 Intra.
A U.S. Department of Energy Office of Science Laboratory Operated by The University of Chicago Argonne National Laboratory Office of Science U.S. Department.
XFD – XF Engineering Group November 15-th, 2004LCLS Undulator Final Design Review1 Undulator for the LCLS project – from the prototype to the full scale.
Zachary Wolf LCLS Undulator October 30, LCLS Undulator Tuning And Fiducialization Zack Wolf, Yurii Levashov, Achim.
Jose Chan FAC Review- LTU-DUMP Installation Status & 11/11/08 1 LTU-Dump Installation Status & Schedule.
Zack Wolf Undulator Magnetic April 11, 2006 LCLS Undulator Magnetic Measurements Zack Wolf, Scott Anderson, Ralph Colon,
Geoff Pile LCLS Und. System Fabrication FAC 29 th, 30 th & 31 st October 2007 LCLS Undulator System Fabrication Schedule FAC.
C.E. Rago Inj/Lin Design & 4_20_06 1 Injector / Linac Design & Fabrication C.E. Rago FAC Review 04_20_06.
Hamid Shoaee Accelerator Readiness Dec. 2, ‘08 SLAC National Accelerator Laboratory Controls Department LCLS Maintenance.
Zachary Wolf Undulator Oct 12, LCLS Undulator Tuning Zack Wolf, Yurii Levashov, Achim Weidemann, Seva Kaplounenko,
1 BROOKHAVEN SCIENCE ASSOCIATES Transition to Installation Erik Johnson ASD Deputy Director and Interface Manager NSLS-II CFAC Meeting November 9-10, 2009.
Marion M. White Undulator System 27 October FAC LCLSLCLSLCLSLCLS Progress on the Undulator Module System Test Marion M.
Procurement and Manufacture of LCLS Undulators FY 04 Activity: Complete design of Second Prototype Undulator This will include field control comb Procure.
Catherine LeCocq, SLAC Alignment Plan for the LCLS Undulator IWAA 2006,1 Alignment Plan for the LCLS Undulator Catherine.
October 27-28, 2005 FAC Meeting Undulator Metrology Catherine LeCocq, SLAC 1 Undulator Metrology Catherine LeCocq, SLAC October.
Collaborating for Quality Quality Assurance (QA) & Quality Control (QC) in the Accelerator Project (ACCSYS) Matthew Conlon ACCSYS QA/QC
Clive Field, Reggie Rogers, Venkat Srinivasan Undulator Week: BFW Card Status Update 01/23/ BFW Card - Physics Requirements.
Cryogenic Plant Controls – Cost and Schedule
Magnetic Measurements For The LCLS Undulator System
LTU/Undulator Installation Status
Linac Coherent Light Source Procurement
Undulator Scope, Management, and Organization
e-Beams Systems Update
Electron Beam Systems ETC and Methodology
Undulator Cost & Schedule Patric Den Hartog, ANL April 24, 2002
Undulator Tuning Status Heinz-Dieter Nuhn, SLAC / LCLS for Zack Wolf, Yurii Levashov, Achim Weidemann, Seva Kaplounenko, Scott Jansson, Ralph Colon, Dave.
LCLS Undulator System Status and Schedule
LCLS Undulator System Production Management
E-Beams Systems Manager
LTU/Undulator Installation Status
LCLS Undulator System Status and Schedule
Undulator Long-Lead Procurement Preparation
Undulator Integration Test Status
Undulator Assembly and Installation Planning
LCLS e- Beams System Overview
Undulator and Magnet Production Status 25 October 2006
Undulator Alignment Plan
Alignment Diagnostic System Status
Undulator Systems Integration
LCLS Undulator Magnetic Measurements
Presentation transcript:

Rodd Pope, SLAC Undulator System April 16-17, 2007 FAC Meeting 1 Undulator System Assembly, Installation, and Integration Rodd Pope, SLAC

Undulator System April 16-17, 2007 FAC Meeting 2 Past Six Months (1 of 4) Production Control Communication 10/06 - Geoff Pile is developing a tool. 4/07 - Tool is developed. 4/07 - Accessed successfully 4/12. 4/07 - Must be fully populated with data and maintained to add value. 10/06 - Release document transfer process is in place. 4/07 - Transfer of large assemblies plus drawings becoming more difficult but still more than worth the effort. 4/07 - Access to ANL ICMS successful on 4/11. 4/07 - SLAC has the ability to “PULL” released engineering drawings, Pro-E models, and STEP translations on-demand – FANTASTIC! 10/06 - Exact Statement of Work content will solidify scope of SLAC work. 4/07 - Undulator, Quadrupole, and Support Mover SOWs release to SLAC 4/07 - Vacuum Chamber Support SOW draft to SLAC 4/07 - Others not to SLAC. This has retarded the assembly and installation planning.

