Injector Performance Requirements Conventional Facilities Update

Slides:



Advertisements
Similar presentations
Henrik Loos LCLS FAC Meeting 27 October RF Gun Status LCLS Facility Advisory Committee Meeting October 26, 2005 Mechanical.
Advertisements

Eric Bong LCLS FAC Injector-Linac April 7, 2005 LCLS Injector/Linac Systems Update E. Bong LCLS FAC April 7, 2005 LCLS.
FAC review, 10/27 D. Schultz 1 e-Beams System Update Injector System Installation has started. Linac System Preparing for ’06 installation. Controls System.
FAC, 10/12/06 D. Schultz 1 e-Beams Systems Update Linac Injector Undulator Production MMF commissioning ARR David Schultz.
FAC, 4/20/06 D. Schultz 1 e-Beams System Update Linac System Preparing for downtime installation. Injector System Installation has started. Undulator System.
Injector RF Design Review November 3, 2004 John Schmerge, SLAC LCLS RF Gun Thermal Analysis John Schmerge, SLAC November 3,
David H. Dowell Injector RF Design November 3, LCLS Injector RF Gun: Design, Fabrication & Tuning Plans D. H. Dowell,
Eric Bong LCLS FAC Injector-Linac October 27, 2005 Injector Design / Diagnostics / Gun & Linac RF Design E. Bong LCLS FAC.
FAC, 4/16/07 D. Schultz 1 e-Beams Systems Update People ARR Linac Installation Undulator Production MMF Operations David Schultz.
C.Limborg-Deprey Beam Dynamics for RF gun November 3 rd 2004 Beam Dynamics Justification of RF Gun Modifications.
LCLS Linac System Management Linac Coherent Light Source Stanford Synchrotron Radiation Laboratory Stanford Linear Accelerator Center.
C.Limborg-Deprey Beam Dynamics Justifying L01 November 3 rd 2004 Beam Dynamics Justifications of modification of.
DUAL FEED RF GUN DESIGN FOR LCLS Liling XIAO, Zenghai LI Advanced Computations Department Stanford Linear Accelerator Center Nov , SLAC-LCLS Injector.
Eric Bong LCLS FAC Injector-Linac System October 27, 2005 Injector –Linac System Overview E. Bong LCLS FAC October 27, 2005.
Richard F Boyce Injector UpdateL0-1 Accelerator 3 November L0-1 Design, Manufacturing & Testing R. F. Boyce, SLAC.
1 Low-energy RHIC electron Cooler (LEReC) Update November 17, 2014.
David H. Dowell Injector April 29-30, 2004 LCLS Injector Overview D. H. Dowell, SLAC FAC Review April 29-30, 2004 Injector.
Before aperture After aperture Faraday Cup Trigger Photodiode Laser Energy Meter Phosphor Screen Solenoids Successful Initial X-Band Photoinjector Electron.
Cecile Limborg-Deprey Injector Commissioning September Injector Commissioning Plans C.Limborg-Deprey Gun exit measurements.
David H. Dowell RF Gun Commissioning LCLS FAC April 16, RF Gun Commissioning Experience David H. Dowell for the LCLS Injector.
Cecile Limborg-Deprey Injector October Injector Physics C.Limborg-Deprey Diagnostics and Commissioning GTL measurements.
David H. Dowell Injector Physics/Diagnostics/Gun&L0 RF April 29-30, 2004 Injector Physics / Diagnostics / Gun & L0 Linac.
Linac Front-End R&D --- Systems Integration and Meson Lab Setup
ILCTA_NML Progress at Fermilab Jerry Leibfritz September 10, 2007.
Injector Accelerator Readiness Review, 10/31/06 Henrik Loos 1 Beam Losses During LCLS Injector Phase-1 Operation Scope of phase 1 operation Operating modes.
SRF Results and Requirements Internal MLC Review Matthias Liepe1.
Low Emittance RF Gun Developments for PAL-XFEL
July LEReC Review July 2014 Low Energy RHIC electron Cooling Sergey Belomestnykh SRF and RF systems.
David H. Dowell and Friends SLAC National Accelerator Laboratory David H. Dowell and Friends SLAC National Accelerator Laboratory The LCLS Gun ICFA Beam.
Electron Source Configuration Axel Brachmann - SLAC - Jan , KEK GDE meeting International Linear Collider at Stanford Linear Accelerator Center.
ILCTA_NML Progress at Fermilab Jerry Leibfritz August 16, 2007.
PAL-XFEL Commissioning Plan ver. 1.1, August 2015 PAL-XFEL Beam Dynamics Group.
PXIE RFQ Design Overview Derun Li for PXIE RFQ Design Team Center for Beam Physics Accelerator and Fusion Research Division Lawrence Berkeley National.
Linac beam dynamics Linac dynamics : C. Bruni, S. Chancé, L. Garolfi,
PHIL: A TEST BEAMLINE AT LAL Specifications of PHIL
CLEX Building Layout, Conventional Facilities, TL2, TL2’,
by P. Musumeci and F.Tazzioli
SPARC RF gun status by P. Musumeci Review committee
DC Injector and Space Charge Simulation Status
Thermal emittance measurement Gun Spectrometer
The Cornell High Brightness Injector
Cornell Injector Performance
LCLS Injector: Introduction D. H
LCLS Linac Update Brief Overview L1 & BC1 Progress LTU & E-Dump Status Continuing Resolution Impact.
Injector –Linac Status & Schedule E. Bong LCLS FAC October 12, 2006
LCLS Gun Commissioning Status & Plans David H
LCLS Commissioning Parameters
Electron Source Configuration
Advanced Research Electron Accelerator Laboratory
Linac/BC1 Commissioning P
Injector / Linac Installation Current Status
LCLS Linac Overview E. Bong Lehman Review August 10, 2004
LCLS Commissioning P. Emma, et al
INJECTOR (WBS 1.2.1) Jym Clendenin, SLAC April 23, 2002
Linac LLP Outline LINAC Long Lead Procurements
Injector Experimental Results John Schmerge, SSRL/SLAC April 24, 2002
Maximum Credible Beam Event Paul Emma et al
LCLS Injector/Diagnostics David H. Dowell, SLAC April 24, 2002
LCLS Injector Commissioning P
LCLS Injector Configuration
LCLS Injector System Overview D. H
Linac Coherent Light Source Project Update
LCLS Commissioning Parameters
Linac Design Update P. Emma LCLS DOE Review May 11, 2005 LCLS.
Injector/Linac Design Status C. E
Injector Physics C. Limborg-Deprey, D. Dowell ,Z. Li. ,H. Loos, J
Overview of RF Gun Specifications and Technical Issues
Injector Physics C.Limborg-Deprey Feb.8th 2006
LCLS e- Beams Systems Manager
Injector/Linac RF Status
Presentation transcript:

