Lafayette New Terminal Program Update

Similar presentations


Presentation on theme: "Lafayette New Terminal Program Update"— Presentation transcript:

1

2 Lafayette New Terminal Program Update
February 13, 2019

3 Terminal Program Update
FAA On site FAA Resident Inspector Currently managing grants LA DOTD Terminal Program Update

4 Terminal Program Update
LA FP&C Received Cooperative Agreement for FP&C contribution to QTA Coordinating with FP&C to confirm bid process and eligible items for terminal contribution 2019 Capital Outlay Application submitted Applying for $7 million towards terminal construction to be available next Fall EDA Grant Application Revised EDA grant application submitted. Awaiting date for Decision Committee TSA OTA Application Submitted Grant Application, Waiting on Feedback Terminal Program Update

5 Terminal Program Update
Airlines Working with Airlines to discuss leasable space and an agreement to buildout space in New Terminal QTA \ Ready Return Continued to meet with Rental Car Companies, moving forward on QTA Lease Rates Working with FP&C on approvals for NTP Concessions

6 Terminal Program Update
Enabling Demo Demolition - Complete AOA fencing and gates – Complete Fill Material and Asphalt – Complete Seeding/Sod – Complete Substantially Complete Reviewing completion paperwork and waiting on 45-day lien-free period Final Acceptance - upcoming Terminal Program Update

7 Terminal Program Update
Rental Car Quick Turn Around Facility Timeline: Oct. 2018: Commission Approved Updated CFC Nov. 2018: Construction Bids Due Dec. 2018: Approved Bids Jan. 2019: FP&C Construction Concurrence Feb. 2019: Award Contract Apr. 2019: NTP Feb. 2020: Construction Complete Terminal Program Update

8 Terminal Program Update
GMP 1: Approved 9/25/18, Notice to Proceed 11/12/18 Terminal Program Update Description Est. Start Sub. Comp. Project 1 - RTR Cable Relocation Nov. 2018 Mar. 2019 Project 2 – RTR Facility Jun. 2019 Project 3 – Terminal Foundations Jan. 2019 Jul. 2019 Project 5 – Enabling Parking GMP 2: Approved 1/15/19, Notice to Proceed 1/15/19 Description Est. Start Sub. Comp. Terminal Structural Steel, Elev. and Escalators Jan. 2019 Nov. 2019 GMP 3: Terminal Building Shell, MEP and Finishes 100% Design to complete in Feb. 2019 Bidding in Feb./ Mar. 2019 Approval by LAC May 2019

9 GMP1 – Project 1 New Terminal Construction Update
Project 1 – RTR Cable Relocation Manholes 1 through 4 set and backfilled. Cable wire pulled, spliced, and the FAA will cutover to the new RTR cable this week GMP1 – Project 1

10 GMP 1 – Project 2 RTR Facility
New Terminal Construction Update Project 2 – RTR Facility Slab pour - complete Duct banks for the RTR cable from the building to tower – ongoing GMP 1 – Project 2 RTR Facility

11 GMP 1 – Project 2 RTR Facility
New Terminal Construction Update Project 2 – RTR Facility CMU installation – ongoing Truss/framing installation – upcoming GMP 1 – Project 2 RTR Facility

12 GMP 1 – Project 5 Enabling Parking
New Terminal Construction Update Project 5 – Enabling Parking Storm drainage installation – complete Underground electrical rough in – complete Economy lot – site grading and compaction – ongoing Short-term parking lot re-striping – ongoing GMP 1 – Project 5 Enabling Parking

13