Hal Tompkins – Photon Beam Systems Deputy June 8, 2009

Slides:



Advertisements
Similar presentations
Richard M. Boyce FAC Review – Accelerator Installation October 29-31, Installation – Accelerator Systems Installation Planning.
Advertisements

LCLS Transition to Science DOE Status Review of the LUSI MIE Project LCLS NEH ARR John Arthur LCLS Experimental Facilities Division August 11, 2009 Welcome.
Hal Tompkins FEE/FEL June 16, FEE/FEL Commissioning Overview By Hal Tompkins Photon Beam Systems Deputy.
1 John Arthur 1 FEH Status CXI Review June 3, 2009 FEH Layout, Status John Arthur – LCLS Expt’l Facilities Div June 3, 2009.
Richard M. Bionta XTOD July 19-21, 2005 UCRL-PRES-xxxxxx X Ray Diagnostics LCLS FAC Meeting Oct. 27, 2005.
James Welch October 30, FEL Commissioning Plans J. Welch, et. al. FEL Commissioning Plans J. Welch, et. al. Accelerator.
1 Roger Erickson 1 Coordination with Accelerator Systems NEH Accelerator Readiness Review Coordination with Accelerator Systems.
Richard M. Bionta XTOD October 12, 2004 UCRL-PRES-XXXXX X Ray Transport, Optics, and Diagnostics, Overview Facility Advisory Committee.
John N. Galayda LCLS FAC 20 April Linac Coherent Light Source Overview and Charge Facility Advisory Committee John.
Paul Emma LCLS Commissioning Status Nov. 11, 2008 SLAC National Accelerator Laboratory 1 LCLS Commissioning Status P. Emma for The.
John Arthur Photon Systems April 16, LCLS Photon Systems Status Technical status and accomplishments Response to.
X Ray Transport / Optics / Diagnostics Overview Richard M. Bionta Facility Advisory Committee Meeting April 29, 2004 Richard M. Bionta Facility Advisory.
LCLS Transition to Science DOE Status Review of the LUSI MIE Project NEH status and XFD operations Hal Tompkins, John Arthur LCLS Experimental Facilities.
John Arthur X-Ray Optics October 12, 2004 X-Ray Prototype Optics Specifications John Arthur.
D. Schultz FAC 6/17/08 1 e-Beams Systems Update People Progress the last review LTU and Dump Installation Status Undulator.
Richard M. Bionta X-Ray Transport, Diagnostic, & Commissioning September 22, 2004 UCRL-PRES Two Problems... LCLS Diagnostics.
Richard M. Bionta XTOD Layout and Diagnostic October 12-13, 2004 UCRL-PRES-XXXXX XTOD Layout and Diagnostic Systems Facility Advisory.
John Arthur Photon October 12, Photon Systems Update John Arthur SLAC 1.
Hal Tompkins Photon October 30, LCLS Photon Systems Installation and Commissioning Presentation to Facility Advisory.
R. M. Bionta SLAC November 14, 2005 UCRL-PRES-XXXXXX LCLS Beam-Based Undulator K Measurements Workshop Use of FEL Off-Axis Zone Plate.
David Schultz Accelerator Readiness Dec. 2, ‘08 SLAC National Accelerator Laboratory 1 Undulator Complex Status LCLS Introduction.
John N. Galayda LCLS Accelerator Readiness December 2, LCLS Overview December 2, 2008 Project Construction Status.
Lessons Learned From the First Operation of the LCLS for Users Presented by Josef Frisch For the LCLS March 14, 2010.
R. Arnold SLAC 24 June 2002 Real Photon Collaboration Conceptual Design Review Beam Monitoring Instruments.
Shielding Design for LCLS Injector Operation – Phase one
Experimental Facilities Planning
Schedule and Priorities 2018 / 2019
LCLS Instrument Development
Steps towards beam commissioning: Photon Diagnostics
Revised Commissioning Strategy
Proposed Offset Mirror System
1 Zoe Van Hoover 1 User Safety: Commissioning and Early Experiments NEH ARR User Safety: LCLS NEH Commissioning and Early Experiments.
Status Report on E-166 Undulator-Based Production of Polarized Positrons K.T. McDonald Princeton University EPAC Meeting SLAC, November 15, 2003.
Commissioning Status of the LCLS Accelerator and Undulator Systems
Stefan Moeller – XES Manager May 14, 2009
John N. Galayda – Director of LCLS Construction March 30, 2009
Risk Assessment Contingency Endgame
Installation of Photon Beam Transport to FEH
Electron Beam Systems ETC and Methodology
X-Ray Endstation Design & Management/Commissioning
X-Ray Transport, Optics, and Diagnostics WBS Alan J
Diagnostics Richard M. Bionta, LLNL April 24, 2002
Overview Pre-Beam Checkouts
AMO Early Science Capability
Transverse size and distribution of FEL x-ray radiation of the LCLS
Optics John Arthur, SLAC & William W. Craig, LLNL April 24, 2002
Experimental Program and Endstations System (WBS ) J
John Arthur – LCLS Experimental Operations
Maximum Credible Beam Event Paul Emma et al
FEE Diagnostics and Commissioning
NEH - Status Stefan Moeller.
The Transition to User Operations
Linac Diagnostics Commissioning Experience
LCLS Injector Commissioning P
Shutdown Planning & Installation Schedule
LCLS Personnel Protection System and Beam Containment System
Heinz-Dieter Nuhn – LCLS Undulator Group Leader May 14, 2009
Hal Tompkins – Photon Beam Systems Deputy May 14, 2009
LCLS Operation in 2009 Roger A. Erickson
Photon Systems Breakout Lehman Review July 11, 2007
Undulator Physics Diagnostics / Commissioning Strategy Heinz-Dieter Nuhn, SLAC / SSRL August 11, 2004 Undulator Overview FEL Parameters Diagnostics and.
Installation Status & Operational Readiness Process
XTOD Attenuator Status
X Ray Transport, Optics, and Diagnostics Overview
P. Emma, for the LCLS Commissioning Team LCLS DOE Review May 14, 2009
X-Ray Endstation Systems (XES) 2006 Schedule
LINAC System Engineering / Design Status C.E. Rago
LCLS Photon Systems Overview
Keith Kishiyama, Marty Roeben Dimitri Ryutov, John Trent and
LCLS Lehman Review February 7-9, 2005
Presentation transcript:

Hal Tompkins – Photon Beam Systems Deputy June 8, 2009 FEE Commissioning Hal Tompkins – Photon Beam Systems Deputy June 8, 2009

First beam into FEE late June/early July First beam into NEH late July Beam Schedule First beam into FEE late June/early July First beam into NEH late July First scheduled user run Sep-Dec. CD 4 goal of beam to FEH accomplished March, 2010

FEE Layout Beam Direction Solid Attenuators Gas Attenuator Thermal Sensor Beam Direction Slit Gas Detectors K-Mono 5 mm collimator Direct Imager (Scintillator) FEL Offset Mirror Systems

Interim FEE Layout

Phase 1 Commissioning Commissioning time must be shared between electron and photon halves Reliable lasing at all wavelengths has already been demonstrated B4C testing is part of commissioning Deposited power is greatest at 830 eV operation - estimated dose to B4C at ST1 is .35 eV/atom, melt dose is calculated at .63 eV/atom B4C testing in ST0 chamber took place in May - this location is 48 m from end of undulator B4C target is continuously monitored with camera at MCC for damage - log entries required on daily basis

Phase 1 Commissioning Cen. Ref.

Phase 1 commissioning (cont.) Requirements for allowing beam to FEE: FEE included in expanded SAD/ASE which is being reviewed internally at SLAC Accelerator Systems Division (ASD) responsible for operation of FEE FEE PPS certified RP survey plan based on LCLS commissioning plan Beam Authorization Sheet for FEE

Phase 1 Commissioning (cont.) Requirements for allowing beam to FEE (cont.): B4C “moveable mask” installed upstream of FEE stoppers (ST1 and ST2) Direct Imager YAG screen permanently installed in beam path C1 Collimator installed in planned location Temporary beam dump (B4C and W alloy) installed on differential pump stand Two protection ion chambers (PIC’s) downstream of C1 and two more downstream of temporary dump Air gap of 20 cm Three pairs of hutch stoppers with BTM’s active and stoppers locked closed installed in planned location C3 collimators installed in planned location Shadow wall and wall 2 window installed

Phase 1 Commissioning (cont.)

