Current Module LT Testing Capability

Slides:



Advertisements
Similar presentations
TEC Production in the US N. Bacchetta, J. Incandela,…and October 14, 2003.
Advertisements

Slide 1Module Testing Meeting March 7, 2003US Hybrid/Module/Rod Testing Model-Anthony Affolder US Hybrid/Module/Rod Testing Model Anthony Affolder (for.
US CMS Silicon Tracker : Schedule J. Incandela University of California Santa Barbara US CMS Silicon Tracker Project Manager Fermilab PMG April 9, 2004.
1 Long Term Module Testing-Anthony AffolderTPO, December 11, 2003 Current Module LT Testing Capability Only Vienna Boxes Available  10 slots at each site.
US Module and Rod Production Overview and Plan For the US CMS Tracker Group.
Slide 1UCSB Rod Production presented by Jim LambDOE review, January 20, 2004 UCSB Rod Production UCSB Rod Production, Jan , presented by Jim Lamb.
Slide 1 Anthony Affolder US Silicon Meeting, March 9, 2004 Equipment Status ARCS equipment status à Single module and 4 hybrid DAQ equipment status à Vienna.
US Tracker Group Status Sep. 1, 2005 J. Incandela For the US CMS Tracker Group.
Slide 1Rod Production presented by Jim Lamb (UCSB)April 9, 2004 Rod Production Rod Production, April , presented by Jim Lamb (UCSB)
1 US Testing Update-Anthony AffolderTracker Meeting, Feb 10, 2004 US Module Testing Update Anthony Affolder (On behalf of the US testing group) Update.
CMS Tracker Week – Module Test Meeting – April 2003 – Patrick Gartung 1 Status of US long term module testing Patrick Gartung University of California,
Lab5 Production Status: Optics and RBX integration Pawel de Barbaro U. of Rochester.
Anthony AffolderUS CMS Meeting 12/3/02DAQ Based Systems LV/HV Needs DAQ Power Supply Needs HV à 600 V/~1mA range –0.1-1  A Current Sensing –Over Voltage/Current.
US Module Production June 2, 2005 J. Incandela For the US CMS Tracker Group.
Tom Kubicki.  Booster HLRF System to be upgraded using 1kW Solid State Driver (SSD) Amplifiers.  Used to drive the 200kW Power Amplifier  Eliminates.
Proton Plan PMG 3/22/07 E Prebys 1 Proton Plan Status February Eric Prebys.
Saverio Minutoli INFN Genova 1 1 T1 Electronic status Electronics Cards involved: Anode Front End Card Cathode Front End Card Read-Out Control card VFAT.
Concluding Summary WBS1.1.2 SCT Subsystem A. Seiden BNL March 2001.
Roberto Tenchini CMS FB December 2004 CMS Tracker The Tracker Cost Review - November 2004.
Fermilab PMG - Results from module testing - April 9, 2004 – E.Chabalina (UIC) 1 Results from module testing E.Chabalina University of Illinois (Chicago)
Run 12: STAR Status and Schedule Update RHIC Coordination Meeting October 18, 2011 Bill Christie BNL Outline Status update Schedule update and issues Summary.
1 ME1/1 ODMB Production Readiness Review: Schedule and Budget Darien Wood Northeastern University For the ME1/1 Electronics Project.
Summary Plans Content Module assembly at CERN and Dubna Readout DAQ Procurement Stacking Summary.
Preparations to Install the HBD for Run 6 Craig Woody BNL PHENIX Weekly Meeting January 26, 2006.
J. Valls, CMS L2-L3 Meeting, Sept ROD Production at CERN  ROD Flow During Production  ROD Flow at CERN  ROD Testing Areas  Infrastructure  Equipment.
Assembly 12/14/06 #1 Assembly and Commissioning Paul Huffman.
ELENA installation progress F. Butin / ELENA collaboration.
PIXEL CAEN Installation Status
Jim Fast Pacific Northwest National Laboratory
CLAS12 DAQ & Trigger Status
GEM DAQ-Chamber Integration Test Stand for GE2/1 & ME0 at Florida Tech
T1 Electronic status Conclusions Electronics Cards:
10/month is the present production rate 2 FTE + sporadic contributions
Status Brussels GANTRY
ROD assembly and test in US
DAQ Equipment Status 2 fully equipped Vienna boxes at UCSB and FNAL
UCSB Testing Status Anthony Affolder
UCSB Testing Status Anthony Affolder
UCSB Short-term Testing Plan
Results from module testing
Unexpected Failures of Modules on Rods
ENGINEERING MANAGEMENT (GE 404)
UCSB Testing Status Anthony Affolder
X-ray Pump-Probe Instrument
Hardware Needs (Near Term)
On behalf of the US TOB testing group
First Assembled Rod in US
Module production in Italy
US Testing Update Anthony Affolder (On behalf of the US testing group)
UCSB Short-term Testing Plan
Operations/Failure Analysis
Hybrid & Module Electrical Testing
EVLA Advisory Committee Meeting
US Hybrid/Module/Rod Testing Model
US Module Testing Progress Report
Operations/Failure Analysis
Current Module LT Capability
HL-LHC upgrade at IPHC news
Operations/Failure Analysis
Hybrid & Module Testing Status
US Module Testing Progress Report
Operations/Failure Analysis
US Rod Burn-in Readiness DAQ Hardware/Power Supplies
Status of Bonding R1N, R1S, R3 of TEC University of Hamburg
Equipment Status ARCS equipment status DAQ equipment status
Software Project Management
Trillo Apparel Company Revised Delivery Plan
Hardware needs (ARCS) Current ARCS capabilities at both sites should be able to keep up with production assuming software changes Automatic I-V curves,
CSC Electronics Installation and Commissioning Oct ‘06
Racks PC Rack >> 24 mini and 12 tall PC racks Mini Racks
Presentation transcript:

Current Module LT Testing Capability Only Vienna Boxes Available 10 slots at each site ~75% efficiency of running time Will estimate the amount of time run per module with: 50,100 module tested at each site 1 month, 2 months, 4 months run periods Will assume 1 week at end to pull together results and 1 week lost to produce modules, procure & test module components, etc.

