Presentation is loading. Please wait.

Presentation is loading. Please wait.

FCC 16 T dipole 4578 dipoles + 5 % spares : 4807 dipole magnets

Similar presentations


Presentation on theme: "FCC 16 T dipole 4578 dipoles + 5 % spares : 4807 dipole magnets"— Presentation transcript:

1 FCC 16T dipoles Analysis of magnet assembly cost drivers update 25/04/2017

2 FCC 16 T dipole 4578 dipoles + 5 % spares : 4807 dipole magnets
16T nominal field; 14.3 m long 7.5 years production Training and pre-series phases : 18 months Start up phase : 12 months Series fabrication : 5 years means 962 magnets/year over 5 years full rate production 20 magnets/week 4 companies  5 magnets/week, 1 magnet/day, but for cost model we will consider as if one single company had to produce all the magnets

3 FCC 16 T dipole – design options
To be updated For all configurations 2 double layer coils / pole 8 double layer coils / magnet Cosintheta configuration Several wedges Coil dimensions (v 16T-22b-37-optd7f8) : 110 x 55 mm² 170 x 85 mm² Block configuration Few wedges (in the ends) Need for High Field splices Coil dimensions (v19ar): 135 x 70 mm²

4 Assembly steps x nb operations/magnet
Coil Winding x 8 Coil Heat-treatment x 8 Internal HF splices (only block graded coils) x 16 Transfert from reaction fixture to impregnation mold x 8 Splices preparation x 2 x 8 Coil Instrumentation x 8 Coil Impregnation x 8 Control measurements x 8 Coil pack assembly x 2 Structure assembly (+ Splices) x 2 Cold mass assembly x 1

5 Coil winding It covers:
Winding preparation (cable, tools, coil parts, ..) Winding itself. Each coil is made of two layers , wound the one after the other, with no internal splices Positioning and closing of the reaction fixture (including cable ends supports) around the winding Cosinetheta vs block : 3 times longer winding Curing of binder : 1 day per layer Min 2 weeks for one coil MQXF : 3 weeks for one coil LHC dipoles : For one layer : 2 shifts, 1 week + curing For one coil (2 layers) : 4 shifts, 1 week  we will consider 2 weeks, 1 shifts for full rate production

6 Coil winding - tools Winding machine Beam + Mandrel
Winding reels 1 and 2 Lathe for cable preparation Guiding tools Handling tools Estimated cost for a winding machine, 15 m long : 300 kCHF

7 Coil Heat Treatment Typical Heat Treatment lasts 2 weeks It covers :
Positioning of reaction fixture(s) into furnace Furnace preparation, pumping, « rinsing », filling with inert gaz Reaction cycle RRP FRESCA2 cable : 7 days + cooldown from 650°C PIT FRESCA2 cable : 10 days + cooldown from 650°C Longer heat treatments for IT strands Reaction fixture(s) extraction from furnace 20 magnets/week 8 double layer coils per magnet 160 coils heat treated/week

8 Coil Heat Treatment - Tools
Reaction fixtures (nb equal to 2 x nb of coils/furnace) Handling tool Furnace(s) Tool for Insertion into furnace

9 Coil Heat Treatment – Furnace 1/2
160 coils/week 2 weeks Heat Treatment If one coil = 1 furnace  320 furnaces are needed If 1 furnace : 1 MCHF  320 MCHF/4807 magnets  67 kCHF/magnet Or big furnaces, with more than one coil heat treated at the same time Température homogeneity should not be an issue Heating parts could be uniformely distributed inside the furnace 4 coils/HT  80 furnaces, 1.5 MCHF each  25 kCHF/magnet up to 20 coils /HT, 5MCHF furnace ?  17 kCHF/magnet Risk analysis needed : 4 coils vs 2 ? 20 coils vs 4 ?

10 Coil Heat Treatment – Furnace 2/2
Inert Gaz furnace vs Vacuum furnace : 4 times cheaper The possibility of using cheaper nitrogen gaz instead of argon should be considered, even if Nitrogen is less inert than Argon.

11 Heat Treatment  Impregnation
Time for transfert from reaction fixture to impregnation mold should not be neglected : Remove all the screws / open reaction fixture (hundreds of screws !) Replace upper part of reaction fixture with upper part of impregnation mold Fix the two parts together Rotate Remove all the screws Replace lower part of reaction fixture by lower part impregnation mold 11 T : 3 weeks (with splices and instrumentation) Tools needed to handle, rotate, tilt, close/unclose fixtures: Tables Rotation tool Handling tool

12 Splices High Field Splices
Needed only for block configuration, graded coils Nb3Sn/Nb3Sn splices between high field and low field regions Thermal diffusion splices or classical SnAg solder splices Nb3Sn / NbTi splices For all coil configurations, at each end of the cable It covers : Reaction parts replacement impregnation Half a day for one splice NbTi / NbTi external splices Assembly of coils in a pole Assembly of poles in apertures (after structure assembly) It can be done once the assembly done in a parallel line (not on critical path)

13 Coil instrumentation During transfert from reaction to impregnation fixtures In // to Nb3Sn / NbTi splices 11 T : 3 weeks (with transfert and splices) MQXF : 1 week We will consider 2 weeks for Coil transfert from reaction to impregnation fixtures Nb3Sn/NbTi splices (+ HF splices if needed) Coil instrumentation

14 Coil impregnation It covers:
Mold preparation (mold closing, sealing, impregnation circuit preparation, ..) : 1 day Pumping, degazing at around 100°C : from 2 to 5 days (cfd Oxford) Filling with resine : 1 day Resin curing cycle : 2 days Mold opening, coil extraction Coil finishing It lasts 1 to 2 weeks for one coil CERN: Building 180 (8 m long coils) : 3 weeks Building 927 (short models) : 1.5 weeks we will consider 1 full week, 1 shift with no need for operators during pumping phase (week-end…)

15 Coil impregnation - resin
FRESCA2, EuCARD2 reference : CTD-101-K 1 Kit 5 gallons, 35 kg cost is 2kCHF, but there are cost savings for increased volumes The resin has a shelf life of 1 year from date of manufacture Resin density around 1 g/cc Needed resin in a coil is quite small but for one impregnation, up to 4 times more should be prepared and injected in the impregnation circuit to allow to put pressure (3-4 bars) inside the mold MQXF, 11T : 1.5 kg needed inside a coil but 6 kg prepared for each imp.

16 Coil impregnation - tools
Impregnation mold Impregnation circuit Heating system Autoclave or Vacuum chamber ? At CERN: Vaccum chamber building 180 : 1M€ Vacuum chamber « standard » : k€

17 Coil controls Coil mechanical measurements
150 mm steps, 15 m  100 measuremens /coil ! Electrical tests Insulation to ground Quench heaters Coil dimensional measurements ? MQXF, 11T : 1 week

18 Magnet assembly It covers: Coil pack assembly
8 Coils assembly  4 poles, 2 apertures Assembly of the structure around the coil pack Insertion of the coil pack inside the structure modules Bladder & keys insertion Structure modulus (laminations, Al shells) pre-assembled 1 m long modules NbTi splices Splices between coils Warm field measurements needed at each steps Aperture Magnet We will consider 2 weeks, 1 shift for full rate production

19 Magnet assembly - tools
Assembly tables Coil dimensional measurement tools, Fuji paper, .. Bladders Warm field measurements bench

20 Cold mass assembly It covers:
Precise positioning of the two halves of the helium vessel Longitudinal welding of the two halves Assembly of end coves Orbital welding of covers Busbars Spool pieces Cold mass finishing Leak tests Warm field measurements on cold mass We will consider 4 weeks, 2 shifts, 2 people/operation Industrial best offer for welding the two halves : 5 magnet/week, 2 shifts, 1 press

21 Cold mass assembly - tools
Laser tracker Welding press Walding posts Leak tests bench Warm field measurements bench

22 Man power 1/2 Technical man power
Working in 2 shifts seems reasonable in term of costs 3 shifts is well more expensive Process step Shifts Time needed (WEEKS) Nb of Operators Work Hours Qualification Operations/magnet Tot hours/magnet Coil Winding 1 2 160 Mechanical/Winding 8 1280 Coil Heat treatment 3 0.1 24 Non skilled worker 192 Internal Splices (HF, if any) 2/coil Mechanical Transfert, Coil instrumentation, end splices Mechanical/Electrical Coil Impregnation 80 Mechanical/chemist 640 Coil tests 40 Electrical/Mechanical 320 Coil pack Assembly 120 240 Structure assembly Cold mass assembly and finishing 4 14 weeks 1344 4712 3.5 months

23 Man power 2/2 Production engineering : around 4/company; 1 every 50 workers Foreman : 1 every 10 workers 1 Engineers for Components inspection 2 Engineers for Quality Assurance 1 Administrative Estimations (max 2 shifts) 70€/hour Technicien 110 €/hour Engineers 48 weeks/year 40 hours a week

24 Next steps Consolidate assembly steps/man power table
Estimate tools cost Contact Rosario Principe for production flow charts exemples Edit a first furnace specification; Friedrich Lackner could discuss with GERO or other firms to evaluate feasability and cost of a large furnace


Download ppt "FCC 16 T dipole 4578 dipoles + 5 % spares : 4807 dipole magnets"

Similar presentations


Ads by Google