Phase 1 Commissioning (cont.) Installation in downstream half of FEE can proceed during day shift, in parallel with B4C testing in ST0 can Diagnostics and FEL commissioning can proceed during swing and owl shifts ASD will have to search and secure the FEE every day Upstream half of FEE will require RSWCF for breaking vacuum Damage to Direct Imager YAG screen requires immediate inspection of C1 and temporary beam dump Target date for beam to FEE is late June/early July C1, C3 collimators FEE PPS

Phase 1 Commissioning (cont.) Overall diagnostics commissioning plan has needed revision - nobody expected immediate lasing at 1.5 Ang. Diagnostics commissioning still begins with Direct Imager - want spontaneous radiation Open FEE stoppers - follow RP survey plan Begin with adjustable slits closed B4C apertures in attenuator rafts open Slowly open adjustable slits - verify proper slit operation Verify 25 mm x 45 mm fixed mask aperture Insert B4C apertures singly, then each raft. Raft alignment best done with FEL - be careful to keep YAG below saturation

Soft X-ray spontaneous from full undulator (calculated) As seen in Direct Imager, using 5 µm YAG

Hard X-ray spontaneous, from full undulator (calculated) As seen in Direct Imager, using 50 µm YAG

Soft X-ray FEL signal in Direct Imager As seen in Direct Imager, using 5 µm YAG Peak pixel has 160 photoelectrons / nJ of FEL

Phase 1 Commissioning (cont.) Commission gas detectors - use FEL Add nitrogen gas to detector volume Power magnet Compare APD & PMT response to changes in intensity Repeat at several different photon energies/gas pressures Commission gas attenuator - interleaved with gas detector commissioning Commission K-monochromator Transmit beam through 4 bounces (~8.172 eV) Check out quadrant photodiode Confirm Ni foil calibration of linac energy

Phase 1 Commissioning (cont.) Commission Total Energy detector Pulse energy already measured to be ~1-2 mJ by electron side with ~50% error bars This measurement is good enough to claim CD 4 goal of 106 photons/mm2-0.1%BW-pulse (though technically it was not made in the FEE) TEM should be accurate to 5-10% Pulse energy measurement is crucial for B4C testing confidence Once total energy monitor is commissioned, cross-calibrate the gas detectors and the direct imager This needs to be done at multiple energies - emphasis on the 830-1800 eV range It also needs to be done at multiple intensities - but we must protect the YAG

Beam to downstream half of FEE Phase 2 Commissioning Beam to downstream half of FEE Very useful for commissioning pop-in monitors and offset mirror systems - can commission through P3’s Will require agreement from RSO that B4C test piece in ST0 can has seen sufficient number of FEL pulses to justify confidence in B4C being “FEL-proof” Some fraction of commissioning time will continue to be spent dumping pulses into ST0 test mask FEL will terminate at hutch stoppers S1, S2, and SH1 or B4C-protected collimators

HOMS and SOMS mounts share a common design With temperature controlled to 0.01 deg, pointing stability is better than 10 nrad

HOMS: Hard x-ray Offset LCLS Offset Mirror Systems HOMS: Hard x-ray Offset Mirror System 830-2000 eV to Hutch 1 SOMS: Soft x-ray Offset Mirror System 830-2000 eV to Hutch 2

NEH Commissioning NEH beam steps Beam to NEH in late July NEH ARR June 30-July 1 AMO IRR mid-July Hutch HPS certified XFD Operations procedures in place, reviewed, and approved by SLAC 24/7 floor coordinator coverage in place Beam Line Authorization for Hutch 1 AMO beam containment plan approved by RSO Beam to NEH in late July

First beam into FEE late June/early July Summary First beam into FEE late June/early July First beam into NEH in late July First scheduled user run Sep-Dec CD 4 goal of beam to FEH March, 2010