Presentation is loading. Please wait.

Presentation is loading. Please wait.

Linac (WBS 1.2.2) Vinod Bharadwaj April 23, 2002

Similar presentations


Presentation on theme: "Linac (WBS 1.2.2) Vinod Bharadwaj April 23, 2002"— Presentation transcript:

1 Linac (WBS 1.2.2) Vinod Bharadwaj April 23, 2002
System Description Major Technical Challenges ES&H Cost Estimates Construction Schedule & Critical Path Issues PED Strategy for FY2003, FY2004 LCLS DOE Review, April 23, 2002 Vinod Bharadwaj, SLAC

2 LCLS Linac Overview The function of LCLS Linac (Accelerator) is
Accept 1 nC electron bunch at 150 MeV from the LCLS Injector Accelerate the beam to 4.54 – GeV ( 15 – 1.5 Å ) Compress the beam to a nominal 22 mm bunch length Transport beam to the input of the undulator Preserve beam emittance during the acceleration, compression and transport ( <20% slice, <100 % projected increase for 1.5 Å) Control energy spread (<0.02 % slice, <0.1 % for 1.5 Å) Measure beam properties before injection into the undulator to allow for an understanding of the FEL Take beam from the output of the undulator and dump it Allow for flexible operation – low charge, range of energies, beam energy chirp … LCLS DOE Review, April 23, 2002 Vinod Bharadwaj, SLAC

3 LCLS Linac Overview The LCLS Linac overlays part of the existing SLAC accelerator complex The use of the existing linac has to be compatible with PEP-II operation LCLS has to allow for test beams for HEP and other uses at low rates, but on an arbitrary pulse stealing mode – this has a major impact on the LCLS Linac Design LCLS DOE Review, April 23, 2002 Vinod Bharadwaj, SLAC

4 Nominal Linac Parameters
Parameter Initial 15 Å 1.5 Å Units Electron energy GeV Bunch Charge nC Normalized projected emittance µm rad Total energy spread % Slice energy spread % RMS bunch length mm Peak current A Longitudinal slice brightness A LCLS DOE Review, April 23, 2002 Vinod Bharadwaj, SLAC

5 LCLS Linac – Major Sub-Systems
The LCLS Linac consists of the following sub-systems (the new systems are colored green L1 – short linac, three 3-m sections in Sector 21-1b,c,d LX – 60-cm long X-band RF structure BC1 – 4-magnet chicane bunch compressor L2 – 330-meter long linac going from Sector 21-3b – 24-6d SC Wiggler – one period wiggler BC2 – 4-magnet chicane bunch compressor L3 – 550-meter long linac going from Sector 25-1a – 30-8d BSY beamline DL2 – beamline transport to the undulator Dump Beamline – dump the electron beam after the Undulator LCLS DOE Review, April 23, 2002 Vinod Bharadwaj, SLAC

6 SLAC linac tunnel undulator hall (12/01/01) courtesy P. Emma
LCLS Accelerator and Compressor Schematic 7 MeV z  0.83 mm   0.2 % 150 MeV z  0.83 mm   0.10 % 250 MeV z  0.19 mm   1.8 % 4.54 GeV z  mm   0.76 % 14.35 GeV z  mm   0.02 % Linac-X L =0.6 m rf=180 rf gun new Linac-1 L =9 m rf = -38° Linac-2 L =330 m rf = -43° Linac-3 L =550 m rf = -10° Linac-0 L =6 m ...existing linac 21-1b 21-1d X 21-3b 24-6d 25-1a 30-8c undulator L =120 m BC-1 L =6 m R56= -36 mm BC-2 L =22 m R56= -22 mm DL-1 L =12 m R56 0 DL-2 L =66 m R56 = 0 SLAC linac tunnel undulator hall (12/01/01) courtesy P. Emma LCLS DOE Review, April 23, 2002 Vinod Bharadwaj, SLAC

7 Major Technical Challenges – Beam Quality
Physics challenges – Paul Emma’s presentation Coherent Synchrotron Radiation in Bends projected emittance growth micro-bunching instability Emittance Preservation in Linacs transverse wakefields component misalignments & chromaticity Machine Stability jitter tolerance budget simulation of budget LCLS DOE Review, April 23, 2002 Vinod Bharadwaj, SLAC