Rodd Pope, SLAC Undulator System April 16-17, 2007 FAC Meeting 3 Past Six Months (2 of 4) 10/06 - WPM mockup operational in B750. 4/07 – Mockup built, operated, data recorded and analyzed, de- commissioned. 10/06 - Material handling equipment in place. 4/07 – Undulator cart refused by MMF. To be used by the assembly and installation group. MMF to produce their own handling cart. 10/ % of Undulators RFI. 4/07 – 0% RFI. 2 of 33 measured and ready for shimming. Technical issues with the shimming hardware design to be resolved with ANL support. 10/06 - Component deliveries beginning. 4/07 – All mu-metal shields and housing feet are at SLAC. 20 of 33 undulators and a portion of the undulator shims are at SLAC.

Rodd Pope, SLAC Undulator System April 16-17, 2007 FAC Meeting 4 Past Six Months (3 of 4) 10/06 - HLS/WPM Final Design Review – 1/07 4/07 – Completed March 23, /06 - HLS/WPM Procurements Placed 4/07 – HLS sensors ordered. Delivery starts June /07 – Vendor qualification for WPM sensors April /07 – Balance of mechanical hardware RFQ by July /06 - Girder Assembly and Component Fiducialization 10/06 - Plan complete 4/07 – Preliminary plan review scheduled for 4/23 10/06 - Tooling designed and ordered 4/07 – Preliminary designs to be reviewed with the plan on 4/23

Rodd Pope, SLAC Undulator System April 16-17, 2007 FAC Meeting 5 Past Six Months (4 of 4) 10/06 - Production Drawings and SOW’s archived at SLAC 4/ of ? Drawings archived at SLAC 4/ of ? SOW’s archived at SLAC 10/06 - Cable Plant Preliminary Design Review Complete – Long Lead Procurement Placed 4/07 – PDR now 6/07, FDR now 10/07, Installation 3/08 10/06 - Pedestal installation Statement of Work out for bid 4/07 – Per the integrated “2008 Installation” schedule, SOW RFQ is 8/07

Rodd Pope, SLAC Undulator System April 16-17, 2007 FAC Meeting 6 Next Six Months (1 of 4) Deliveries through September 2007 Assembly will not start until Vacuum Chambers and RF BPMs have arrived (November 2007).

Rodd Pope, SLAC Undulator System April 16-17, 2007 FAC Meeting 7 Next Six Months (2 of 4) HLS/WPM Sensors and Mechanical Hardware Delivered HLS/WPM Electronics on Order 20 of 33 of Undulators RFI 11 of 33 Quadrupoles RFI

Rodd Pope, SLAC Undulator System April 16-17, 2007 FAC Meeting 8 Next Six Months (3 of 4) Cable Plant PDR 6/07, FDR 10/07, Installation 3/08 Award Davis-Bacon Contracts: Core drilling contract award 9/07 Pedestal installation contract award 9/07 Install Cable Plant contract award 12/07 Girder installation contract award 12/07

Rodd Pope, SLAC Undulator System April 16-17, 2007 FAC Meeting 9 Next Six Months (4 of 4) Production Control Communication As the SOW’s are released, archive online at SLAC. Use the ASK system to track procurements, deliveries, and transfer of design ownership. Pull released drawings from ANL into SLAC archive. Incorporate information into assembly and installation documentation.

Rodd Pope, SLAC Undulator System April 16-17, 2007 FAC Meeting 10 Schedule

Rodd Pope, SLAC Undulator System April 16-17, 2007 FAC Meeting 11 Component Delivery Schedule Actual Plan

Rodd Pope, SLAC Undulator System April 16-17, 2007 FAC Meeting 12 Assembly Delayed start until November 2007 due to component deliveries Impacted by the Continuing Resolution Fixed Support, Support Mover, Girder, and Translational Stage assembled and delivered in a 3 sub-assembly kit: 3-Cam Pedestal, 2-Cam Pedestal, Girder SLAC to perform QC and modify as necessary

Rodd Pope, SLAC Undulator System April 16-17, 2007 FAC Meeting 13 Installation Member of Integration Management Team Member of Installation Management Team Coordinating Davis-Bacon contracts project wide Core drilling, pedestal install, cable plant, girder install Risks include girder assembly, project wide coordination of access and resources

Rodd Pope, SLAC Undulator System April 16-17, 2007 FAC Meeting 14 Integration Communication More complicated through Continuing Resolution, challenging before. Technical data beyond drawings is limited. Focus has been getting the procurements on the street. Quality Issues Drawing errors, lack of QC data, communication of QC data that is available. Example: The oversized outer diameter of the undulator strongback was known since the strongbacks were machined. But the information was not forwarded and the impact of the deviation was not thoroughly analyzed. This deviation caused the ANL mu-metal shields not to fit, the SLAC kinematic mounts not to fit, and the ANL support feet not to fit.)