Injector Performance Requirements Conventional Facilities Update LCLS Injector Update D. H. Dowell, SLAC FAC Review, October 12-13, 2004 Injector Performance Requirements Conventional Facilities Update Shield Wall Installed Sector 20 Alcove Title I complete Title II begun RF Design Update Drive Laser Update Injector Physics Update Summary

LCLS Injector Performance Requirements:

LCLS Injector Configuration SLAC Main Linac Beamline Transverse RF Cavity Laser Heater & Chicane 35o Bend Straight Ahead Spectrometer L0-1 & L0-2 3-m SLAC Sections Electro-Optic Diagnostic OTR Emittance Diagnostics Radiation Shield Walls RF Gun & Solenoid Load Lock Gun Diagnostics

S20 Floor Plan Cable Plant Specs Defined Title II Design Started See PRD: Conventional Facilities Specifications For the Sector 20 Alcove

RF Design Progress L0-1 Accelerator section 120 Hz Gun Dual feed RF design complete L0-1 engineering design nearly complete 120 Hz Gun Solenoid design complete RF design nearly complete Redesigned coupler holes solved pulsed heating problem Adopted racetrack geometry for full cell Held technical meetings with prospective vendors Unresolved issues: Final design for bulk cooling system Load lock deferred Decide how much SLAC vs. vendor engineering and fabrication Technical review first week of November

Dual Feed RF Gun and Solenoid Dual Feed/Racetrack Design Corrects RF Fields to Second Order Solenoid Design Includes Both Dipole and Quadrupole Field Correctors

Localized Pulsed Heating of RF Coupling Port Gun body stress in Pa Localized heating of the RF coupling port. The heat flux (watts/m2) is shown for the gun operating at 140 MV/m and 120 Hz. Total dissipated power is 3676 watts. The BNL/SLAC/UCLA gun design has a DT of 137oC/pulse at the port. The redesigned port gives a DT of 41oC/pulse. NLC designs limit DT to 50oC/pulse Pulse Heating Analysis: Zenghai Li and Liling Xiao ANSYS Analysis: John Hodgson and Nancy Yu

L0-1 Structure RF Design

L0-1 Structure RF Dual Feed

Drive Laser Update (Details in “Drive Laser Update” Presentation) Technical Review Committee Assembled C. Barty (LLNL) chairman, M. Babzien (BNL), R. Falcone (Berkeley), Y. Li (ANL) Review Held July 21, 2004 at SLAC Committee involved in procurement process Laser baseline design is diode-pumped Ti:Sapphire based upon extensive discussions with vendors Request for Proposal ready to submit to vendors Laser pulse shaping studies underway at BNL/DUVFEL Developing collaboration with LLNL on both near term and long term laser needs

Injector Physics, see breakout Diagnostics and Commissioning Gun measurements Accurate thermal evaluation Gun spectrometer 6D beam characterization at 135 MeV Simulations Low Charge tunings RF studies L01 dual feed, racetrack shape necessary RF gun dual feed, racetrack shape in full cell mode 0 studies 8MHz mode separation better klystron pulse shaped 8% modulation Name r 80  (80  5%) Nom.,1nC,10ps 1.2 mm 0.9 mrad 2.5 1 nC, 17.5 ps 0.85 0.75 1.5 0.2nC,10ps 0.39 0.38 0.2nC,5ps 0.42 0.37 5

Injector Schedule Schedule Coordinated with Shutdowns Over a Year for Injector Commissioning Injector Not on Project Critical Path

Summary and Conclusions Conventional facilities at S20 defined to support Title II Facilities for two drive lasers RF design of 120 Hz gun nearly complete Solenoid design with dipole and quadrupole correctors finished Pulsed heating solved Dual RF feed + racetrack full cell L0-1 accelerator section RF design finished Engineering design in progress RF design review first week of November Beamline components (magnets) being designed Drive laser specifications defined in Request for Proposal