8 Major Technical Challenges – Diagnostics
LCLS is a challenging machine to tune and operate LCLS charge range nC (order of magnitude less than SLC) Need good diagnostic capabilities, (see PK & DD Talks in Injector/Linac BO) LCLS is divided into logical pieces Injector – L1+LX+BC1 – L2+BC2 – L3+DL2 Diagnostics stations at the end of each logical piece so that they can be set up independently Emittance and Energy Spread measurement using standard SLAC diagnostics – wires, BPMs .. ...existing linac L0 rf gun L3 L1 X L2 gex,y sE LCLS DOE Review, April 23, 2002 Vinod Bharadwaj, SLAC

9 Major Technical Challenges – Longitudinal Diagnostics
RF transverse deflecting cavities – TC (slide courtesy PK) Electro optic systems - EO Terahertz radiation monitors for bunch length - Tz Energy and energy spread BPMs and Profile Monitors - DE CSR measurements from synch light from BC bends Beam phase measurements - f Zero phase crossing measurement of bunch length - Zf EO f Tz Zf TC DE CSR LCLS DOE Review, April 23, 2002 Vinod Bharadwaj, SLAC

10 Major Technical Challenges – Diagnostics
Feedback systems needed for bunch length commissioning, tuning and operation Emittance and orbit control Helped by SLC operational experience Need new Beam Position Monitor readout electronics LCLS charge range smaller than SLC running BPMs still need to work in HEP mode LCLS resolution requirements more stringent LCLS DOE Review, April 23, 2002 Vinod Bharadwaj, SLAC

11 Major Technical Challenges – RF
The LCLS design has very tight tolerances for RF phase stability in the various linacs in order to make the bunch compression work well Need phase stability of 0.1 degrees S-band in L1, L2 Need amplitude stability of 0.1 % The present RF has this stability of timescale of order one minute To achieve this Install new LLRF (Solid State Sub-Boosters - SSSB, Isolator-Phase-shifter-Attenuator - IPA) + associated controls for critical klystrons – L1, two in L2, two in L3 (and the transverse RF diagnostic cavity) New timing system will trigger L1 and LX directly Extensive work needed on RF feedbacks to correct drifts on the one minute time scale LCLS DOE Review, April 23, 2002 Vinod Bharadwaj, SLAC

12 Major Technical Challenges – timing system schematic
LCLS DOE Review, April 23, 2002 Vinod Bharadwaj, SLAC

13 Major Technical Challenges – HEP test beams
SLAC running in the LCLS era LCLS is scheduled to run 75% of the time HEP dedicated runs for the remaining 25% Low rate test beams for HEP and other uses are required on demand in “pulse stealing” mode during LCLS running Test beams will not compromise the LCLS beam Test beams during LCLS running Arbitrary pulse stealing at low rate (<10 Hz) Maximum beam energy of 30 GeV – LCLS is just a beam transport Beam transmission through BC1, BC2 chicanes needs careful design Pulsed quads needed in order to have optimal test beam quality for the higher energy test beams ( LCLS ~ 150 MeV – 15 GeV ; Test Beams ~ 30 GeV ) LCLS DOE Review, April 23, 2002 Vinod Bharadwaj, SLAC

14 ES&H Issues The LCLS Linac is a modification of the existing SLAC accelerator complex and all the needed policies, practices and rules are already in place. Two issues are worth mentioning .. The maximum credible beam power has been calculated. At injection into the LCLS Linac it is 1.5 kW and at 15 GeV it is 150 kW. (LCLS-TN J.E. Clendenin, I. Evans, S. Mao, D.T. Palmer, J. Schmerge, and M. Woodley, "LCLS Maximum Credible Beam Power," March 30, 2001) We are putting a tuneup dump in DL2. This is needed so that the beam quality can be checked and optimized before attempting injection into the undulator. The tuneup dump is located in the part of the FFTB tunnel that is under the berm so there are no associated shielding problems LCLS DOE Review, April 23, 2002 Vinod Bharadwaj, SLAC

