ESAC Review February 2013 CEA Saclay

Slides:



Advertisements
Similar presentations
CIEMAT technological contributions to linear colliders Fernando ToralGandía, 3/12/2005.
Advertisements

EuCARD-HFM ESAC review of the high field dipole design, 20/01/2011, Maria Durante, 1/40 EuCARD-HFM ESAC Review of the high field dipole design Fabrication.
ILC Main Linac Superconducting Cryogen Free Splittable Quadrupole Progress Report V. Kashikhin for Superconducting Magnet Team.
Coil working group video-meeting P. Ferracin, J. C. Perez, S. Izquierdo Bermudez, X. Sarasola February 4th, 2014.
11 T Dipole informal coil and assembly readiness review Long coil and fabrication tooling development status and plans September 22 nd, 2013 – F. Savary.
MQXFS Assembly Procedure J.C Perez 4 th Joint HiLumi LHC-LARP Annual Meeting November 17-21, 2014 KEK, Tsukuba N. Bourcey, D. Cheng, B. Favrat, H. Felice,
Eucard WP 7.3 HFM Winding and tooling tests Insulation choice F.Rondeaux /01/2011 Dipole design review- II-8 Winding and tooling tests – insulation.
Coil working group video-meeting P. Ferracin, J. C. Perez, S. Izquierdo Bermudez, X. Sarasola January 29, 2014.
SMC Plans for new SMCs for Fresca2 program J.C. Perez EUCARD-WP7-HFM Short Model Coil review 12 December 2011.
Eucard-WP7-HFM 10 th Collaboration Meeting at LASA Milano Status on SMC & RMC Models J.C Perez on behalf of SMC/RMC collaboration team.
FReSCa2 Technical Review, 9 th June 2015, CEA Saclay FReSCa2 Technical Review June 2015 CEA Saclay J.C Perez on behalf of Fresca2 collaboration team.
Development of the EuCARD Nb 3 Sn Dipole Magnet FRESCA2 P. Ferracin, M. Devaux, M. Durante, P. Fazilleau, P. Fessia, P. Manil, A. Milanese, J. E. Munoz.
SC magnet developments at CEA/Saclay Maria Durante Hélène Felice CEA Saclay DSM/DAPNIA/SACM/LEAS.
NED Project P. MANIL – CEA/IRFU/SIS – Short Model Coils meeting #18 – 25/01/2008 – slide 1/18 SHORT MODEL COILS PROGRAM SMC meeting #18 Pierre MANIL CEA/IRFU/SIS.
11 T Nb3Sn Demonstrator Dipole R&D Strategy and Status
11 T Dipole Experience M. Karppinen CERN TE-MSC On behalf of CERN-FNAL project teams The HiLumi LHC Design Study (a sub-system of HL-LHC) is co-funded.
Eucard-WP7-HFM 9 th Collaboration Meeting at Warsaw University of Technology Status on SMC & RMC Models J.C Perez on behalf of SMC collaboration team.
HQ01e CERN test preparation update CERN Team: H. Bajas, M. Bajko, A. Chiuchiolo, G. Deferne, O. Dunkle, J. Feuvrier, P. Ferracin, L. Fiscarelli, F. Flamand,
Fred Nobrega, Nikolai Andreev 21 September, 2015.
October/7/2011 J.C. Perez TE-MSC-MDT EuCARD WP7-HFM Collaboration Meeting (Geneva) SMC E U CARD WP7 HFM S TATUS UPDATE MEETING O CTOBER 2011 J.C. Perez.
S. Caspi, LBNL HQ Progress and Schedule Shlomo Caspi LBNL LARP Collaboration Meeting – CM13 Port Jefferson November 4-6, 2009.
Outline: Main characteristics of the FRESCA2 cable Main characteristics of the strand Strand stability, an issue to avoid magnet quench at low field Procurement.
Superconducting Magnet Group Superconducting magnet development for ex-situ NMR LDRD 2003 Paolo Ferracin, Scott Bartlett 03/31/2003.
Subscale quadrupole (SQ) series Paolo Ferracin LARP DoE Review FNAL June 12-14, 2006.
MQXFS Assembly Procedure J.C Perez N. Bourcey, B. Favrat, P. Ferracin, Ph. Grosclaude, M. Juchno, L. Lambert, P. Moyret, J. Parrilla Leal, N. Peray, T.
