MICE PM Report Progress with the Infrastructure A few problems

Slides:



Advertisements
Similar presentations
1 UK Project Alan Grant, STFC. Finance How savings are made Update on stepIV position Milestones Critical Path - stepIV Concerns 2.
Advertisements

Project Managers Update Roy Preece Particle Physics Department, STFC MICE Video Conference, 18 th September 2014.
1 MICE CM31 Key schedule drivers for Step IV Schedule table Milestone summary Comment on Step V Step VI Andy Nichols, STFC, 3/11/11.
MOM Report Ray Gamet MICE Operations Manager University of Liverpool MICO 18 th May 2009.
June 26, 2009TLH, NFMCC Friday Meeting1 MICE Updates MICE News Overview ISIS and MICE Schedules DAQ Review Spectrometer Update Aspirational Schedule Terry.
1 MICE Video Conference Installations to date Future installation work Plans for May shutdown MICO organisation Use of Technical Board.
MOM Report Paul Soler MICE Operations Manager University of Glasgow MICO April 20, 2009.
1 MICE PM Report General Update –Phase I civil engineering –R5.2 in June –Phase II design work –Phase II hardware –A few questions –Schedule, milestones.
Spectrometer Solenoid Design and Procurement Review Steve Virostek Mike Green Mike Zisman Lawrence Berkeley National Lab MICE Collaboration Meeting October.
Paul drumm; 1 st December 2004; PM&TB Report 1 Project Management & Technical Board Reports.
1 Project Manager Report Andy Nichols, STFC – RAL MICE Collaboration Meeting, Harbin, 13-17th January 2009.
Spectrometer Solenoid Fabrication Update Steve Virostek Lawrence Berkeley National Lab MICE CM23 at ICST, Harbin January 14, 2009.
1 MICE PM Report Installations to date Future installation work Preparations for Phase Two Target status MICE Video Conference, 22nd May, 2008.
MOM Report. Shield Wall – Gone Before During After 2.
Alain Blondel MICE VC 9 september 2010 Spokesmouse report o VC 22nd April o 12th-13th May posters for IPAC (Vittorio Palladino) o VC 20th May o IPAC May.
MOM Report Paul Soler MICE Operations Manager University of Glasgow MICO May 5, 2009.
1 Status of infrastructure MICE Video Conference, August 17, 2005 Yury Ivanyushenkov Applied Science Division, Engineering and Instrumentation Department.
1 Implications Of Infrastructure Build The Infrastructure Project is bigger than anyone thought, but now it’s understood The cost was underestimated, but.
Update Hardware for conductive cooling of the quench resistors has been fabricated at LBNL. Preparation for installation to start this week. Installation.
1 Summary of MICE beamline & hall installations This is a very rough summary of the progress since mid-December Richard Apsimon & Andy Nichols MICO meeting.
Alan Grant OsC 30/4/ UK Project Finance & Schedule.
1 Project Manager Report Andy Nichols, STFC MICE Collaboration Meeting, RAL, June 2009.
1 MICE PM Report Phase One installations to date Phase One remaining items Progress with Phase Two Phase Two planning sequence Worries Don’t have time.
1 MICE Video Coference Project Manager Report Contents: Technical organisation of project Target and upstream beamline Muon beamline Infrastructure and.
1 MICE CM32 Summary Scheduling and planning; aims for this year Schedule update Main schedule drivers Keeping us on schedule Comment on Steps V & VI Detail.
1 Hall & Beamline Installation Richard Apsimon, Andy Nichols, Willie Spensley MICE Collaboration Meeting, th Feb 2008.
1 Technical Co-ordination, Phase One The shared post of PM/TC has worked quite well Six months ago there was much for us to learn:  Revised the WBS 
1 MICE - INFRASTRUCTURE MICO meeting 7 th February 2008 Tim Hayler.
MICE: overview K. Long, 18 March, Contents ► Introduction ► Beam line ► Infrastructure ► MICE steps ► Phase II (comment) ► Conclusions.
Infrastructure Update As at 11 th March 2009 Remaining four plates now fitted to North shield wall North & South walls and all galleries are considered.
1 MICE PM Report Phase One installations to date Problems with target & decay solenoid and rolling platforms Phase One remaining items Progress with Phase.
1 UK PM Report Costs & Schedule Alan Grant, STFC.
1 MICE PM Report Completion of Infrastructure Target, solenoids Phase Two planning & schedule Non-MICE costs Staffing & visitors Don’t have time for a.