Current Time Estimates 1 Month 2 Months 4 Months 50 Modules 2 ½ Days 7 Days 16 Days 100 Modules 1 ¼ Days 3 ¼ Days 8 Days Modules Per Site To run 100 modules for ~week each will need either: Both sites running for ~2 months 1 running for ~4 months Any production beyond the 100 modules mentioned disrupts this test significantly Any new modules would have to be put into Vienna box for testing as rods will not be available at rates to burn-in on rods Thus, more modules could be run, but for less time Even more time lost to loading/etc. How long do we want to run the modules?

Way To Increase Modules Run Run modules on rods in rod burn-in box To get statistics needed (~100 modules), use 16 single sided rods Use of DS rods will not increase statistics; DAQ hardware max-ed out at 8 SS4 rods Two fully equipped/functional rod burn-in boxes Or multiple runs with smaller number of rods Calculate time run assuming: 2, 4, or 8 rods per box DAQ components for 2 rod running should be available at end of December 4, 5, or 6 month periods from today Assume 3 months to commission system to point that it is safe enough to run unattended and assemble 16 rods Assume 75% efficiency once stable Very aggressive, assumes that software and hardware works almost immediately and that system scales from 1 to 8 rods with no major problems 10 more cabled rods available late Jan./early Feb. Assume 2 weeks total to pull together results after run THIS SCHEDULE IS EXTREMELY AGGRESSIVE AND HAS NEVER HISTORICALLY OCCURRED IN SIMILAR SITUATIONS

Rod Burn-in Time Estimates 4 Months 5 Months 6 Months 2 Rods 3 Days 8.5 Days 14 Days 4 Rods 6 Days 17 Days 28 Days 8 Rods 12 Days 34 Days 56 Days Rods Per Cycle To get more significant running time per module (2 weeks) Need 6 months with 2 rod per cycle capability Need 5 months with 4 rod per cycle capability Need 4 months with 8 rod per cycle capability If a month per module is preferred, need 4-8 rod per cycle capability in order to finish test in time period given Would take significant manpower, hardware increases, and software and data analysis development Takes resources from other commitments: TOB/TEC hybrid PA wire bonding/testing, starting TEC module production, ramp up of TOB module production, finalization of module LT setups

Difficulties in Rod Burn-in (Hardware) Assumes equipment/hardware we do not have yet: 12 assembled rods PS cables 2 rods per cycle still need: 2 Delphi LV PS 2 OFED (2 OEC each) 2 oMUX crates with 3 oMUX each 4 rods per cycle still need: 6 Delphi LV PS 4 OFED (2 OEC each) 2 oMUX crates with 5 oMUX each 8 rods per cycle still need: 14 Delphi LV PS 8 OFED (2 OEC each) 4 oMUX crates with 5 oMUX each Recent/imminent deliveries of: All oMUX All OFED Parts and test equipment limit number of rods usable Assembled rods 10 more rods late Jan/early Feb Rest in late Feb Delphi LV PS 5 total for tracker in Dec. 5 total for tracker in Jan. 12 total for tracker at end of Feb. Rest in April To do significant number of rods would require majority of Delphi LV PS built May have to “borrow” existing supplies from current sites

Difficulties in Rod Burn-in (Software) Assumes software we do not have yet LT only shown to work on 1 rod May not be easily expandable to number of modules needed (Multiple oMUX crates, memory, etc.) May require significant fraction of Wim’s and Valery’s time Single rod commissioning/ validation software not developed yet Do not have algorithms to do fault finding Software to monitor/find changes in module response during module burn-in does not exist yet Similar rod software would have to follow the module software Rod burn-in slow controls/interlocks have not been commissioned with rods yet Integration beginning as we speak

Difficulties in Rod Burn-in (Manpower) The same personnel at UCSB/FNAL would have to be used for: Testing/assembly of modules/rods for this study Begin TEC module construction/testing Begin TOB/TEC hybrid testing Construction/commissioning rod burn-in stand Development in stages due to lack of rods and power supplies The same personnel needed for software development Module LT analysis Rod commissioning Rod burn-in software Rod burn-in analysis

Conclusions (1) The rod burn-in stands needed to run large number of modules for a significant period of time Such a program would require a commitment of a large fraction of the resources needed for sub-structure assembly/testing (Almost) all the Delphi LV PS in community Large fraction of testing manpower at UCSB/FNAL Most of the software developers time This commitment will leave few resources for other tasks Hybrid/module production and testing TEC module production in US If everything delivered on schedule and works perfectly, earliest we could get 100 modules run for 1 month each would be April This assumes 8 rod burn-in assemble and commissioned at both sites starting late February This assumes 4 complicated software packages will developed and commissioned in the same time frame

Conclusions (2) From historically similar situations It is not likely that all equipment needed will arrive in the time needed It is not likely that all the software needed will be developed in time From this experience I would assume that we could run 100 modules for an one-month period by June/July/Aug I do not have enough information now to make a more precise estimate Each equipment piece (2 types) and software package (4 types) can easily be delayed by a month easily