PIP Shutdown Status 9/17/2014. RIL/Linac Jobs L1 Transformer ◦Rigging complete ◦Electrical work started ◦Turn on this coming weekend Laser notcher flange.

Slides:



Advertisements
Similar presentations
July 01, Shutdown Machine Status:  NTF Treatments and Dosimetry as scheduled  Proton Source Commissioning and Studies RFQ Injector.
Advertisements

KICKOFF AS PRESENTED 6/17/11, SEE THIS WEEKS SCHEDULE FOP THE LATEST UPDATE Shutdown Shutdown ‘11.
All Experimenters’ Meeting January 09, Accelerator Operation Summary Calendar Week # 51 NuMI Weekly Integrated Intensity 8.81E18 protons BNB Weekly.
A. Bross MTA RF WS August 22, Welcome MTA RF Workshop.
Proton Source Task Shutdown 2014 RFQ Injection Linac Tank 1 to 2 emmittance probe and Collimator NTF Beam Line Repair 400 MeV Turbo Station Replacement.
Scientific Goals: V. Litvinenko’s RHIC retreat talk Commissioning Goals: I. Pinayev presentation last week Run 14 Goals: Complete assembly of 112 MHz SCRF.
NOvA meeting PIP Update W. Pellico. PIP Goals and Scope (Provided in 2011 – Directorate S. H. / DOE Talk ) Goals: Specific to the issues surrounding the.
PIP Update July Agenda Summary Update – Budget/RLS – Current Activities – Upcoming Activities/ Changes Update Slides High-Power Ferrite TestingDennis.
PIP Update June 25 th Agenda Summary Update – Current Activities/Updates – Ryan Crawford: Anode Supply Update – Peter Prieto: BPM Update – CY Tan:
PIP Update Linac Utilities for 2014 shutdown Matthew Gardner, 4/23/14.
ANU Shutdown Status AEM meeting Cons Gattuso 6/3/2012.
LHC Machine Status Report Roberto Saban LHCC June 4 th 2014.
Proton Improvement Plan (FY13 PMG Q4). William Pellico, Fermilab PMG, Nov PIP FY13 Q4 Summary Task Highlights Budget and Labor Review Summary.
PIP Update April 30 th Agenda Summary Update – Current Activities/Updates – Nathan Eddy – Booster Longitudinal Damper.
PIP Update Aug 6 th Agenda Summary Update – Current Activities/Updates – New Tuner Test Result: Reid & Slabaugh – Anode Supplies: Crawford.
Proton Improvement Plan Bob Zwaska August 3, 2015 All-Experimenters Meeting.
1 LEReC Funded! From: Fedotov, Alexei Sent: Thursday, May 14, :04 PM Subject: LEReC project approved Dear All, FYI. The LEReC project is now formally.
PIP Update Feb 20 th Agenda Summary Update – Current Activities/Updates – Startup Schedule Highlights – Upcoming Talks, Reports, Meetings Updates/Talks:
Proton Improvement Plan (FY13 PMG Q1). William Pellico, Fermilab PMG, January FY13 Summary Q1 Task Summary – Highlights RFQ Injector Budget.
All Experimenters Meeting PIP Report William Pellico on behalf of PIP team 4/7/2013.
PIP Update Feb 11 th Agenda Summary Update – Current Activities – Updates (Tom Kubicki) – Additional Meetings/Notes.
09/28/07Shutdown’07 Week 8 F.G. Garcia1 MTA beam line installation Weekly Report September 28, 2007 Period covered: September 24 th September 28 th (Week.
August 05, Startup 2013 Machine Status:  Proton Source Commissioning and Studies RFQ Injector Line (RIL) Linac Booster  Main Injector Startup.
PIP Update Jan Agenda Summary Update – Current Activities – Updates (Ken, Pat and John) – Additional Meetings/Notes.
Proton Improvement Plan Bob Zwaska July 7, 2014 All-Experimenters Meeting.
PIP Update Dec. 4th Agenda Summary Update – Current Activities/Updates – Recent PIP News – Upcoming Talks, Reports, Meetings Updates/Talks: Trevor.
PIP Update June 3 rd Agenda Summary Update – Current Activities – Updates Ken Domann – Budget & Schedule Ryan Crawford – Anode Supply Update – Additional.
PIP FY14 PMG W. Pellico 7/8/14 7/8/2014PIP PMG. PIP Activities RIL & Linac – 200MHz RF Power System High Level RF Linac Modulator 7835 Procurement – Accelerator.
 A brief history of time  In the years BC.  My years at CERN  Current position  What is a Technical Coordinator?  The different type of intervention.
2015 Shutdown Joe Compton 3/11/2015. RIL PIP Work  Install operational laser notcher  5 days  Dave Johnson & Todd Johnson.
Accelerator and NuMI Upgrades Shutdown Update Cons Gattuso July 02, 2012 July 2, 2012 Cons Gattuso1.
Proton Improvement Plan Bob Zwaska January 7, 2013 All-Experimenters Meeting.
PIP Update Sept. 18 th Agenda Summary Update – Current Activities/Updates – Recent PIP News – Upcoming Talks, Reports, Meetings Updates/Talks: Pat.
PIP Update Dec. 4th Agenda Summary Update – Current Activities/Updates – Recent PIP News – Upcoming Talks, Reports, Meetings Updates/Talks: Ken.
08/31/07Shutdown’07 Week 4 F.G. Garcia1 MTA beam line installation Weekly Report August 31, 2007 Period covered: August 24 th to August 31 st (Week 4)
PIP FY15 PMG W. Pellico PIP PMG March 5 th PIP FY15 Year to Date Outline –FY15 activities PIP quarterly milestones Linac Booster Project Controls.
Booster Beam Notching Installation Update PIP Talk Salah Chaurize February 20, 2013.
Proton Improvement Plan Keith Gollwitzer January 5th, 2015 All Experimenters’ Meeting 11/5/2015Gollwitzer AEM.