Project manager report paul drumm CM16 October 2006.
1 MICE CM28 PM Report Progress since CM27 Schedule, dates, milestones Electrical substation Visiting RAL Andy Nichols, STFC 4 th October 2010.
1 MICE CMPB Contents: Progress to date Project management things Plans for the May shutdown Steps towards Phase Two Problems and open issues summary Andy.
RSLR mtg 28/3/2014 RLSR mtg Alan Grant. 2 RLSR mtg 28/3/ MICE Finances - Forward Look.
The status of the construction of MICE Step IV K. Long, on behalf of the MICE collaboration.
Schedule and Work We are moving into a very intensive 4 months with a lot of work to be carried out Electrical services to the devices – after the South.
1 Project Manager Report Andy Nichols, STFC – RAL MICE Collaboration Meeting, RAL, nd October 2008.
1 Project Manager Report Andy Nichols, STFC – RAL MICE Collaboration Meeting, DL, 4 th -7 th June 2008.
Status of the MICE Project & Dashboard MICE Project Board 14 th November 2013 Roy Preece.
1 MICE Hall construction status Richard Apsimon MICE VC meeting 29th Nov 2007.
MICE FAC Alain Blondel 21 september   MICE The International Muon Ionization Cooling Experiment BRIEF STATUS OF MICE.
MICE VC Alain Blondel 1 MICE NEWS MICE VC 161 Agenda Overall schedule Magnetic field mitigation review Status of things.
1 MICE PM report Target News Outcome of Spectrometer Solenoid Review New plans for Steps II & III RF Power news MICE CMPB, 4th December, 2009.
1 MICE PM Report Summary since CM21 Decay solenoid Infrastructure progress Step One Installation Worries MICE Video Conference, 19 th June, 2008.
1 MICE Beamline Installation, status & plans Contents: Upstream & Target, BPM Decay solenoid DSA, D2, Q4,5,6 cKOV support Q7,8,9 Open issues & concerns.
1 MICE CM27 PM Report Re-defining the UK project this FY Schedule things Apologies and accommodation Andy Nichols, STFC 7 th July, 2010.
MICE Project Report Alan Bross (for Paul Drumm). Project Issues ● Key dates: – ISIS Synchrotron start-up scheduled for 1st August ● Shielded area around.
CM27 – 8 th July 2010 LH2 System Progress and Future Plans M Hills T Bradshaw M Courthold I Mullacrane P Warburton.
Pre-CM33 schedule planning SuperMICO meeting, June 6th Motivation: For all of us to understand the main drivers behind the top-level MICE schedule So that.
OsC mtg 24/4/2014 OsC mtg Alan Grant. 2 OsC mtg 24/4/ MICE Finances - Forward Look.
1 MICE PM Report Phase One installations to date Some problems with target & Decay Solenoid Phase One remaining items, schedule & milestones Progress with.
1 UK PM Report Costs & Schedule Alan Grant, STFC.
1 MICE PM Report General Update –Phase I nearing completion –MICE Power –Actions for Decay solenoid & target –Follow-ups from last VC –Conclusions MICE.
1 MICE PM Report Infrastructure/integration progress Electrical work AFC, diffuser, etc Help with project control & staffing issues Worries & problems.
MICE CM20 Alain Blondel 10 February The International Muon Ionization Cooling Experiment MICE CM20 Spokesmouse remarks.
1 Project Infrastructure for steps I-III Tim Hayler, STFC – RAL MICE Collaboration Meeting, RAL, nd October 2008.
MICE CM23 Introduction and Meeting Goals Michael S. Zisman Center for Beam Physics Accelerator & Fusion Research Division Lawrence Berkeley National Laboratory.
OsC mtg 15/10/2014 MICE Step IV Alan Grant. Content Step IV – Construction Status – Finances – Schedule – Risks – Summary 2.
1 UK Project Roy Preece – STFC Alan Grant, STFC. Finance Staffing Update on stepIV position Milestones Critical Path – stepIV Magnetic field mitigation.
1 MICE PM Report Phase One installations to date Phase One remaining items Progress with Phase Two Worries Don’t have time for a detailed status report,
Schedule to completion, Risk and Critical Interfaces Roy Preece STFC RAL RLSR 16 th April 2015.
Schedule and Milestones Roy Preece STFC RAL FAC 17 th April 2015.
1 UK Project Finance & Schedule. Overview Finance  Budget Setting 2013/14  June Finance  Forward look to complete stepVI Schedule  Overview 2.
MICE CM28 Engineering Session Summary (On behalf of Wing)
MICE CM31 Schedule summary
Presentation transcript:

MICE PM Report Progress with the Infrastructure A few problems Planning Phase Two Visitor arrangements MICE Video Conference, 18th September, 2008

Progress with the Infrastructure August and September have been good months! South Shield wall complete, floor plates laid North Wall support structure is about half done Steel plate order is fully delivered and contractual hiccups solved The mound excavation is done and vacuum service ducts installed All infrastructure design work is finished DSA PPS Installation is working Tim & Willie have an aggressive but believable plan for parallel work in Hall – brings civil engineering to close by 24th November This defines the earliest date the tracker readout can be integrated in the Hall

A few problems Decay solenoid: Plans: Summary only, see Mike C’s talk later Various problems with Linde fridge now fixed Coils 1-5 (upstream) confirmed to be superconducting Coils 6-10 (downstream) non-superconducting Plans: Remove end cap of cryostat October (20th-30th) shutdown for detailed fault diagnosis Withdraw half cold mass to expose downstream coils in December/Jan shutdown (18th Dec – 22nd Jan 09) Presumption is that we do not need to dismantle shield wall Tim & Mike are working on detailed plan

A few problems Target: Plans: Again a summary – Chris’s talk later: ISIS target remains reliable, but we only have ~ 60K cycles left of our original agreement Two demonstrator targets have failed, actuator shorted and bearings/shaft seized badly Plans: Demonstrator problems need to be understood and fixed methodically New design and parts need to be made made, on & offline running programme needs to be re-defined and run to enable operable target for Decay solenoid start up (End Jan 2009) – it’s crucial this work has a proper engineering basis But we must not exclude a ground-up re-design of the target project – but the UK itself cannot pay for this

A few problems Spectrometer Solenoid Plans and schedule: See Mike Z’s talk later Magnet no.1 is complete and working but has problems with rad shield and vent pipework Plans and schedule: Shift priority to magnet no.2 Improve thermal path to rad shield and improve vent tubes Finish early November Then field map and shipment – eight weeks Integration at RAL – six weeks So we’ll be running in mid Feb ’09 Magnet no.1 follows these steps but eight weeks behind Even if we postpone FNAL field map, it’s hard to believe we’ll be running this year

Planning for Phase Two Blondel, Long, Nichols, Zisman met in early July Discussed the shape of the Phase Two project given the constraints of UK funding It looks like we have a four-year project AN is working (but not very quickly) on both cost and technically-limited versions of the overall schedule Reviews of major subsystems are planned at & around CM in October Milestones from these are vital input to the project plan

Visitor arrangements MICE Liaison/admin officer, Rosie Hayes, will start in early November Will be located in R1, second floor Aiming to establish office in R1 for visitor use also Rosie will help with: Induction Accommodation Travel Safety Etc.