Jess Albino CF – Breakout Session June 17, Facility Advisory Committee LINAC Coherent Light Source Project Conventional.
David Saenz FAC CF April 20, 06 Meeting of the LCLS Facilities Advisory Committee LCLS Conventional Facilities D. Saenz.
David Saenz CM/GC April 8, 2005 CM/GC Overview CM/GC Plan & Status Systems Description Cost Estimate Construction Schedule.
Jess Albino Session 5 Conventional November 11, Facility Advisory Committee LINAC Coherent Light Source Project.
David Saenz Facility Advisory October 30, 2007 CONVENTIONAL FACILITES MANAGEMENT.
Mark Reichanadter LCLS FAC April 20-21, 2006 Meeting of the LCLS Facilities Advisory Committee LCLS Project Management M.
Jess Albino FAC CF April 16, 2007 Meeting of the LCLS Facilities Advisory Committee LCLS Conventional Facilities Jess.
1 Jess Albino 1 Conventional Facilities Status FAC Review – Breakout Session CONVENTIONAL FACILITIES STATUS Jess Albino – Associate.
Jess Albino Facility Advisory October 29, 2007 FACILITY ADVISORY COMMITTEE PLENARY CONVENTIONAL FACILITIES UPDATE October.
Bob Law FAC Oct 24, Sector 20 Project Overview Sector 20 Site Plan Description Organizational Chart Schedule Cost.
Development plan and quality plan for your Project
M. Scharfenstein - ES&H Coordinator 8 June 2009
CVE 1000 Construction Engineering The Project Delivery System Prof. Ralph V. Locurcio, PE.
David McGiven FAC: Construction April 2006 Facility Advisory Committee (FAC) Construction Procurement David.
1 BROOKHAVEN SCIENCE ASSOCIATES LOB - Ring Building Construction Coordination Michael P. Bromfield Construction Engineer NSLS-II Conventional Facilities.
1 BROOKHAVEN SCIENCE ASSOCIATES Construction Management Status Steve Sawch Assistant Director for Construction Management NSLS-II Conventional Facilities.
1 BROOKHAVEN SCIENCE ASSOCIATES Ring Building Construction Status Steve Sawch Assistant Director for Construction Management NSLS-II Conventional Facilities.
1 BROOKHAVEN SCIENCE ASSOCIATES CFAC Review Martin Fallier Director, Conventional Facilities Conventional Facilities Value and Risk Management May 8, 2008.
BROOKHAVEN SCIENCE ASSOCIATES National Synchrotron Light Source II Project Management Jim Yeck NLSL II Deputy Director (Project Management)
1 BROOKHAVEN SCIENCE ASSOCIATES NSLS-II Project Baseline Jim Yeck NSLS-II Deputy Project Director NSLS-II PAC Meeting November 20, 2007.
1 BROOKHAVEN SCIENCE ASSOCIATES NSLS-II Status & Charge to ASAC Steve Dierker Associate Laboratory Director for Light Sources, NSLS-II Project Director.
1 BROOKHAVEN SCIENCE ASSOCIATES NSLS-II Update Steve Dierker Associate Laboratory Director for Light Sources NSLS-II Project Director Conventional Facilities.
CVE 4070 Construction Engineering Course Review & Critique Prof. Ralph V. Locurcio, PE.
David Saenz FAC Review CF Design, Cost and Schedule Oct 27, 2005 CF Overview & Status Design Status CMGC Status Latest.
1 BROOKHAVEN SCIENCE ASSOCIATES NSLS – II CFAC Review Conventional Facilities Method of Accomplishment Marty Fallier Director for Conventional Facilities.
M. Reichanadter LCLS Project November 2008 FAC Meeting Slac National Accelerator Laboratory Report to the LCLS.
Mark Reichanadter LCLS FAC October 12-13, 2006 Report to the LCLS Facilities Advisory Committee LCLS Project Management.
David Saenz Readiness for Oct 12, 2006 # Meeting of the LCLS Facilities Advisory Committee LCLS Conventional Facilities.
DOE Stanford Site Office Office of Science U.S. Department of Energy 1 U.S. Department of Energy’s Office of Science Office of Science Review of the LCLS.
Mark Reichanadter LCLS October 9-11, 2007 LCLS BCR Overview and EIR LOIs Project Progress / Status Revised Project Baseline.
CVE 4070 Construction Engineering Course Review Prof. Ralph V. Locurcio, PE.
David Saenz EIR Review Oct 9-11, Conventional Facilities (CF) WBS 1.9 ETC and Methodology David Saenz CF Systems Manager.
CLAIMS MANAGEMENT. PRESENTATION OUTLINE INTRODUCTION TYPICAL CLAIMS AGAINST OWNER TYPICAL CLAIMS AGAINST CONTRACTOR CRITICAL PATH METHODS UTILIZATION.
OTC Pres Project Del P5 12/08 Page 1 Project Delivery Performance Improvement Report to the Oregon Transportation Commission Jeff Gower, State Construction.
1 BROOKHAVEN SCIENCE ASSOCIATES Conventional Facilities Schedule Steve Sawch Asst. Director, Construction Management CF Advisory Committee Review of the.
CHANGE ORDER/CLAIMS MANAGEMENT MODULE 9. Change Order Management.
CBETA Project ALD’s Cost and Schedule Review February 6, 2017
Green Line Extension Project
Project Management W. J. Foyt
CF Organization & Schedule
Meeting of the LCLS Facilities Advisory Committee
Far Experimental Hall Hutches Civil Construction
LESSONS LEARNED NYP Design and Construction NYP BEST PRACTICES.
Far Experimental Hall Hutches Civil Construction
CONVENTIONAL FACILITIES STATUS
M. Scharfenstein - ES&H Coordinator 14 May 2009
Electron Beam Systems ETC and Methodology
Delta Water Supply Project
CONVENTIONAL FACILITIES LCLS Office Space
Department Of Energy Review LINAC Coherent Light Source Project
Details supporting the increase
CONVENTIONAL FACILITIES LCLS Office Space Procurement
DOE Review of the LCLS Project
Project Management Issues John N. Galayda, SLAC April 24, 2002
Project Status Review May 13-15, 2008.
Conventional Facilities WBS 1.9
Integrated Safety and Environmental Management
Department of Energy Review of the LCLS Project
Conventional Facilities Status
CONVENTIONAL FACILITIES
Installation Status & Operational Readiness Process
Conventional Facilities
Phase 1 Statement of Work Preconstruction “Plan The Work”
DOE Mini-Review of the LCLS Project
DOE Review of the LCLS Project
AE Title III Status Introduction
CF Scope, Management & Organization
DOE Status Meeting of the LCLS Project
CMGC Overview SLAC Site Plan Systems Description Construction Schedule
Presentation transcript:

