Edward Downer Elementary School Playfield Renovation Status Update 06/10/14
Construction Manager:Gabriel Fortich (SGI) Project Engineer:Shawn Fitzgibbons (SGI) Inspector of Record:Man Wah Cheng Architect of Record:Rod Sepulvida (BCA Architects) General Contractor: Maggiora & Ghilotti, Inc.
DEMOLITION OF EXISTING ASPHALT PAVING AND MISCELLANEOUS ITEMS TO BUILD A NEW GRASS FIELD INCLUDING ROUGH AND FINISH SITE GRADING, IRRIGATION, PLANTING, AND FIELD DRAINAGE. ELECTRICAL SCOPE CONSISTING OF POWER AND DATA CONNECTION TO NEW IRRIGATION CONTROLLER AND PROVISION OF CONDUIT AND FULL BOXES FOR FUTURE LOW VOLTAGE SYSTEMS.
Project Duration:180 (Calendar Days) Notice To Proceed Date: May 19, 2014 Completion Date:Nov 15, 2014 Percent Complete: 18% Base Contract Amount:$563,226.00
Site Demolition
Clear and Grubbing
Utility Trenching
Electrical and Signal Conduit
Sub-Grade Preparation