10/3/2014 Proton Source Update. RIL Update Source B is back in place and under vacuum It will be baked over the weekend It will be started early next.

Similar presentations


Presentation on theme: "10/3/2014 Proton Source Update. RIL Update Source B is back in place and under vacuum It will be baked over the weekend It will be started early next."— Presentation transcript:

1 10/3/2014 Proton Source Update

2 RIL Update Source B is back in place and under vacuum It will be baked over the weekend It will be started early next week Should be stable when Linac requests beam the following week Source A assembly and installation next week Will be started next week Source gas valve calibration in progress Downloaded code to RFQ vacuum PLC to support new MBET vacuum valve

3 RIL Continued Running test stand source with new extractor pulser Fiber optic controls for one source being installed Need to establish communications Low power conditioning of Buncher & RFQ in progress Preps finished to install new solid state extractor switcher controller Install/terminate cabling

4 RIL Continued Next week Install source A after cleaning complete Start both sources Finish gas valve calibration Condition Buncher & RFQ Continue work on Extractor pulser Fiber optic controls Switch controller upgrade

5 Linac Update 400 MeV vacuum upgrade Under vacuum PLC work in progress NTF line re-installed and under vacuum Old target mounting found damaged -- Replaced QPS upgrade in progress Solid state upgrade in progress LCW maintenance complete except Water group rebuilding two Klystron LCW pumps General LE and HE station maintenance continues

6 Linac Continued Next week Dual temp system work will start Electrical work will start middle of next week Solid state upgrade testing continues QPS upgrade continues Continue with general station maintenance CDC testing

7 Booster Update LCW repairs continue Valves cracked open to verify leaks fixed Notcher kicker ceramic beam tube repairs in progress The TLM 7/8” cable pull has been completed Installation has been completed Thermistor cable pulls completed Thanks to Dave Augustine for finding extra RG-108 cable Replaced IP22A HV cable end and cable-to-pump HV adapter can Center conductor interface was scorched

8 Booster Continued RF maintenance continued Booster west gallery transformer replaced last weekend Booster east gallery transformer replacement has been cancelled for this Saturday Parts need to be ordered for installation Will be installed next shutdown L12 corrector work starting Removed old corrector cables from penetration BP16-P14 Penetration needed for future BRF20 cables

9 Booster Continued Next week Next BRF cavity should be ready for installation L12 corrector work continues Dual temp system work starts Electrical work will start midweek RF maintenance continues LCW work continues S12 corrector and absorber work Start sealing penetrations TLM work continues Booster enclosure cleaning