PIP Update April 8 th Agenda Summary Update – Current Activities – Updates (V. Kapin: Booster Collimator) – Additional Meetings/Notes.
PIP Update April 8 th Agenda Summary Update – Current Activities – Updates (Joe Compton - shutdown) – Additional Meetings/Notes.
All Experimenters Meeting PIP Report Fernanda G. Garcia on behalf of PIP team 07/01/2013.
Proton Plan PMG 7/7/05 E Prebys 1 Proton Plan Status June Report Eric Prebys.
Substation L1/ Booster Substation Y-BE2 Update #3 August 15,2012.
Proton Plan PMG 9/27/07 E Prebys 1 Proton Plan Status Eric Prebys.
Proton Improvement Plan Bill Pellico April 19, 2013 NOvA collaboration Meeting Bill Pellico NOvA.
PIP Update June 17 th Agenda Summary Update – Current Activities – Updates (Alexander Valishev - Simplified Modeling of Space Charge Losses in Booster.
Booster Losses Keith Gollwitzer PIP and MI 700 kW review January 2015.
Proton Improvement Plan (FY13 PMG Q3). William Pellico, Fermilab PMG, Aug PIP FY13 Q3 Summary Task Highlights Budget and Labor Review Summary.
PIP Update Aug. 21 st Agenda Summary Update – Current Activities/Updates – Startup Plans – Upcoming Talks, Reports, Meetings Updates/Talks: B Pellico.
PIP Update Dec 17 th Agenda Summary Update – Current Activities – Updates – Additional Meetings/Notes.
Proton Plan PMG 10/13/05 E Prebys 1 Proton Plan Status September Report Eric Prebys.
Booster Shutdown Work - Week 4 Dump and Shielding installation completed Q805/Q806 re-installed, Septum in place Need to align quads and septum before.
July 15, 2013 Photo by Greg Vogel. Shutdown Machine Status:  Proton Source Commissioning and Studies RFQ Injector Line (RIL) Linac Booster.
PIP Update Jan. 16 th Agenda Summary Update – Current Activities/Updates – Shutdown ScheduleHighlights – Upcoming Talks, Reports, Meetings Updates/Talks:
PIP Update Oct 29 th Agenda Summary Update – Current Activities – Updates – Additional Meetings/Notes.
August 12, Machine Status: 2013  Proton Source Commissioning and Studies RFQ Injector Line (RIL) Linac : Roof hatch installed Booster : Magnet.
Proton Improvement Plan Bob Zwaska September 9, 2013 All-Experimenters Meeting.
PIP Update July 29 th Agenda Summary Update – Current Activities – Updates Tom Kubicki (Station 20,21,22 – Gallery and Equipment Work) – Additional.
PIP Update August 12 th Agenda Summary Update Current Activities Update – Ryan Crawford - Booster Anode Power Supplies – Dave Johnson - Laser Notcher.
Intensity Dependent Quad Ramps We know that in order to get the most intensity, the quad ramps must be tuned for a particular intensity. The way this is.
Proton PMG September 3 rd 2015 Cons Gattuso AD Shutdown Manager.
LEReC System 1. Project Schedule 2015 shutdown COMPETE! Move beam line equipment from IP 01:00 Install cooling section beam line 2016 shutdown Install.
Programme for the Physics Start-up Stable and radioactive beams Jose Alberto Rodriguez, BE-OP-PSB (167538)
Friday 5/1/ meeting. I wish to lock in the power outage onTuesday 5/5/09 at the end of the 0930 lab scheduling meeting speak now or :
PIP Update June 17 th Agenda Summary Update – Current Activities – Updates (Matt – Cavity Refurbishment) – Additional Meetings/Notes.
Work in the Tevatron A0 D0 B0 C0 E0 F0 Separators A49 Separator B48 TEL 2 installation A0 Xtal Collimator 1.5 m collimator A48 Shimming 6 magnets/day At.
Work in the Tevatron A0 D0 B0 C0 E0 F0 Separators A49 Separator B48 TEL 2 installation A0 Xtal Collimator 1.5 m collimator A48 Shimming 6 magnets/day At.
10/3/2014 Proton Source Update. RIL Update Source B is back in place and under vacuum It will be baked over the weekend It will be started early next.
All Experimenters Meeting PIP Report Fernanda G. Garcia on behalf of PIP team 10/06/2014.
Proton PMG May 7 th 2015 Cons Gattuso AD Shutdown Manager.
Presentation transcript:

PIP Shutdown Status 9/17/2014

RIL/Linac Jobs L1 Transformer ◦Rigging complete ◦Electrical work started ◦Turn on this coming weekend Laser notcher flange installed 25 cell test on LRF1 will not be performed this shutdown 400MeV vacuum to start after the NTF quad magnet replacement Dual temp system work to start soon

Booster Jobs Anode supply upgrade ◦Unlikely to occur this shutdown Cable pulls for new turbos is completed ◦May get a couple of new turbos installed New sector valve installation ◦Depends on other jobs New east/west yard transformers to be installed weekends of 9/27 & 10/4 S12 corrector & absorber work on schedule for later in the shutdown

Booster Jobs TLM shielding work ongoing ◦Most cables pulled except 7/8 inch heliax Kicker maintenance underway ◦Replace notcher long kickers to short kickers Cavity refurbishment underway ◦About two weeks out from next cavity change L1 corrector & NTF work may delay some jobs until next shutdown

RIL

L1 Transformer

Booster Notcher Kickers PS