1 ERMC/RMM activities May 2017
15th May 2017

2 Tooling design Tooling code Tooling name Designer Status
Drawings available ERMC 10 Winding tool N.Peray Production - ERMC 20 Reaction tool ERMC 30 Splicing tool J.Osieleniec 3D on-going End of May ERMC 40 Impregnation tool ERMC 50 Rotating tool J.Massard July ERMC60 GI forming tool ERMC 70 Coil-pack insertion table 3D done, 2D on-going ERMC 80 Axial loading system June ERMC 90 Connection box tooling August EMC 100 Lifting tool 2D done

3 Magnet design ERMC coil RMM coil Structure
Cable being CGP. Expected delivery Coil components fabrication launched. Expected delivery July Trace design will start on W20. First prototype expected by September RMM coil Pole design to be completed. Reaction and impregnation test to be performed Structure Shell: price inquiry for raw material on-going Yoke, pad: drawings ready to launch procurement End-plates, rods: order of raw material, design to be completed with connection box Connection box: not yet started

4 Order of priority Jeremie: Jakub Insertion table Axial loading system
Rotating tool Ground insulation tooling Jakub Splicing tool RMM pole QH and vtaps Connection box with end-plate and tooling Coils lifting tools

5 ERMC components & tooling design
Jakub Osieleniec

6 ERMC Splicing tooling design

7 Required tooling : Clamping tool – cable clamping during splicing operation Tinning tool – Tinning operation to stabilise the cable before splicing Cutting tool – Cutting the tinned cable to the required length Splicing tool – Connection of Nb3Sn and NbTi cables Design status: CAD models for clamping, tinning and cutting ready What has to be done: CAD models for splicing Drawings for all processes components Modification of the reaction mold base for splicing tool clamping

8 Clamping tool

9 Tinning tool

10 Cutting tool

11 Other components status:
ERMC coil components: manufacturing in progress Magnet Structure: yoke, pads, shells drawings signed and ready to launch the fabrication Coil pack lifting system: manufacturing drawings completed Impregnation mold: manufacturing in progress Reaction mold: manufacturing in progress (except HFMMHERT0014 – base plate; some modification needed to accommodate the splice tooling) Material order for ERMC End Plate (Nitronic 50) is done; final design of the end plate to be completed including the connection box design

12 What next… Splicing tooling drawings to be completed
Traces design: Quench heater, voltage taps & Spot-heaters Connection Box + End Plate design to be completed Study of RMM central post sealing during impregnation

13 ERMC Introduction table

14 Requirements : Compatibility with: Be able to support 8 tons max
- RMC Magnet: L820, Ø570 - ERMC Magnet: L1240, Ø800 - ERMC Magnet with graded coils: L1435.6, Ø800 Be able to support 8 tons max  Possibility to set up the distance between the coil-pack and the shell Repeatability of the magnet position Keep the first table as base and modify this Adapted for bladders extraction Be able to do axial loading Be able to do azimuthal loading Be able to mount/dismount bladders Be able to mount end-plates on ERMC magnet

15 Solutions : compatibility
Position 1: ERMC graded coils Position 2: ERMC Position 3: RMC

16 Solutions : Position Repeatability: Pin to insure the correct position on the lower table “Grenouillère” to clamp the upper table in different positions

17 Solutions : Bladders extraction
Upper table removed In work during bladders extraction, with end-plates and rods

18 Solutions : Adaptable 2 positions for each ERMC magnet
Adaptable with the old RMC support

19 Solutions : Position -Threaded pins with screws and nuts mechanism for height set up -Spherical end in conical hole for repeatability

20 Solutions Side friction block

21 Solutions 2 positions for needle bearings Guide set up

22 Planning Parts drawings completed – 18/05
Assembly drawings completed – 22/05 Drawings checking – 24/05