Department Of Energy Review Linac Coherent Light Source Project Conventional Facilities Management and Organization J. Albino

TEC Estimate to Complete Cost to Go at WBS Level 3 1.09 Conventional Facilities $M, Burdened, Escalated TEC Estimate to Complete Contingency % Contingency Total Estimated Cost (TEC) 96.22 15.5% 14.89 1.09.01 System Management & Integration 15.91 13.5% 2.15 1.09.02 Title 1 & Title 2 Conventional Facilities 0.05 0.01 1.09.03 Construction-T3 Conventional Facilities 80.27 15.9% 12.73

Basis of Estimate - ETC

CONSTRUCTION CONTINGENCY Contingency Analysis CONSTRUCTION CONTINGENCY QUALITY OF DESIGN 2-5 % OF CONSTRUCTION COST – USE 3% CONSTRUCTION MANAGEMENT 3-7 % OF CONSTRUCTION COST – USE 4% OWNER-INITIATED CHANGES 5-? % OF CONSTRUCTION COST – USE 8%

CONTINGENCY ANALYSES

CF Construction Phase Cost/Schedule Performance CPI = 1.03 SPI = 1.01 Title III Awarded Amount: $63,972,680 Obligated Funds: $10,592,451 SPI = 1.01 NTP: 01Aug06 Commence Sitework: 01Sep06 Beam Line Beneficial Occupancy: 8Feb08 Contract Close-out: 18Aug08 Contract Administration Submittals Received: 32 Approved: 18 RFI: Received: 55 Closed: 55

CF Construction (cont.) Field Change Orders: Authorized with NTE: 10 Not-to-exceed sum: $100,000 Pending: 2 Estimate: $275,000

Schedule Delays Schedule Mitigation Bid Groups 1 and 2 Evaluation – 2 months (NTP 01AUG06) Re-sequence Beam Transfer Hall – 2 months Weather Contingency – 2 month Schedule Mitigation Develop Early Occupancy Dates Baseline Construction on Shorter Duration

LCLS CF Construction Schedule Jan 07 Feb 08 Feb 08 Feb 08 Feb 08 Feb 08 Feb 08 Feb 08 Aug 08

BASELINE FRAG-NET (BEAMLINE)

Level 3 Milestones

Level 3 Milestones

Next 6 Months CONSTRUCTION Complete Site Grading Excavate Undulator Hall tunnel Excavate Near Experimental Hall, Pour base slab Excavate and Pour Central Utility Plant base slab Excavate and Pour Fixed End Enclosure Form and Pour Beam Dump Slab-On-Grade

Next 6 Months (cont.) CONSTRUCTION (cont.) ADMINISTRATION Form and Pour Beam Transfer Hall Slab-On-Grade Begin Access Tunnel ADMINISTRATION Delete Central Lab Office Complex Complete CF Project Management Documents Timely Submittal Processing Process Changes Enforce Safety Plan Enhance Coordination with Technical Systems Monitor Contractor

CF Construction Organization

Issues (and Mitigation) Encountering Remnant Utilities Surveys to locate active utilities Coordination with CEF to review historical records Trenching to locate abandoned and unmapped utilities Site Security and Safety Signing and Fencing Communication with SLAC residents All-hands Bulletin Active Enforcement Construction Delays Mitigation Plans in advance Work-arounds and Re-sequencing Contingency Plans

Issues (and Mitigation) cont. CLOC De-scoping Thorough Scrubbing of CLOC scope items Definition of Scope Reduction Interfaces Coordination and Negotiation with CM/GC Technical Systems Construction Tolerances Definition of Needs in concert with Tech. Systems Coordination with Trade Contractor to meet spec. Preparation of Work Plans to accomplish goals Increasing Market Costs Maximize Forward Pricing Minimize Change Orders Use Volume Purchasing where practical Disputes and Claims Quickly Address Claims Implement Dispute Review Board Process Prepare and Use an Issues Resolution Ladder

Summary Good Progress on all fronts since last review. CF staff has been strengthened to ensure adequate experience is integrated in all requirements Continue to Value Engineer Interface with SLAC, Tech. Systems, CM/GC Support TCCo and Construction to prevent delays – keep to the schedule. Complete Development of tools for CF Staff Team is in place to safely construct the LCLS “house”!