Rodd Pope, SLAC Undulator System April 16-17, 2007 FAC Meeting 15 End of Presentation

Rodd Pope, SLAC Undulator System April 16-17, 2007 FAC Meeting 16 Component Delivery Schedule

Rodd Pope, SLAC Undulator System April 16-17, 2007 FAC Meeting 17 Undulator Assembly, Installation & Maintenance (U-AIM) Ben Poling, S&E Associate Ed Akerstrom, Principle Technician Nicolas Horton, Senior Technician TBH – When? Responsibilities include: Material handling, assembly, installation planning and execution Assembly and QA documentation Space and personnel resource planning

Rodd Pope, SLAC Undulator System April 16-17, 2007 FAC Meeting 18 Assembly, Install, & Storage Space B750 – Storage/Assembly B081 – MMF Tuning/Fiducialization Undulator Tunnel

Rodd Pope, SLAC Undulator System April 16-17, 2007 FAC Meeting 19 SLAC Magnetic Measurement Facility Wolf, Zachary, LCLS Management Presentation, April 11, 2006, Slide 3 Floor plan divided into three functional areas Magnetic Measurements (± 0.1º C) Fiducialization and Assembly (± 1º C) Storage (± 2.5º C) Quadrupole Fiducialization CMM Shared Area: Magnetic Measurements/Cam Calibration LCLS-TN-04-1

Rodd Pope, SLAC Undulator System April 16-17, 2007 FAC Meeting 20 Girder Assembly Flow

Rodd Pope, SLAC Undulator System April 16-17, 2007 FAC Meeting 21 Undulator System Girder Assembly Field Installation Precise/Vacuum Assembly performed in a control environment

Rodd Pope, SLAC Undulator System April 16-17, 2007 FAC Meeting 22 Process Travelers Traveler Drafts Out For Review Undulator Tuning & Fiducialization Girder Assembly BFW Fiducialization Quadrupole Measurement & Fiducialization Pedestal Assembly CAM Assembly Inventory Database Physical location tracking Quality Assurance data collection Installation location mapping

Rodd Pope, SLAC Undulator System April 16-17, 2007 FAC Meeting 23 SHORT BREAK By Scott Doran, ANL

Rodd Pope, SLAC Undulator System April 16-17, 2007 FAC Meeting 24 SHORT BREAK CROSS SECTIONS By Scott Doran, ANL

Rodd Pope, SLAC Undulator System April 16-17, 2007 FAC Meeting 25 LONG BREAK By Scott Doran, ANL

Rodd Pope, SLAC Undulator System April 16-17, 2007 FAC Meeting 26 LONG BREAK CROSS SECTIONS By Scott Doran, ANL

Rodd Pope, SLAC Undulator System April 16-17, 2007 FAC Meeting 27 Girder Assembly Prerequisite All necessary components fiducialized Stands aligned in all staging areas Outside MMF (possibly in Building 750) following the SPEAR3 Approach as suggested by Richard M. Boyce Step 1 Prepare Girder: Mount CAM wedges under girder Step 2 Component Installation, part 1 roll-away slides, component supports HLS & WPM components undulator vacuum chamber Step 3 Component Installation, part 2 quadrupole, BFW and BPM Step 4 Wiring / Plumbing In the Controlled Environment of the MMF Step 1 Optical Alignment Step 2 CMM Storage LeCocq, Catherine, October 27-28, 2005, FAC Meeting, Slide 13

Rodd Pope, SLAC Undulator System April 16-17, 2007 FAC Meeting 28 UNDULATOR CELL ASSEMBLY NEXT CELL UNDULATOR SHOWN FOR CLARITY By Scott Doran, ANL

Rodd Pope, SLAC Undulator System April 16-17, 2007 FAC Meeting 29 UNDULATOR CELL ASSEMBLY NEXT CELL UNDULATOR SHOWN FOR CLARITY By Scott Doran, ANL