Injector/BC1 Commissioning (Jan through Aug. 2007) P. Emma, et al

Slides:



Advertisements
Similar presentations
Joe Frisch LCLS FAC Oct. 30, Linac/BC2 Commissioning (Dec through Sep., 2008) J. Frisch, et al. LCLS FAC Meeting.
Advertisements

Paul Emma LCLS FAC April 16, Initial Experience with Injector Commissioning P. Emma, et al. Facilities Advisory Committee.
P. Emma, SLACLCLS Commissioning – Sep. 22, 2004 Linac Commissioning P. Emma LCLS Commissioning Workshop, SLAC Sep , 2004 LCLS.
Hamid Shoaee High Level Physics 20 April 2006 High Level Physics Applications Update on Plans, New Directions Fairley,
P. Emma, SLACLCLS FAC Meeting - April 29, 2004 Linac Physics, Diagnostics, and Commissioning Strategy P. Emma LCLS FAC Meeting April 29, 2004 LCLS.
Eric Bong LCLS FAC Injector-Linac October 27, 2005 Injector Design / Diagnostics / Gun & Linac RF Design E. Bong LCLS FAC.
Paul Emma LCLS Commissioning Status Nov. 11, 2008 SLAC National Accelerator Laboratory 1 LCLS Commissioning Status P. Emma for The.
FAC, 4/16/07 D. Schultz 1 e-Beams Systems Update People ARR Linac Installation Undulator Production MMF Operations David Schultz.
James Welch October 29, 2007 Injector Commissioning Injector Commissioning Results presentated to the Facilities Advisory Committee,
LCLS Linac System Management Linac Coherent Light Source Stanford Synchrotron Radiation Laboratory Stanford Linear Accelerator Center.
E. Bong, SLACLCLS FAC Meeting - April 29, 2004 Linac Overview E. Bong LCLS FAC Meeting April 29, 2004 LCLS.
David H. Dowell Injector April 29-30, 2004 LCLS Injector Overview D. H. Dowell, SLAC FAC Review April 29-30, 2004 Injector.
Hamid Shoaee LCLS FAC Review – October Control System Overview Hamid Shoaee Controls System Manager Injector control system commissioning & Support.
Paul Emma Injector/BC1 Commissioning April 20, Injector/BC1 Commissioning (Dec. 1, ’06 through Aug. 1, ‘07) P. Emma LCLS.
Cecile Limborg-Deprey Injector Commissioning September Injector Commissioning Plans C.Limborg-Deprey Gun exit measurements.
Henrik Loos High Level 17 June 2008 High Level Physics Applications for LCLS Commissioning Henrik Loos.
David H. Dowell Injector Physics/Diagnostics/Gun&L0 RF April 29-30, 2004 Injector Physics / Diagnostics / Gun & L0 Linac.
Hamid Shoaee LCLS Control April 20, 2006 LCLS Control System Controls Organization Overview A Progress Report Hamid Shoaee.
Injector Accelerator Readiness Review, 10/31/06 Henrik Loos 1 Beam Losses During LCLS Injector Phase-1 Operation Scope of phase 1 operation Operating modes.
LCLS Accelerator SLAC linac tunnel research yard Linac-0 L =6 m Linac-1 L  9 m  rf   25° Linac-2 L  330 m  rf   41° Linac-3 L  550 m  rf  0°
Injector Accelerator Readiness Review, 10/31/06 D. Schultz 1 Readiness of Commissioning Procedures Personnel & Hardware David Schultz LCLS e - -beams Systems.
LCLS Control Group FAC – 06 Installation October 27/28, Plans for 2006 Installation October 27, 2005 Installation.
PAL-XFEL Commissioning Plan ver. 1.1, August 2015 PAL-XFEL Beam Dynamics Group.
Multi-bunch Operation for LCLS, LCLS_II, LCLS_2025
Thermal emittance measurement Gun Spectrometer
Injector Performance Requirements Conventional Facilities Update
Revised Commissioning Strategy
BC2 Commissioning Parameters
LCLS Linac Update Brief Overview L1 & BC1 Progress LTU & E-Dump Status Continuing Resolution Impact.
Injector –Linac Status & Schedule E. Bong LCLS FAC October 12, 2006
LCLS Gun Commissioning Status & Plans David H
LCLS Commissioning Parameters
LCLS Commissioning Parameters
Electron Source Configuration
Commissioning Status of the LCLS Accelerator and Undulator Systems
Injector/BC1 Commissioning (Jan. 2, 2007 through Aug. 31, 2007) P
LCLS Injector Commissioning Dates ( )
LCLS Commissioning Parameters
Injector Commissioning C
Linac/BC1 Commissioning P
Electron Beam Systems ETC and Methodology
Injector / Linac Installation Current Status
LCLS Linac Overview E. Bong Lehman Review August 10, 2004
Linac (WBS 1.2.2) Vinod Bharadwaj April 23, 2002
LCLS Commissioning P. Emma, et al
Overview Pre-Beam Checkouts
LCLS Tracking Studies CSR micro-bunching in compressors
High Level Physics Applications for LCLS Commissioning
LCLS Commissioning: Results & Plans P
INJECTOR (WBS 1.2.1) Jym Clendenin, SLAC April 23, 2002
Linac Physics, Diagnostics, and Commissioning Strategy P
Electron Beam Systems Wrap-up
Maximum Credible Beam Event Paul Emma et al
LCLS Injector/Diagnostics David H. Dowell, SLAC April 24, 2002
Diagnostics RF and Feedback
Linac Diagnostics Commissioning Experience
LCLS Injector Commissioning P
Control System Overview Hamid Shoaee LCLS Control System Manager
LCLS Global Controls Overview August 10, 2004
LCLS Commissioning Parameters
Diagnostics overview Beam profile monitors Cherenkov radiators Summary
Injector Diagnostics Status
P. Emma, for the LCLS Commissioning Team LCLS DOE Review May 14, 2009
Linac Design Update P. Emma LCLS DOE Review May 11, 2005 LCLS.
Injector/Linac Design Status C. E
LCLS e- Beams System Overview
Injector Physics C.Limborg-Deprey Feb.8th 2006
Physics Update P. Emma FAC Meeting October 27, 2005 LCLS.
LCLS e- Beams Systems Manager
Control System Overview Hamid Shoaee LCLS Control System Manager
Presentation transcript:

Injector/BC1 Commissioning (Jan. 2006 through Aug. 2007) P. Emma, et al. LCLS DOE Review Oct. 25, 2006 LCLS http://www-ssrl.slac.stanford.edu/lcls/internals/commissioning/index.html

LCLS Accelerator Schematic 6 MeV z  0.83 mm   0.05 % 135 MeV z  0.83 mm   0.10 % 250 MeV z  0.19 mm   1.6 % 4.30 GeV z  0.022 mm   0.71 % 13.6 GeV z  0.022 mm   0.01 % Linac-X L =0.6 m rf= -160 Linac-0 L =6 m rf gun L0-a,b Linac-1 L 9 m rf  -25° Linac-2 L 330 m rf  -41° Linac-3 L 550 m rf  0° 25-1a 30-8c ...existing linac 21-3b 24-6d 21-1 b,c,d undulator L =130 m X BC1 L 6 m R56 -39 mm BC2 L 22 m R56 -25 mm DL1 L 12 m R56 0 DL2 L =275 m R56  0 Commission in Jan. 2007 Commission in Jan. 2008 SLAC linac tunnel research yard

Complete & Detailed Optics (cathode to dump) BC2 L3 LTU undulator sec-21 sec-30 Full MAD files at: http://www-ssrl.slac.stanford.edu/lcls/linac/optics/

LCLS Installation and Commissioning Time-Line Drive-Laser Commissioning LTU/und. Install Drive-Laser Installed Controls Checkout LTU/und. hall “ready” First Spont. Light A S O N D J F M A M J J A S O N D J F M A M J J 2006 2007 2008 Gun/Inj./BC1 Install (8/21 – 2/20) Gun/Inj./BC1 Commissioning linac/BC2 Commissioning linac/BC2 Install LTU/und. Commissioning Oct. 18, 2006

