Merritt College Proposed New Science Complex PCCD Board of Trustee Meeting May 20, 2008 Presented By Dr. Sadiq B. Ikharo, Vice Chancellor Department of.

Similar presentations


Presentation on theme: "Merritt College Proposed New Science Complex PCCD Board of Trustee Meeting May 20, 2008 Presented By Dr. Sadiq B. Ikharo, Vice Chancellor Department of."— Presentation transcript:

1 Merritt College Proposed New Science Complex PCCD Board of Trustee Meeting May 20, 2008 Presented By Dr. Sadiq B. Ikharo, Vice Chancellor Department of General Services

2 2 Project History The growing demand and expanding science and allied health programs at Merritt College has created a great need to build the District’s largest classroom building (Building D) that would total 80,000 square feet.  Under Measure E, $5,747,150 was allocated for the initial planning and design to renovate Building D at 50,000 square feet.  Although the project is still in the planning and design process, early investigations indicate that the building’s utilities, functionality, and the usefulness of the fixtures, furniture and equipment surpassed its usefulness.  An additional $39,365,000 was from Measure A was allocated to the project budget for a total of $45,112,150. This amounts reflects the project construction cost of $31,578,505 and projected soft cost of $13,533,645.  Further analysis suggest that the option of a new “state of the art” science building at $45.1 million is more financially prudent when you consider the building life cycle analysis.  The District is required to bring the existing building up to code (seismic retrofit) by DSA (50% rule), if the cost of renovation is more than 50% of the value of the building. 2

3 3 Merritt College-Building “D” Development Alternative Schemes Option 1: Two-Phase Renovation of Existing Building 2PR) $39M Option 2: Full Renovation of Existing Building (FR) $44M Option 3: New Building (NB) $45M 50 M 45 M 40 M 35 M 30 M 25 M 20 M 15 M 10 M 2PR FR NB Cost in Million Dollar Construction Costs

4 4  Advantages: Preliminary and development design plans 90% completed. Soil sampling and testing 100% complete. Existing spaces available  Issues: Telephone and data systems need upgrades. Space constraints restricting full program development Restricted storage. Costly augmentation to structural, mechanical, and electrical systems. Potential change orders for unforeseen conditions. LEED Certification may not be possible. Disruption of instruction for moving and during construction. Timeline for relocation and swing space construction. Specialized costly swing space that would require augmentation for any future use. Additional 4000 sq. ft needed for new programs such as Tissue Culture, Genomics, Microscopy, Diet Nutrition, and DNA Analysis.  Next Steps: Coordinate with Peralta CCD and Merritt College representatives to expedite decision to abandon the old D building. Option 1: Two-Phase Renovation of Existing Building (2PR)

5 5 Cost Summary for Option 1: Two-Phase Renovation of Existing Building (2PR Item No. Description 2-Phase Renovation of Existing Building 1 Architectural/Engineering design (consultation services) Including Hazardous Material Consultants and Miscellaneous 2.8 M $ 2 Construction Management Construction/Project Manager, Inspection, and Testing and Inspection 1.55 M $ 3 Temporary Facilities/Relocation (Miscellaneous Project Cost) Transitional Housing (set-up), Transitional Housing (Lease@28months), Moving, Storage, and Maintenance & Operation 7.0 M $ 4 Construction Demolition if applicable, Site Contractor (Site Preparation), General Contractor, Other Prime Contractor (Portables), Low Voltage Wiring Contractor, and Change Orders# 23.5 M $ 5 Procurement (Equipment & Furniture) 1.5 M $ 6 Owners Miscellaneous 0.3 M $ 7 Contingencies Construction Contingency, Other Project Contingencies, and Miscellaneous. 2.35 M $ Total 39.0 M $ $ 23.5 M $ 2.8 M $ 2.35 M $ 1.55 M $ 0.3 M

