Filter Rehabilitation and Seismic Upgrades – Construction Update

Similar presentations


Presentation on theme: "Filter Rehabilitation and Seismic Upgrades – Construction Update"— Presentation transcript:

1 Filter Rehabilitation and Seismic Upgrades – Construction Update
Formed in 1912 District Operated for 46 years without any treatment plants. Changing regulations, increases in water demand resulted in the need to operate the reservoir system that required treatment plants. Today our treatment plants are the engine of our water system and we cannot operate without them. MESSAGE – Treatment plants are essential to supply of drinking water. District Operations Committee Presentation December 16, 2016

2 Overview of Construction Status
Work progress Schedule Project administration QA/QC results Submittal status Weather delays Costs Anticipated work

3 Work Progress - Mobilization
Construction Start November 12, 2016 Trailer moved on-site SGTP Filters 1-3 drained

4 Work Progress – Demolition
Filter media removed Underdrains removed Grout and wall coatings removed

5 Work In-Progress Drilling dowel holes Rebar fabrication
Complete in wall air piping Electrical conduit

6 Schedule Notice to Proceed – Nov 10, 2016
Base Contract Duration 425 Days Original Completion Date – Dec 3, 2017 Time Extension Authorized – None Weather Days Expended – 3 Time Expended – 23 Days Percent Time Expended – 5.4%

7 Project Administration
QA/QC Filter Media Testing Sand Effective size = 0.52mm Specific Gravity = 2.67 Uniformity Coefficient = 1.33 Anthracite Effective size = 1.04mm Specific Gravity = 1.7 Uniformity Coefficient = 1.31 Shotcrete Test Panels – Tuesday Dec 20

8 Project Administration
Submittals Received 31 Reviewed and returned 23 Pending 8 RFIs Received 13 Returned 11 Pending 2

9 Project Management Team
Title Role Expense To Date Valentine Contractor $202,908.00 MWH Engineer $16,136.00 MMWD Construction Manager $25,676.79 Total $244,720.79

10 Anticipated Work for January 2017
Complete walls in filters 1-3 Install air manifold piping Place rebar cage Shotcrete walls Install Underdrains Test fit blocks to air manifold Place grout, install and anchor blocks Pass manufacturer inspection

11 Projected Progress Actual progress

12 Questions?