LCLS Injector Commissioning Dates (2006 - 2007) Dec 18: PPS Certified Dec 20-Jan 1: Holidays Jan 2: VVS’s switched on for PEP-II (RF power available) Jan 15: L0a, L0b, L1 RF processing begins Feb. 1: X-band RF processing begins Feb 20: GTL beamline installation complete Mar 6: Virtual cathode fully characterized (ready to install gun) Mar 7: RG gun installation begins – laser rate to 30 Hz Mar 16: First laser UV-light on cathode! Mar 17: Electrons in GTL and gun-spectrometer Apr 9: Beam through L0a, L0b and down to 135-MeV spectrometer Apr 24: Beam into main linac (to TD11 dump) ~July: Take beam down full linac (to BSY SL2 stopper) http://www-ssrl.slac.stanford.edu/lcls/internals/commissioning/documents/commissioning-dates-2006-2007.ppt

Commissioning Definition and Strategy All components installed, aligned, connected, and initially verified by system engineer, before commissioning starts. Commissioning Sequence – Layered Approach (0-3) 0. Pre-Beam Checkout (tunnel, gallery, control room) Controls/software testing, camera checks, beamline inspection, etc Magnet polarities, cable connections, verify motion-control, etc Beam-based Hardware and Software Checkout Establish beam transport, RF setup, MPS/BCS tests, etc Checkout of all BPMs, magnets, wires, screens, toroids, etc First-Order Optics: Measurement and Correction Steering, transmission, oscillation data, feedback setup, etc Beta and dispersion matching, beam-base align key quads, etc Full Beam Characterization: Measurement and Correction Measure emittance, energy spread, distributions - correct Measure beam sensitivities, optimize tuning, beam experiments No (serious) emittance measurements until all hardware/software checked out!

(detailed schedule available) pass-1 pass-2 pass-3 pass-1 pass-2 pass-3

http://www-ssrl. slac. stanford http://www-ssrl.slac.stanford.edu/lcls/internals/commissioning/documents/2007-commissioning-plan.doc

LCLS Injector Commissioning Day 24-Hour Cycle (7 days/week, 1/2/07 to 8/31/07, 35 total weeks) DAY SHIFT (8:00-16:00) 1 lead physicist, 1 physicist, 1 controls eng., 1 sys. engineer, 1 LCLS operator, 1 laser operator SWING SHIFT (16:00-24:00) 1 lead physicist, 1 physicist, 1 LCLS operator, 1 laser operator OWL SHIFT (0:00-8:00) 1 LCLS operator, 1 laser operator ?

Personnel Available for LCLS Injector/BC1 Commissioning Shift Leaders (initially) (1 per D/S shift) Dave Dowell Paul Emma Jim Turner Bill White (laser) Joe Frisch Cecile Limborg Controls eng. (1 per DAY shift) Stephanie Allison Mike Zelazney Debbie Rogind Diane Fairley Stephen Norem Arturo Alarcon Doug Murray Sergei Chevtsov Dayle Kotturi Patrick Krejcik Kristi Luchini Sheng Peng Stephen Schuh Till Straumann Sys. Engineers (1 per DAY shift) Eric Bong Carl Rago Leif Eriksson Richard F. Boyce Jose Chan Tim Montagne Paul Bellomo Antonio de Lira Dave MacNair Ron Akre LCLS Physicists (1 per D/S shift) Sasha Gilevich Henrik Loos Heinz-Dieter Nuhn John Schmerge Dave Schultz Jim Welch Juhao Wu Accelerator, ILC, SSRL Franz-Josef Decker Rick Iverson Doug McCormick Jeff Corbett James Safranek... Operations (1 per DAY & SWING shift and 2 per OWL) Laser Operators (4-5) Visitors ?