6 6 Swing Space Cost For Two Phase Renovation TOTALS UNIT COST /s.f.total s.f. TOTAL RENTAL DURATION (MONTHS) SIZE OF EACH UNIT QUANTITY SCOPE scenario 1: existing building renovation in two phases $ 1,872,000 $ 130.00144003236 x 4010 science lab portables to replace 10 existing $ 1,000,000 $ 100,000.00 32 10premium cost per lab $ 873,600 $ 130.0067203224 X40 7 standard classroom portables to replace 14 $ 74,880 $ 130.005763212 X 242cadaver and dry storage $ 748,800 $ 130.0057603212 X 401212 portables housing 24 offices $ 74,880 $ 130.005763212 X 2422 men and women restrooms $ 4,644,160 28032 Portable Subtotal Cost $ 1,200,000 Site and Utilities Work $ 450,000 Moves (4) $ 753,248 Soft Cost $ 7,047,408 Estimates Total

7 7  Advantages: Preliminary and development design plans 90% completed. Soil sampling and testing 100% complete. Existing building space available for renovation. Design phase nearly complete. Ready to move to construction drawings. Space reassignment and usage will benefit capacity load ratios.  Issues: Telephone and data systems need upgrade. Space constraints restricting full program development Restricted storage. Costly augmentation to structural, mechanical, and electrical systems. Potential change orders for unforeseen conditions. LEED Certification may not be possible. Disruption of instruction for moving and during construction. Timeline for relocation and swing space construction. Specialized costly swing space that would require augmentation for any future use. Additional 4000 sq. ft needed for new programs such as Tissue Culture, Genomics, Microscopy, Diet Nutrition, and DNA Analysis.  Next Steps: Coordinate with Peralta CCD and Merritt College representatives to expedite decision to abandon the old D building. Option 2: Full Renovation of Existing Building (FR)

8 8 Item No. Description Full Renovatio n of Existing Building 1 Architectural/Engineering design (consultation services) Including Hazardous Material Consultants and Miscellaneous 2.8 M $ 2 Construction Management Construction/Project Manager, Inspection, and Testing and Inspection 1.55 M $ 3 Construction Demolition if applicable, Site Contractor (Site Preparation), General Contractor, Other Prime Contractor (Portables), Low Voltage Wiring Contractor, and Change Orders# 23.5 M $ 4 Procurement (Equipment & Furniture) 1.5 M $ 5 Owners Miscellaneous 0.3 M $ 6 Contingencies Construction Contingency, Other Project Contingencies, and Miscellaneous 2.35 M $ 7 Temporary Facilities/Relocation (Miscellaneous Project Cost) Transitional Housing (set-up), Transitional Housing (Lease@28months), Moving, Storage, and Maintenance & Operation. $ 12 M Total 44.0 M $ Cost Summary for Option 2: Full Renovation of Existing Building (FR) $ 23.5 M $ 2.8 M $ 2.35 M $ 1.55 M $ 0.3 M

9 9 Swing Space Cost For Full Building Renovation TOTALSUNIT COST /s.f.Total s.f. TOTAL RENTAL DURATION (MONTHS) SIZE OF EACH UNIT QUANTITY SCOPE scenario 2: existing building renovation in single phase $ 2,684,880 $ 124.30216002436 x 4015 science lab portables to replace 15 existing $ 1,500,000 $ 100,000.00 24 15premium cost per lab $ 2,028,576 $ 124.30163202424 X40 17 standard classroom portables to replace 34 $ 71,597 $ 124.305762412 X 242cadaver and dry storage $ 715,968 $ 124.3057602412 X 401212 portables housing 24 offices $ 71,597 $ 124.305762412 X 2422 men and women restrooms $ 7,072,618 44832 Portable Subtotal Cost $ 1,800,000 Site and Utilities Work $ 350,000 Moves (2) $ 1,861,785 Soft Cost $ 11,084,403 Estimates Total

10 10  Advantages: Preliminary and development design plans 90% completed. Soil sampling and testing 100% complete. Space assignment and usage will benefit capacity load ratios. Relocation of Learning Center provides space during construction for new programs such as Tissue Culture, Genomics, and Microscopy. State of the art building-smart classroom and laboratories without constrains from the building. New Space assignment and usage will benefit capacity load ratios. New programs provided with adequate space – Existing building serves as swing space. New building would be LEED Certified. Diminishes cost for change order for the unforeseen conditions.  Issues: High cost to upgrade existing HVAC telecom and electrical and plumping system. Telephone and data systems need upgrade. Potential to generate costly change orders. Need for swing space. Extended projected time starting with new design. Development of new Site location and infrastructure.  Next Steps: Coordinate with Peralta CCD and Merritt College representatives to expedite decision to abandon the old D building. Option 3: New Building ( NB)