Magnet design, final parameters Paolo Ferracin and Attilio Milanese EuCARD ESAC review for the FRESCA2 dipole CERN March, 2012.
Helene Felice HQ Test Results Review Thursday December 16 th Overview of HQ coils and Magnet.
FRESCA2 Technical Meeting 5-Validation of coil winding with Cu coils Françoise Rondeaux 09/06/ CEA-Irfu-SACM-LEAS - 5-Rondeaux- FRESCA2 Technical.
Dipole review, January Dipole design review: outlines of talks Gijs de Rijk, Francois Kircher and Jean- Michel Rifflet.
LARP Collaboration Meeting Racetrack Coil Fabrication
11 T Dipole Project CERN Status M. Karppinen 11 T Management meeting 1 July 2013.
11 T Dipole Status May 2012 M. Karppinen CERN TE-MSC On behalf of CERN-FNAL collaboration.
MQXFB design, assembly plans & tooling at CERN J.C Perez On behalf of MQXF collaboration team MQXF Workshop on Structure, Alignment and Electrical QA.
ESAC R EVIEW OF THE HIGH FIELD DIPOLE DESIGN R EACTION O VEN, S PLICING AND IMPREGNATION M ARCH 2012 FOR E U CARD-WP7-HFM J.C. Perez on behalf of SMC collaboration.
CERN/CEA Collaboration agreement No. KE2275/TE WP5 – HTS insert Meeting 04/09/2015.
MQXFB Prototype structure and plans at CERN J.C Perez On behalf on MQXF collaboration team Joint HiLumi-LARP Meeting & 24 th LARP Collaboration Meeting.
KEK-CEA Superconducting Magnet Co-operation Program The FJPPL workshop LAPP, Annecy-Le-Vieux (France), June LHC-3 Superconducting Magnets.
2 nd LARP / HiLumi Collaboration Mtg, May 9, 2012LHQ Goals and Status – G. Ambrosio 11 LHQ Goals and Status Giorgio Ambrosio Fermilab 2 nd LARP / HiLumi.
3 rd ESAC Review, 27 th February to 1 st March 2013, CEA Saclay Fresca2 Dipole Structure Assembly J.C Perez on behalf of Fresca2 collaboration team.
CERN QXF Conductor Procurement and Cable R&D A.Ballarino, B. Bordini and L. Oberli CERN, TE-MSC-SCD LARP Meeting, Napa, 9 April 2013.
TE-MSC-MDT. FTEC Follow-Up Meeting Juan Carlos Perez TE-MSC-MDT Jose Ferradas TE-MSC-MDT 28/04/2016.
EuCARD-WP7-HFM meeting 15 November 2011 Status of construction of FRESCA2 dummy coil assembly Attilio Milanese, Juan Carlos Perez.
P. Ferracin on behalf of the MQXF collaboration
Responses to the recommendations of the first ESAC dipole review
Hardware Challenges and Limitations
QXF Coil Fabrication & Tooling Reaction / Impregnation
TQS Overview and recent progress
Status of the manufacturing process of a Nb3Sn wiggler prototype
11 T Dipole Integration & Plans M. Karppinen
HQ Mirror Assembly R. Bossert
CSP 25th November 2010 Technical agreement number 3: overview
TQS Structure Design and Modeling
11T Dipole – Single Aperture 2m Model
ERMC/RMM activities May 2017
FCC 16 T dipole 4578 dipoles + 5 % spares : 4807 dipole magnets
J.C. Perez on behalf of SMC collaboration team J.C. Perez
CERN Conductor and Cable Development for the 11T Dipole
CEA KE 2775 progress meeting WP3 – FRESCA 2 Magnet
FRESCA2 Update on the dipole design and new calculations
Mechanical stability and QXF coil winding
P. Ferracin and G. Ambrosio
the MDP High Field Dipole Demonstrator
Analytical Cost Model (16 T dipole)
Analytical Cost Model (16 T dipole)
SMC Design overview of the construction and project issues
Introduction to the technical content The Q4 magnet (MQYY) for HL-LHC
CEA Nb3Sn quadrupole magnet : test results and future
Paolo Ferracin, Giorgio Ambrosio
MQXF updates P. Ferracin October 9th, 2014.
MQXF coil cross-section status
Presentation transcript:

ESAC Review February 2013 CEA Saclay Fresca2 Dipole Reaction, Instrumentation, Impregnation RMC project status J.C Perez on behalf of Fresca2 collaboration team

Juan Carlos Perez TE-MSC Outline Fresca2 Heat treatment mold and reaction furnace Splicing and instrumentation Impregnation mold and impregnation system Coil assembly procedure and tooling Coils interconnection Conclusions RMC RMC project overview Juan Carlos Perez TE-MSC February 27th 2013

Fresca2 heat treatment mold After winding operation @ CEA the coil will be closed in its reaction mold and shipped to CERN for heat treatment. After reaction, the top part of the mold will be opened to allow Nb3Sn/NbTi splicing and coil instrumentation. The instrumented coil will be moved to its impregnation mold*. Juan Carlos Perez TE-MSC *Reaction and impregnation molds have been design to have inter-exchangeable parts. February 27th 2013

Heat treatment furnace Juan Carlos Perez TE-MSC The heat treatment furnace ordered to GERO has been fully commissioned at CERN Several runs have been performed using Cu coils to precisely tune the temperature over-shoot and the time of the plateau The first layer 3-4 copper coil will be used to setup the oven parameters to treat RRP as well as PIT conductor February 27th 2013

Juan Carlos Perez TE-MSC Fresca2 splices Nb3SnCoil Rail Nb3Sn/ NbTi Splice Insulating plate NbTi Lead Nb3Sn Cable End Shoe Filler piece Copper stabilizer Juan Carlos Perez TE-MSC Presented in December 2011 February 27th 2013

Fresca2 instrumentation Each double pancake will be equipped with 2 traces Dedicated traces have been designed and are being produced at CERN (first pair to be installed on the copper coil in March 2013) 50 μm thick Kapton® sheets Heater strip 25 μm thick Wiggling geometry: 12 mm width X 3.1 m long (370 cm2) R≈ 5.2 Ω, I≈60 A, V≈ 310 V  Power deposition 50 W/cm2 (125 W/mm3) Capacitor of 10 mF, discharge 480 J with t =52 ms  60 K in 1 ms (adiabatic approximation) Each coil layer will be protected by 2 independent quench-heater circuits Voltages across the coil will be monitored thanks to 10 Vtaps per side Juan Carlos Perez TE-MSC February 27th 2013

Juan Carlos Perez TE-MSC Impregnation system The acceptance tests for the new vacuum impregnation tank has been held in Spain in January 2013 The system is being installed in 927 laboratory and the commissioning @ CERN will start on second week of March 2013 Commissioning in Spain Assembly at CERN Juan Carlos Perez TE-MSC February 27th 2013

Juan Carlos Perez TE-MSC Impregnation mold Juan Carlos Perez TE-MSC The order to fabricate the mold for layer 3-4, has been placed. Delivery scheduled for April 2013. February 27th 2013 Courtesy of J.F. Millot

Coils Assembly procedure Coil layer 1-2 Coil layer 3-4 Fiber glass cloth filler Juan Carlos Perez TE-MSC Presented in December 2011 February 27th 2013

Juan Carlos Perez TE-MSC Gap impregnation (1/2) 2 facing surfaces of the coils will be mold released Gap between coils will be filled with 0.9 mm fiber glass cloth Impregnation of the fiber glass using the coils as cavity This will guarantee a perfect contact between the 2 coils This technique will allow to separate the coils in case of failure of one coil Juan Carlos Perez TE-MSC Presented in December 2011 February 27th 2013

Juan Carlos Perez TE-MSC Gap impregnation (2/2) Impregnation tests using a fake mold with 1 mm gap have been performed (as recommended by the committee during the last review) Gap between plates filled with 3 sheets 0.25 mm thick fiber glass cloth Impregnation of the fiber glass using MY 750 & Jeffamine D400 Tests performed at CERN polymer laboratory confirm the feasibility Juan Carlos Perez TE-MSC February 27th 2013

Coil pack assembly steps Vertical pads assembly Stacking coils and horizontal pads Coil lifting and rotation Juan Carlos Perez TE-MSC Coil pack Coil pack rotation Rotation tooling still to be defined and produced February 27th 2013 Presented in December 2011

Lifting tools for coil handling Juan Carlos Perez TE-MSC The fabrication of the lifting tools has been out-sourced to a French company The delivery of all remaining lifting tooling, CE certified, is expected in March 2013 February 27th 2013

Fresca2 Interconnection Juan Carlos Perez TE-MSC Presented in December 2011 February 27th 2013

Juan Carlos Perez TE-MSC Conclusions The reaction furnace is operational The vacuum impregnation system will be commissioned in March Impregnation mold has been ordered. Delivery due for April 2013 The first prototypes of traces will be delivered in March 2013 All dedicated lifting tools to handled the coils will be operational in April The copper coil will be used to validate all fabrication steps Juan Carlos Perez TE-MSC February 27th 2013

Juan Carlos Perez TE-MSC RMC Juan Carlos Perez TE-MSC February 27th 2013

Juan Carlos Perez TE-MSC From SMC to RMC towards FRESCA2 SMC RMC FRESCA2 Juan Carlos Perez TE-MSC RMC goals: test FRESCA2 cable and FRESCA2-type coils in realistic cond. Constraints Layer jump similar to FRESCA2 Power supply limit ~20 kA Magnet OD: 570 mm February 27th 2013 Presented in December 2011