Manpower Requirements (1/2/07 - 8/31/07) 35 weeks total (1/2/07 to 8/31/07, minus 2 weeks) 80% coverage (downtime) 14 lead-physicist shifts/week 14 physicist shifts/week 7 controls eng. shifts/week 7 sys. engineer shifts/week Average of 2-3 shifts/week for each physicist Average of 1/2 shift/week for each controls eng. Average of 1 shift/week for each sys. engineer

LCLS Commissioning Parameters Value Comments RF rate 10-30 Hz 10 Hz in linac with possible 30-Hz rate - 120 Hz in gun for short time to verify full rate Beam rate ≤30 Hz 30 Hz e- beam as baseline – possible short term 120-Hz tests in L0-BC1 for feedback tests, etc Drive-laser rate 30 Hz 120-Hz during laser commissioning – 30 Hz during e- commissioning - shutters provide lower e- rate Bunch charge 200-500 pC depends on QE and diagnostics – some short spans at 10 pC – later in ’07 explore 1-nC Drive-laser pulse length 10 ps fwhm 10-ps fwhm startup with possibility of 6-ps at 0.2 nC Gun gradient 120 MV/m Set as goal, although 110 MV/m is adequate in ‘07

Issues Controls will be mixed (SLC, Epics, Matlab) and capabilities may be limited initially (H. Shoaee) Most High-Level Applications (emittance, bunch length, feedback) done through MATLAB as temporary solution Many LCLS physicists not experienced with existing SLC controls Help from operations group is essential

RF Photo-Cathode Gun Q  1 nC f  120 Hz e- G  120 MV/m gex,y  1 mm Dt  10 ps I  100 A E  6 MeV e- spec. dipole e- UV laser solenoid YAG screens RF gun cathode

Injector Diagnostics YAG screen RF Gun trajectory (BPMs) emittance (+ slice) energy spread (+ slice) bunch length (+ dist.) charge (+ dark current) YAG screen YAG screen YAG screen YAG screen gun spectrometer Transverse RF deflector OTR & wire Injector Diagnostics OTR & wire OTR & wire OTR & wire main SLAC Linac injector spectrometer YAG YAG & OTR

Straight Ahead Spectrometer Bunch Length Diagnostics Injector Through BC1 RF Gun & Solenoid L0a&L0b S-Band Linacs Transverse RF Cavity Bunch-Compressor-1 (BPM, OTR, collimator) OTR & Wire Scanners Gun Spectrometer L1 S-Band Linac Wire Scanners + OTR 135 MeV 250 MeV TD-11 stopper X-Band RF Straight Ahead Spectrometer Bunch Length Diagnostics 40 m

Accelerator Sections Straightened Coordinate Measurement Machine (CMM) after before (De/e  30%) Four RF sections measured on CMM and straightened (L0a, L0b, L1a, L1b) Jose Chan

Magnet Polarities Defined and Documented DIPOLES QUADRUPOLES SOLENOIDS

BPMs, Wire-Scanners, etc. Polarities Defined q = 0 q = +45º q = -45º q = +45º

All Magnets Measured (all steering coil ‘types’) 2 Solenoids 19 Inj. Quads 2 GTL Quads 2 BC1 Quads 3 Linac Quads 2 DL1 Dipoles 4 BC1 Dipoles 2 Spect. Bends 6 corr. types Dipole field vs. x Current vs. integrated field FINT = 0.454 Solenoid eff. length Dipole fringe field vs. z + field harmonics

BC1 Chicane tweaker quad 2 0-30 cm translation stage tweaker quad 1 OTR X-band RF collimator BPM

BC1 Dipole Fields are Marginal tracking through fields measured with stretched wire De/e0  1 to 6 % Pole nose pieces in fabrication + tweaker quadrupoles available

Dispersion Correction in SPPS Chicane One linear comb. of 2 tweaker quads

Pre-Beam Tunnel Check List etc.

Summary Injector e- commissioning starts Mar. ’07 Main ’07 goal is to verify full functionality of gun, injector beam-line, diagnostics, and controls, not generate full beam brightness immediately Will need frequent linac access initially (8-16 hrs/week?) + 1 install-day per month (24-48 hrs?) Phase-II of commissioning comes in Dec. ’07 Information available at commissioning web-site: http://www-ssrl.slac.stanford.edu/lcls/internals/commissioning/index.html