15 Cost Estimate – 1.2.2 WBS – Summary Parts list
LCLS DOE Review, April 23, 2002 Vinod Bharadwaj, SLAC

16 1.2.2 Accelerator Cost Estimate (FY02 Dollars, Thousands)
Name PED Construction Contingency Total % Contingency 1.2.2 Accelerator $ 6,269 $ 11,909 $ 4,874 $ 23,052 27% $ 1,954 $ 8,222 31% Mechanical $ 1,238 $ $ 1,598 29% Vacuum $ 1,079 $ 1,440 33% Diagnostics $ 1,070 $ $ 1,332 24% Power Conversion $ 2,724 $ $ 3,094 14% Magnets $ 1,720 $ $ 2,150 25% Controls $ 1,876 $ $ 2,356 26% RF $ 2,201 $ $ 2,860 30% LCLS DOE Review, April 23, 2002 Vinod Bharadwaj, SLAC

17 Construction Schedule
LCLS Linac construction milestones – Magnets to bid Oct 2004 SC wiggler to bid Oct 2004 BC-1 Magnets award Jan 2005 SC wiggler award Jul 2005 Start of BC-1 shutdown Oct 2005 BC-1 Magnets received Dec 2005 X-band installed Jan 2006 BC-1 installed Jan 2006 First beam to BC-1 Mar 2006 SC wiggler received May 2006 Start BC-2/DL2 shutdown Oct 2006 BC-2 installed Jan 2007 DL2 installed Jan 2007 Start BC-2 commissioning Mar 2007 LCLS Linac commissioned Oct 2008 LCLS DOE Review, April 23, 2002 Vinod Bharadwaj, SLAC

18 Technical Risk in the LCLS Linac
Emittance control Emphasis on diagnostics SLC and SLAC operational experience Understanding physics effects such as CSR Bunch length optimization Fast relative bunch length measurement Beam temporal structure measurements Bunch length feedback Stability issues Control of input parameters such as charge, timing RF improvements for phase, amplitude stability Feedbacks Start-to-end simulations of the system LCLS DOE Review, April 23, 2002 Vinod Bharadwaj, SLAC

19 Critical Path Issues Goals: Commission up to BC1 – Spring 2006
Commission Linac – Summer 2007 BC1 system design Fast bunch length monitoring needed for BC1 commissioning Timing, RF modifications for L1, and LX needed for BC1 commissioning (RF mods in Injector PED) LCLS DOE Review, April 23, 2002 Vinod Bharadwaj, SLAC

20 PED Milestones in FY2003 December 2002 March 2003 June 2003
Dipole magnet modelling finished March 2003 Quadrupole magnet modelling finished Fast bunch length monitor design complete June 2003 X-band structure design complete September 2003 SC wiggler magnet specs finished BC1 magnet design, vacuum and articulation finished High resolution BPM electronics designed LCLS DOE Review, April 23, 2002 Vinod Bharadwaj, SLAC

21 PED Milestones in FY2004 December 2003 March 2004 June 2004
Magnet power supplies defined March 2004 BC2 magnet, vacuum chamber and articulation design complete Fast bunch length monitor prototype testing complete June 2004 Vacuum system design complete High resolution BPM electronics prototyping finished Magnet and wiggler design complete RF systems design complete September 2004 Designs finished & reviewed Bid packages for all systems ready LCLS DOE Review, April 23, 2002 Vinod Bharadwaj, SLAC

22 CD-2 Preparations LCLS Linac is a modification of the existing SLAC accelerator complex, the majority of equipment is already in place and operational By April 2003 New magnet modelling complete Fast bunch length monitor design complete X-band RF system design started LCLS DOE Review, April 23, 2002 Vinod Bharadwaj, SLAC

23 Conclusions LCLS Linac physics is well understood
Needed modifications to the SLAC accelerator complex well understood System is well instrumented PED plans for FY03, FY04 presented Construction milestones are set to provide first beam at the end of DL2 in spring 2007 LCLS DOE Review, April 23, 2002 Vinod Bharadwaj, SLAC


Download ppt "Linac (WBS 1.2.2) Vinod Bharadwaj April 23, 2002"

Similar presentations


Ads by Google