Juan Carlos Perez TE-MSC RMC coil design Same design as SMC 2 end spacers 33 turns (like FRESCA2) FRESCA2-type layer jump As a result Straight section: 300 mm 150 mm in SMC Coil length: 820 mm 500 mm in SMC 96 m of cable per coil 4.0 km of strand RMC coil Juan Carlos Perez TE-MSC FRESCA2 coil Presented in December 2011 February 27th 2013

Juan Carlos Perez TE-MSC RMC magnet design RMC configuration 2 RMC coils Iss (1.9 K) = 18.3 kA Below power supply limit Bpeak = 16.0 T Significantly higher forces From 2.2 MN/m in SMC to 5.4 MN/m New structure required Thicker shell, new yoke design, larger bladders, larger axial rods RMC Juan Carlos Perez TE-MSC Presented in December 2011 February 27th 2013

RMC 1 double pancake VS. 2 double pancakes Juan Carlos Perez TE-MSC Still possible to test individual coils up to 20 kA Corresponding to about 93% of Iss @ 4.2 K February 27th 2013 Presented in December 2011

Juan Carlos Perez TE-MSC RMC exploded view Horizontal Pad Nb3Sn Coil Electrical connexion box Juan Carlos Perez TE-MSC Vertical Pad Laminated Yoke Aluminium Shell Longitudinal Rods February 27th 2013

RMC structure fabrication Rolled AL 7175 cylinder production in Fr (Forgital) Juan Carlos Perez TE-MSC All structure components machined in Spain and delivered at CERN 4th week of February February 27th 2013

Coil components and molds Juan Carlos Perez TE-MSC Coils components delivered in June 2012 Plasma coating in July 2012 Reaction and impregnation molds delivered in August First winding in September 2012 using Fresca2 type copper cable with 66 Tex braided insulation February 27th 2013

RMC copper coil winding Layer jump Fresca2 type Winding first layer Winding second layer Juan Carlos Perez TE-MSC Al2O3 Plasma coated spacers Winding Completed Reaction mold closed February 27th 2013

RMC copper coil Instrumentation Juan Carlos Perez TE-MSC The coil has been reacted in November 2012 in the furnace used for SMC coils The copper coil will be used to test and validate tooling and procedures The coil will be instrumented to validate the traces design The splicing procedure, Fresca2 type, will be validated The coil will be impregnated in the new vacuum impregnation system February 27th 2013

First RMC Nb3Sn coil winding Juan Carlos Perez TE-MSC The first Nb3Sn RMC coil has been wound in January 2013 February 27th 2013

Juan Carlos Perez TE-MSC RMC Nb3Sn coil reaction Juan Carlos Perez TE-MSC The Nb3Sn coil will be reacted in the new reaction furnace in March 2013* * O2 analyser failure in February (waiting for repair) February 27th 2013

Juan Carlos Perez TE-MSC Some relevant dates RMC project presented to ESAC reviewers at CERN December 2011 End of magnetic and mechanical computation and Start design work with drawing office February 2012 Launch price enquiry for production of components Mai 2012 Coil components delivered to CERN and sent for plasma coating June 2012 Reaction and impregnation mold delivered. Order placed for structure components July 2012 Winding of first copper coil September 2012 Heat treatment of first copper coil November 2012 Winding of first Nb3Sn coil January 2013 Reaction of first Nb3Sn coil (O2 analyser failure). Mechanical structure delivery. February 2013 Instrumentation of first Nb3Sn coil. March 2013 Impregnation of first Nb3Sn coil. First mechanical assembly using Al dummy coils April 2013 First Magnet assembly with one Nb3Sn coil July 2013 First assembly with single coil configuration to be delivered to SM18 August/September 2013 Juan Carlos Perez TE-MSC February 27th 2013

Juan Carlos Perez TE-MSC Conclusion Shell, rods and aluminium dummy coils will be instrumented with strain gauges First structure mechanical assembly scheduled for April-Mai 2013 Copper coil will be used to validate coil fabrication procedures First Nb3Sn coil expected in May 2013 Cold powering test expected end of summer 2013 around 18 months after quick-off meeting of the project (limited resources) First RMC results will be on time to be used for Fresca2 project Juan Carlos Perez TE-MSC February 27th 2013

Juan Carlos Perez TE-MSC Collaboration team CEA/Saclay: M. Devaux, M. Durante, P. Manil, J.F. Millot, J.M. Rifflet, F. Rondeaux ….. CERN: H. Bajas, M. Bajko, S. Clement, P. Ferracin, J. Feuvrier, E. Fornasiere, R. Gauthier, M. Guinchard, G. de Rijk, J. Humbert, A. Milanese, J. E. Muñoz Garcia, L. Oberli, T. Sahner, M. Timmins, G. Villiger , TE/MSC-MDT Section and many others … Juan Carlos Perez TE-MSC Thanks for your attention February 27th 2013

TE-MSC-MDT