11 11 Cost Summary for Option 3: New Building (NB) Item No. Description New Building 1 Architectural/Engineering design (consultation services) Including Hazardous Material Consultants and Miscellaneous 3.2 M $ 2 Construction Management Construction/Project Manager, Inspection, and Testing and Inspection 2.4 M $ 3 Site Work (acquisition and special studies) Including toxic, geotechnical, topological survey and SEQA 0.9 M $ 4 Construction Demolition if applicable, Site Contractor (Site Preparation), General Contractor, Other Prime Contractor (Portables), Low Voltage Wiring Contractor, and Change Orders# 30.0 M $ 5 Procurement (Equipment & Furniture) 4.0 M $ 6 Owners Miscellaneous 0.5 M $ 7 Contingencies Construction Contingency, Other Project Contingencies, and Miscellaneous. 4.0 M $ Total 45.0 M $ $ 30.0 M $ 3.2 M $ 2.4 M $ 4.0 M $ 0.9 M $ 0.5 M

12 12 Item Description 1. Existing Building Half Renovated 2. Existing Building Full Renovated 3. New Building (NB) 1 Site Work (acquisition cost and special studies ) Including toxic, geotechnical, topological survey and SEQA) 900,000.00$ 2 Architectural/Engineering design (consultation services) Including Hazardous Material Consultants and Miscellaneous 2,800,000.00$ 3,200,000.00$ 3 Project / Construction Management PM/CM Construction/Project Manager, Inspection, and Testing and Inspection 1,550,000.00$ 2,400,000.00$ 4 Construction Demolition if applicable, Site Contractor (Site Preparation), General Contractor, Other Prime Contractor (Portables), Low Voltage Wiring Contractor, and Change Orders# 23,500,000.00$ 30,000,000.00$ 5 Procurement (Equipment & Furniture) 1,500,000.00$ 4,000,000.00$ 6 Close-out 7 Owners Miscellaneous 300,000.00$ 500,000.00 $ 8 Contingencies Construction Contingency, Other Project Contingencies, and Miscellaneous. 2,350,000.00 $ 4,000,000.00 $ Board Approved Total 32,000,000.00 $ Temporary Facilities/Relocation (Miscellaneous Project Cost) Transitional Housing(set-Up), Transitional Housing (Lease@28months), Moving, Storage, and Maintenance & Operatio n,000,000.007, $ $12,000,000.00 Total Estimate Project Cost $39,000,000.00$44,000,000.00$45,000,000.00 Building D - Development Alternative Schemes

13 13 Scoping Completed Design Completed Construction DrawingsDSA/BIDConstruction Close-Out 1 Month5 Month9 Month8 Month32 Month4 Month Total Remaining Months51 Months Timeline Comparison for Proposed Options Scoping Complete Design Completed Construction Drawings DSA/BIDConstructionClose-Out 1 Month5 Month9 Month8 Month24 Month4 Month Total Remaining Months43 Months Re-ScopingDesign Construction Drawings DSA/BIDConstructionClose-Out 1 Month5 Month11 Month8 Month24 Month4 Month Total Remaining Months53 Months Option 2: Full Renovation of Existing Building (FR) Option 1: Two-Phase Renovation of Existing Building (2PR) Option 3: New Building ( NB)

14 14 Additional Issues To Address With Construction Of New Science Building 1.Use for existing Building D  House new and expanding educational programs  Contract Ed 2. Cost to for minor repairs the existing Building D - $ 500,000 3. How to address the District’s “Overbuilt“ state status  New and expanding educational programs  Contract Ed  Emeritus College  Remove space from District space inventory and change the building to “Offline” status.  Schedule future maintenance will be contingence on revenues realized from usage.


Download ppt "Merritt College Proposed New Science Complex PCCD Board of Trustee Meeting May 20, 2008 Presented By Dr. Sadiq B. Ikharo, Vice Chancellor Department of."