EARNED VALUE MANAGEMENT & ORACLE PRIMAVERA P6 TREY MILLER, MBA, PMP ORACLE PRIMAVERA P6 EPPM CERTIFIED IMPLEMENTATION SPECIALIST GLOBAL PROJECT MANAGEMENT,

Slides:



Advertisements
Similar presentations
Project Cost Management
Advertisements

Connoizor Enabling Performance for Businesses through Software Website: Contact:
Presenter: Sohel Akhter, PMP, CCNA,ISMS
Budget Management. 57 Budget Management Budget Development Good scheduling skills and abilities Understanding of the project scope Well developed WBS.
 Costs are planned, measured, analyzed and controlled in terms of project activities.  Expenditure for any activity is incurred evenly over the duration.
1 Earned Value Management a tool for project Portfolio management Jim Strong DLMP PMO Director.
Earned Value Management (EVM) Reference Card EVM Terminology ACWPActual Cost of Work Performed (Actual cost incurred for work accomplished during a given.
Monitoring and Control Earned Value Management (EVM)
Project Cost Management Sections of this presentation were adapted from A Guide to the Project Management Body of Knowledge 4 th Edition, Project Management.
CSSE Oct.2008 Monitoring and reporting project status Chapter 10, pages
Chapter 10: Monitoring and Controlling Change
Degree and Graduation Seminar Cost Management
Earned Value Project Management: a powerful tool for software projects
Project Monitoring and Control. Introduction Goal: ensuring that the project is on time and on budget and/or highlight any deviation from the plan Areas.
Project Evaluation and Control
Project Management Process Project Description Team Mission/ Assignment Major Milestones Boundaries Team Identification Measures of Success Roles & Responsibilities.
IIPM1 TIPS AND TECHNIQUES FOR PMP EXAM Tip # 1. Tense Verification - Verify the TENSE of the question before answering. International Institute of Project.
Project Evaluation and Control
Project Evaluation and Control
Project Management 6e..
CPM-400: xxx Lesson B: EV Data Analysis I Instructor Ellen Udell
EARNED VALUE MANAGEMENT SYSTEM A Project Performance Tool
Earned Value Analysis by John Cornman. Introduction “Earned Value Analysis” is an industry standard way to measure a project’s progress, forecast its.
Project Management Methodology Project monitoring and control.
Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall13-1 Project Evaluation and Control Project Termination and Closeout Chapter
1. Earned Value Analysis (EVA) Earned value is a measure of progress enables us to assess the “percent of completeness” of a project using quantitative.
Conducted By: Dr. Madhu Fernando, PMP, DBA, MEng. MGT PROJECT MANAGEMENT LESSON 5 AND 6: PROJECT PLANNING – TIME AND COST PLANNING AND MANAGEMENT.
Software Project Management (SPM)
EARNED VALUE MANAGEMENT (EVM)
Earned Value Management System (EVMS). Given: –total budget of $100,000 –12 month effort –produce 20 units Status: –spent to date: $64,000 –time elapsed:
10/19/ :26 AM 1 Project Cost Control. 10/19/ :26 AM 2  Controlling involves making sure that the results achieved are in line with the planned.
Earned Value SOS section Sp8Jan24ev3. Earned Value Analysis One approach to measuring progress in a software project is to calculate how much.
Project Management Part 6 Project Control. Part 6 - Project Control2 Topic Outline: Project Control Project control steps Measuring and monitoring system.
Mohawk Vehicle - MEGA HERZ ELEC & VEN - MOH-2 F C-0050 J:\CS40\Data Analysis\- Standard Analysis Package/Sample Standard Analysis Package.
Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall13-1 Project Evaluation and Control Chapter 13.
Earned Value Management (EVM) Reference Card EVM Terminology ACWPActual Cost of Work Performed (Actual cost incurred for work accomplished during a given.
UU Master Class Earned Value 17 July Earned Value Contents What is Earned Value / Earned Value Analysis Why and where is it used A brief history.
Introduction To Earned Value November 14, Definition Earned Value is a method for measuring project performance. It compares the amount of work.
Earned Value Analysis Tracking Project Progress. Introduction | Components | Project Scenario | Values | Calculations | Forecasts | Summary l What Is.
1 Earned value analysis Planned value (PV) or Budgeted cost of work scheduled (BCWS) – original estimate of the effort/cost to complete a task (compare.
PMP Study Guide Chapter 11: Controlling Work Results.
Presented by Niyi Ladipo September 14,  Results of the Survey  What is Earned Value Management (EVM)?  EVM vs. Traditional Cost Management 
EVM – Do You Really Know What the Numbers Mean? Booz | Allen |Hamilton Seth Huckabee EVP, PMP, PMI-SP.
1 Understanding Earned Value in Under an Hour Breakout Session # A11 Name: Wayne Brantley, MS Ed, PMP, ITIL Senior Director of Professional Education.
EARNED VALUE  Earned Value Management Systems  Earned Value Analysis.
0 Earned Value Management. 1  What is it?  Where did it come from?  What’s so special about it?  How do you do it?  What is an EVMS?
Schedule Control (Earned Value)
October 11, EARNED VALUE AND PERFORMANCE MANAGEMENT.
Agenda ‒ Cost Management ‒ Cost Budgeting ‒ Cost Control Learning Goals 1.Cost Control 2.Earned Value Management.
Project Management 1 Project Control. Project Management 2 Topics Project Control Status Reporting Earned Value Analysis.
Earned Value Management
Project Cost Management
Project Management Earned Value Management Demonstration
Performance Measurement Baseline Contract Price (Project Price)
“PMP® Exam Prep” Earned Value Management
TOPIC-8B- PROJECT COST CONTROL
CHAPTER:7 Project Cost Management
Earned Value Management
Performance Measurement Baseline Contract Price (Project Price)
Earned Value Management & Oracle Primavera P6
An introduction to Earned Value Management Simplex project management Education|Training|Mentoring|Coaching|Consulting.
Progress and Performance Measurement and Evaluation
Earned Value Management
An Introduction to Earned Value Performance Measurement
Earned Value Measures Planned Value (PV) Earned Value (EV)
فرآيند كنترل پروژه.
Project Evaluation and Control
Project Cost Management
Managing Project Work, Scope, Schedules, and Cost
Project Evaluation and Control
Presentation transcript:

EARNED VALUE MANAGEMENT & ORACLE PRIMAVERA P6 TREY MILLER, MBA, PMP ORACLE PRIMAVERA P6 EPPM CERTIFIED IMPLEMENTATION SPECIALIST GLOBAL PROJECT MANAGEMENT, LLC 3090 GAUSE BOULEVARD, NO. 614 SLIDELL, LA TEL:

GLOBAL PROJECT MANAGEMENT, LLC  Based in Slidell, LA  Project consulting, training, and staffing since 1996  PMI Global Registered Education Provider  Partner / reseller of:  Oracle  Hard Dollar  View Point 1

GLOBAL PROJECT MANAGEMENT, LLC  Consulting:  Consulting: Scheduling & Cost Controls  Staffing:  Staffing: Schedulers, PMs, Planners, Estimators, and project support personnel.  Training:  Oracle Primavera Products: Primavera P6, Contract Manager, Contractor, Risk Analysis, P3, and SureTrak  PMP® and CAPM® Certification  Project Management and Scheduling Fundamentals  Earned Value Management 2

WHAT IS EARNED VALUE MANAGEMENT?  Earned Value Management (EVM) is a project management technique for measuring project performance and progress.  A systematic approach to the integration and measurement of cost, schedule, and scope on a project. 3

EVM IN HISTORY  1960s – DoD adopted it as an objective measure of project progress.  1970s – Continued use in DoD as a means to offset cost and schedule risk in cost reimbursable contracts.  1990s – Policy moved Earned Value into all federal agencies 4

5

EARNED VALUE MANAGEMENT  Terminology Differences  Three data points  Actual Costs  Planned Value  Earned Value 6

ACTUAL COST (AC)  Primavera P6: “Actual Cost”  Cumulative  Graph: ACWP 7

PLANNED VALUE (PV)  Primavera P6: “Planned Value Cost”  Budget at Completion X Planned % Complete  Graph: BCWS 8

EARNED VALUE (EV) 9  Primavera P6: “Earned Value Cost”  Budget at Completion X % Complete  “Completed Work Value”  Graph: BCWP

BUDGET AT COMPLETION (BAC)  Primavera P6: “Budgeted Total Cost”  PV at end of project 10

COST VARIANCE ABBREVIATED CV Over / Under budget? CV = EV – AC Results?? Negative Number Positive Number 11 AC c EV

COST PERFORMANCE INDEX (CPI) CPI = EV / AC 12

ESTIMATE AT COMPLETION (EAC)  The expected total cost of a project when the project work will be completed.  AKA: Forecast At Completion  EAC = BAC / CPI 13 EV

TO COMPLETE PERFORMANCE INDEX 14  TCPI is an index showing the efficiency at which the resources on the project should be utilized for the remainder of the project.  Remaining Work / Funds Remaining  TCPI = (BAC – EV) / (BAC – AC)

ORACLE PRIMAVERA P Grady Booch

USING P6 FOR EVM 16 A few considerations…  Understand EVM  Percent complete type?  Customize the layout

CREATING THE LAYOUT 17

COST LOADED SCHEDULE & UPDATE IT! What is the Earned Value for activity A1020? 18

EARNED VALUE CALCULATIONS So, what is the TCPI? 19

THANK YOU! TREY MILLER, MBA, PMP ORACLE PRIMAVERA P6 EPPM CERTIFIED IMPLEMENTATION SPECIALIST GLOBAL PROJECT MANAGEMENT, LLC 3090 GAUSE BOULEVARD, NO. 614 SLIDELL, LA TEL: